Job No.: TCS00881/18 & TCS00944/18

 

 

 

 

 

 

 

 

 

Site Formation and Associated Infrastructural Works for Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge Cemetery

 

 

 

 

 

 

 

 

 

Monthly Environmental Monitoring and Audit Report (No.54) ¡V January 2023

 

 

 

 

 

 

 

 

Prepared For

 

 

 

 

Hsin Chong Tsun Yip Joint Venture &

Sang Hing Civil Contractors Co., Ltd

 

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

14 February 2023

TCS00881/18/600/R0714v2

Nicola Hon

(Environmental Consultant)

Tam Tak Wing

(Environmental Team Leader)

 

Version

Date

Remarks

1

9 February 2023

First Submission

2

14 February 2023

Amended according to the IEC¡¦s comment

 

 

 

 

 

 

 


 

 

 

 

 

 

executive summary

ES.01.        This is the 54th Monthly Environmental Monitoring and Audit (EM&A) Report summarizing the monitoring results and inspection findings under the Project for the period from 1st to 31st January 2023 (the Reporting Month).

 

Environmental Monitoring and Audit Activities

ES.02.        In the Reporting Month, the major construction works under the Project included Contract CV/2016/10 (hereinafter named ¡§Contract 1¡¨) and Contract CV/2017/02 (hereinafter named ¡§Contract 2¡¨).  Environmental monitoring activities under the EM&A programme in this Reporting Month are summarized in the following table.

Table ES-1        Summary of EM&A Programme in the Reporting Month¡@

Issues

Environmental Monitoring Parameters / Inspection

Monitoring Locations

Total Occasions/ dates

CV/2016/10

CV/2017/02

Air Quality

1-hour TSP

ASR-1

ASR-2

ASR-3

54

24-hour TSP

15

Construction Noise

Leq (30min) Daytime

CN-1

CN-2

CN-3

CN-4

20

Water Quality

In-situ measurement and Water sampling

M3

M1, M2 and M4

12

Ecology

Sensitive Habitat

Transect within site area of CV/2016/10

Transect within site area of CV/2017/02

10th Jan 2023

Landscape & Visual

Site Inspection

Site area of CV/2016/10

Site area of CV/2017/02

31st Jan 2023

Inspection & Audit

Environmental Team (ET)  Regular Environmental Site Inspection

Site area of CV/2016/10

Site area of CV/2017/02

4

Independent Environmental Checker (IEC) Monthly Environmental Site Audit

1

 

Breach of Action and Limit (A/L) Levels

ES.03.        In the Reporting Month, no exceedance of air quality and water quality monitoring was recorded.  No noise complaint (which triggered Action Level) was received and Limit Level exceedance for noise monitoring exceedance was recorded. The statistics of environmental exceedance, Notification and investigation of exceedance are summarized in the following table.

Table ES-2        Breach of Action and Limit (A/L) Levels in the Reporting Month

Environmental Issues

Monitoring Parameters

Action Level

Limit Level

Event & Action

Investigation Findings

Corrective Actions

Air Quality

1-hour TSP

0

0

-

-

24-hour TSP

0

0

-

-

Construction Noise

Leq30min Daytime

0

0

-

-

Water Quality

DO

0

0

-

-

Turbidity

0

0

-

-

Suspended Solids (SS)

0

0

 

 

ES.04.        Monthly ecological monitoring for sensitive habitat for area of Contract 1 and Contract 2 were undertaken on 10th January 2023.  After analysing survey results in January from 2019 to 2023, there was no significant drop in species richness and abundance for wetland and non-wetland habitat for area of both Contract 1 and 2. Yet, good site practice during construction, with reference to EM&A Manual, is required to prevent or alleviate environmental impacts.  For instance, the size of work areas should be minimized and disturbed areas should be reinstated immediately after completion of construction works. In addition, implementing proper waste disposal is necessary to reduce contamination to water and soil. Continuous monitoring is also recommended to inspect any significant decrease in species diversity.

 

ES.05.        There was no precautionary check for the presence of nesting birds conducted outside the concerned breeding season (February to July).

                                                                                                                             

ES.06.        Landscape and visual inspection at both Contracts were undertaken on 31st January 2023.  The Contractor was reminded to prevent the construction material pile within Tree Protection Zone and ensure no works is allowed within the TPZ.

 

ENVIRONMENTAL COMPLAINT

ES.07.        No environmental summons or successful prosecution was recorded in this Reporting Month.  The statistics of summons or successful prosecutions are summarized in the following tables.

Table ES-3        Environmental Complaint Summaries in the Reporting Month

Reporting Month

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

1st ¡V 31st January 2023

Contract 1

0

2

(1) Air Quality

(1) Noise

Contract 2

0

5

(1) Water

(2) Air Quality

(1) Noise

(1) soil/ muddy water

 

Notification of Summons and Successful Prosecutions

ES.08.        No environmental summons or successful prosecution was recorded in this Reporting Month.  The statistics of summons or successful prosecutions are summarized in the following tables.

Table ES-4        Environmental Summons Summaries in the Reporting Month

Reporting Month

Environmental Summons Statistics

Frequency

Cumulative

Summons Nature

1st ¡V 31st January 2023

Contract 1

0

0

NA

Contract 2

0

0

NA

 

Table ES-5        Environmental Prosecution Summaries in the Reporting Month

Reporting Month

Environmental Prosecution Statistics

Frequency

Cumulative

Prosecution Nature

1st ¡V 31st January 2023

Contract 1

0

0

NA

Contract 2

0

0

NA

 

ES.09.        In addition, no complaint and emergency event relating to violation of environmental legislation for illegal dumping and landfilling was received. 

 

Reporting Change

ES.010.    No reporting change was made in the Reporting Month.

 

Site Inspection

ES.011.    In the Reporting Month, joint site inspections for Contract 1 to evaluate the site environmental performance were carried out by the Resident Engineer, ET and the Contractor of the Contract 1 on     5th, 12th, 19th and 27th January 2023.  Moreover, joint site inspections for Contract 2 by the RE, ET and the Contractor of Contract 2 were carried out on  5th, 12th, 19th and 27th January 2023.  IEC attended joint site inspection for both Contracts on 19th January 2023.  No non-compliance was noted during the site inspections.

 

 

Future Key Issues

ES.012.    During dry season, the Contractors are reminded to pay special attention on the air quality mitigation measures such as wheel wash facilities, watering of haul roads, loose soil construction surface and covering of dusty materials with tarpaulin sheet should be implemented as far as practicable.

 

ES.013.    Water quality mitigation measures as recommended in the EM&A Manual should be fully implemented, in particular to prevent surface runoff and other pollutants from flowing to local stream and Conservation Area.  

 

ES.014.    Construction noise would be a key environmental issue during construction phase of the Project.  Noise mitigation measures such as using quiet plants and mobile noise barriers should be implemented in accordance with the EM&A requirement.

 


 

Table of Contents

1.      Introduction   1

1.1                 Project Background   1

1.2                 Report Structure  2

2.     Project Organization and Construction progress  4

2.1                 Construction Contract Packaging   4

2.2                 Construction Progress  4

2.3                 Summary of Environmental Submissions  4

2.4                 Summary of Submission Under the Environmental Permit Requirements  5

3.     Summary of Impact Monitoring Requirement  7

3.1                 General  7

3.2                 Monitoring Parameters  7

3.3                 Monitoring Locations  7

3.4                 Monitoring Frequency and Period   9

3.5                 Monitoring Equipment  9

3.6                 Equipment Calibration   12

3.7                 Data Management and Data QA/QC Control  12

3.8                 Determination of Action/Limit (A/L) Levels  12

4.     Air Quality   14

4.1                 Monitoring Results  14

4.2                 Air Monitoring Exceedance  14

5.     Construction Noise  15

5.1                 Monitoring Results  15

5.2                 Noise Monitoring Exceedance  15

6.     Water Quality   16

6.1                 Monitoring Results  16

6.2                 Water Quality Monitoring Exceedance  17

7.     Ecology Monitoring   18

7.1                 Requirement  18

7.2                 Methodology   18

7.3                 Ecological Monitoring Survey Findings (Contract 1) 19

7.4                 Ecological Monitoring Survey Findings (Contract 2) 21

7.5                 Monitoring of Flora Species of Conservation Interest  22

7.6                 Measure for Protection of Nesting Bird   22

8.     Landscape and Visual  23

8.1                 Requirement  23

8.2                 Findings / Deficiencies During Site Inspection in the Reporting Month   23

9.     Waste Management  24

9.1                 General Waste Management  24

9.2                 Records of Waste Quantities  24

10.   Site Inspection   25

10.1              Requirement  25

10.2              Findings / Deficiencies During Site Inspection in the Reporting Month   25

11.   Environmental Complaint and Non-Compliance  26

11.1              Environmental Complaint, Summons and Prosecution   26

12.   Implementation Status of Mitigation Measures  27

12.1              General Requirements  27

12.2              Tentative Construction Activities in the Coming Month   28

12.3              Key Issues for the Coming Month   28

13.   Conclusions and Recommentations  30

13.1              Conclusions  30

13.2              Recommendations  30

 


List of TABLES

Table 2-1        Status of Environmental Licenses and Permits for Contract 1

Table 2-2        Status of Environmental Licenses and Permits for Contract 2

Table 2-3        Status of Submission as under FEP for Contract 1

Table 2-4        Status of Submission as under FEP for Contract 2

Table 3-1        Summary of EM&A Requirements

Table 3-2        Designated Air Quality Monitoring Location under the Project

Table 3-3        Designated Construction Noise Monitoring Location under the Project

Table 3-4        Designated Water Quality Monitoring Stations under the Project

Table 3-5        Air Quality Monitoring Equipment

Table 3-6        Noise Monitoring Equipment

Table 3-7        Water Quality Monitoring Equipment

Table 3-8        Action and Limit Levels for Air Quality Monitoring

Table 3-9        Action and Limit Levels for Construction Noise

Table 3-10      Action and Limit Levels for Water Quality

Table 4-1        Summary of Air Quality Monitoring Results at ASR-1 under Contract 1

Table 4-2        Summary of Air Quality Monitoring Results at ASR-2 under Contract 2

Table 4-3        Summary of Air Quality Monitoring Results at ASR-3a under Contract 2

Table 5-1        Summary of Construction Noise Monitoring Results under Contract 1

Table 5-2        Summary of Construction Noise Monitoring Results under Contract 2

Table 6-1        Summary of Water Quality Monitoring Results ¡V M3 under Contract 1

Table 6-2        Summary of Water Quality Monitoring Results (M1, M2 and M4) under Contract 2

Table 6-3        Summary of Field Measurements for Water Quality

Table 6-4        Action and Limit (A/L) Levels Exceedance Record

Table 6-5        Summary of Investigation of Water Quality Exceedance in the Reporting Month

Table 7-1        Action and Limit Levels for Wet Woodland Habitats Monitoring

Table 7-2        Action and Limit Levels for Non-Wet Woodland Habitats Monitoring

Table 7-3        Schedule of Faunal Surveys in each year During Construction Phase

Table 7-4        Result of Faunal Survey under Contract 1

Table 7-5        Result of Freshwater Communities Survey under Contract 1

Table 7-6        Result of Faunal Survey under Contract 2

Table 7-7        Result of Freshwater Communities Survey under Contract 2

Table 8-1        Landscape & Visual Inspection Finding for Contract 1

Table 8-2        Landscape & Visual Inspection Finding for Contract 2

Table 9-1        Summary of Quantities of Inert C&D Materials

Table 9-2        Summary of Quantities of C&D Wastes

Table 10-1      Site Observations for the Works of Contract 1

Table 10-2      Site Observations for the Works of Contract 2

Table 11-1      Statistical Summary of Environmental Complaints

Table 11-2      Statistical Summary of Environmental Summons

Table 11-3      Statistical Summary of Environmental Prosecution

Table 12-1      Environmental Mitigation Measures

Table 12-2      Work Undertaken and Mitigation Measures for Contract 1

Table 12-3      Work Undertaken and Mitigation Measures for Contract 2

 

List of Appendices

Appendix A    Layout Plan of the Project

Appendix B    Organization Structure and Contact Details of Relevant Parties

Appendix C    Three Months rolling Programme

Appendix D    Designated Monitoring Locations

Appendix E    Calibration Certificates of MONITORING EQUIPMENT and Laboratory Certificate

Appendix F     Event and Action Plan of Air Quality, Noise and Water Quality

Appendix G    Monitoring Schedules of the Reporting Month and Coming Month

Appendix H    Monitoring Data of 24-Hour TSP Air Quality, Noise and Water Quality

Appendix I     Graphical Plots of Air Quality, Noise and Water Quality

Appendix J     Meteorological Data of the Reporting Month

Appendix K    Ecological Survey Report

Appendix L    Landscape & Visual Inspection Checklist

Appendix M   Monthly Summary Waste Flow Table

Appendix N    Complaint Log

Appendix O    Implementation Schedule for Environmental Mitigation Measures (ISEMM)

Appendix P     Illustrations of Site Activities

 

 

                                              

                                              


1.      Introduction

1.1              Project Background

1.1.1        Civil Engineering and Development Department (CEDD) is the Project Proponent for the Project ¡§Site Formation and Associated Infrastructural Works for Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge Cemetery¡¨.  The Project is a Designated Project to be implemented under Environmental Permit No. EP-534/2017/A and FEP-01/534/2017/A.  The layout plan of the Project is shown in Appendix A.  Major works to be executed under the Project shall include to the following:

Designated Works under EP-534/2017/A

(i)        Site formation of about 5.5 hectares of land and associated drainage, sewerage and landscape works for development of Columbarium and Crematorium facilities at the Sandy Ridge Cemetery;

(ii)      Construction of a new road (about 800m) connecting the Crematorium and Man Kam To Road and the pick-up/drop-off point at Man Kam To Road;

(iii)    Widening two sections of the existing Sha Ling Road (about 900m and 500m respectively);

(iv)    Widening of about 1.4km of the existing Lin Ma Hang Road; and

(v)      Improvement works to the existing barging point at Siu Lam (the barging point is rejected by Tuen Mun DC and no improvement works required)

 

Designated Works under FEP-01/534/2017/A

(i)        Site formation works for a formed platform of about 1.8 hectares and associated drainage, sewerage and landscape works for development of Columbarium at the Sandy Ridge Cemetery;

(ii)      Construction of the pick-up/drop-off point at Man Kam To Road;

(iii)    Widening of 900m of the existing Sha Ling Road;

(iv)    Improvement works to the existing barging point at Siu Lam (the barging point is rejected by Tuen Mun DC and no improvement works required)

 

1.1.2        To facilitate the Project management, the Project works were separated into three Contracts to be executed which are described in below sub-sections.

 

1.1.3        Contract No. CV/2016/10 ¡V Site Formation and Associated Infrastructural Works for Development of Columbarium at Sandy Ridge Cemetery (hereinafter named ¡§Contract 1¡¨):-

Ÿ   Site formation of about 1.77 ha of land for the proposed pick-up and drop-off area for shuttle bus operation;

Ÿ   Upgrading of a section of 900m existing Sha Ling Road from 3m wide carriageway to 7.3m wide carriageway with footpath at both sides;

Ÿ   Construction of one EVA with a total length of about 160m;

Ÿ   Construction of noise barriers along Sha Ling Road;

Ÿ   Modification of junction between Man Kam To Road and Sha Ling Road;

Ÿ   Construction of a new pick up / drop off point at Man Kam To Road;

Ÿ   Relocation and construction of a new refuse collection point near junction between Man Kam To Road and Sha Ling Road;

Ÿ   Associated geotechnical works including cut and fill slopes, soil nailing works and retaining structures;

Ÿ   Associated drainage, sewerage and waterworks along Sha Ling Road; and

Ÿ   Associated landscaping works.

 

1.1.4        Contract No. CV/2017/02 ¡V Infrastructural Works at Man Kam To Road and Lin Ma Hang Road for Development of Columbarium at Sandy Ridge Cemetery (hereinafter named ¡§Contract 2¡¨):-

Ÿ   Construction of a new road connecting Columbarium site to Crematorium site;

Ÿ   Construction of one EVA with a total length of about 300m;

Ÿ   Widening of a section of 1.4 km long Lin Ma Hang Road (between Man Kam To Road and Ping Yuen River) from 6m wide carriageway to 7.3m with 2m width footpath on both sides;

Ÿ   Provision of a pair of lay-by at Lin Ma Hang Road;

Ÿ   Construction of a new vehicular access connecting the Sheung Shui Landmark North PTI and Lung Sum Avenue;

Ÿ   Construction of covered walkway along Fanling Station Road;

Ÿ   Removal of planters and central divider along Fanling Station Road and San Wan Road;

Ÿ   Associated drainage, sewerage, waterworks and utility works along Man Kam To Road and Lin Ma Hang Road;

Ÿ   Associated geotechnical works including cut and fill slopes, soil nailing works and retaining structures; and

Ÿ   Associated landscaping works.

 

1.1.5        CEDD Contract No. (to be confirmed):-

Ÿ   Site Formation for the platform of the columbarium site;

Ÿ   Construction of two 2 at-grade access roads;

Ÿ   Construction of road junction between Man Kam To Road and the new access road;

Ÿ   Associated drainage, sewerage and waterworks along the two new access roads;

Ÿ   Associated geotechnical works including cut and fill slopes, soil nailing works and retaining structures; and

Ÿ   Associated landscaping works

 

1.1.6        Hsin Chong Tsun Yip Joint Venture (hereafter referred as ¡§HCTYJV¡¨) has been awarded Contract 1 on 5 December 2017.  According to the Contract requirement, HCTYJV shall take over the responsibility for part of the Environmental Permit No. EP-534/2017 for ease of management, therefore application for Further Environmental Permit was submitted by HCTYJV to EPD on 26 January 2018 and Further Environmental Permit No. FEP-01/534/2017 was granted to HCTYJV by EPD on 23 February 2018.  Furthermore, EPD issued Environmental Permit No. FEP-01/534/2017/A on 24 December 2018.

 

1.1.7        Sang Hing Civil Contractors Company Limited (hereinafter referred as ¡§Sang Hing¡¨) was awarded Contract 2 on 23 May 2018. The Contract Works is a Designated Project as under Environmental Permit (EP) No. EP-534/2017.  Furthermore, EPD issued Environmental Permit No. EP-534/2017/A on 24 December 2018.

 

1.1.8        Action-United Environmental Services & Consulting (AUES) has been commissioned by the Contractors as an Environmental Team (ET) to implement the Environmental Monitoring and Audit (EM&A) programme in accordance with the approved EM&A Manual as well as the associated duties.  As part of the EM&A programme, baseline monitoring to determine the ambient environmental conditions was completed before construction work commencement.  The Baseline Monitoring Report (air, noise and water) certified by ET Leader (ETL) and verified by Independent Environmental Checker (IEC) was submitted to Environmental Protection Department (EPD) and it was approved by EPD on 25 October 2018.

 

1.1.9        Major construction work of Contract 1 and Contract 2 was commenced on 16 August 2018 and 5 November 2018 respectively.

 

1.1.10    This is the 54th Monthly EM&A Report summarizing the monitoring results and inspection findings for the period from 1st to 31st January 2023.

 

1.2              Report Structure

1.2.1        The Monthly EM&A Report is structured into the following sections:-

Section 1       Introduction

Section 2       Project Organization and Construction Progress

Section 3       Summary of Monitoring Requirements

Section 4       Air Quality Monitoring Results

Section 5       Noise Monitoring Results

Section 6       Water Quality Monitoring Results

Section 7       Ecology Monitoring Results

Section 8       Landscape & Visual

Section 9       Waste Management

Section 10     Site Inspections

Section 11     Environmental Complaints and Non-Compliance

Section 12     Implementation Status of Mitigation Measures

Section 13     Conclusions and Recommendation


2.      Project Organization and Construction progress

2.1              Construction Contract Packaging

2.1.1        To facilitate the project management and implementation, the Project was divided by the following contracts:

Ÿ   Contract 1 (Contract No. CV/2016/10)

Ÿ   Contract 2 (Contract No. CV/2017/02)

Ÿ   Contract 3 (Contract No. TBA)

 

2.1.2        Organization structure and contact details of relevant parties with respect to on-site environmental management are shown in Appendix B.

 

2.2              Construction Progress

2.2.1        The three-month rolling construction programme for Contract 1 and Contract 2 are enclosed in Appendix C.  Construction activities of the Contract 1 and Contract 2 undertaken in the Reporting Month are presented below.

 

Contract 1 (CV/2016/10)

Ÿ    Installation of Type 2 railing and street lighting

Ÿ   Paving block installation works

Ÿ   Compaction work at footpath

Ÿ   Laying bitumen works

 

Contract 2 (CV/2017/02)

Ÿ   Construction of footpath at Lin Ma Hang Road

Ÿ   Watermain pipe and sewer installation at Man Kam To Road North Slow Lane

Ÿ   Construction of road works at Sandy Ridge

 

2.3              Summary of Environmental Submissions

2.3.1        Summary of the relevant permits, licenses, and/or notifications on environmental protection for the Project in this Reporting Month is presented in Tables 2-1 and 2-2.

Table 2-1        Status of Environmental Licenses and Permits for Contract 1

Item

Description

License/ Permit ref no.

License/ Permit Status

1

Air Pollution Control (Construction Dust) Regulation

Ref. no. 428909

Acknowledged by EPD on 20/12/2017

Valid

2

Chemical waste Producer Registration

WPN: 5231-641-H3937-01

Issued by EPD on 27/03/2018

Valid

3

Water Pollution Control Ordinance

License no. WT00030795-2018

Issued date: 9/5/2018

Expire Date: 31/5/2023

Valid

4

Billing Account for Disposal of Construction Waste

Account no.: 7029769

Valid

Table 2-2        Status of Environmental Licenses and Permits for Contract 2

Item

Description

License/ Permit ref no.

License/ Permit  Status

1

Air Pollution Control (Construction Dust) Regulation

Ref. no. 440406

Acknowledged by EPD on 14/12/2018

Man Kam To Road (near Sha Ling Road to Kong Nga Po Road

Valid

Ref. no. 440405

Acknowledged by EPD on 14/12/2018

Fanling Station Road

Valid

Ref. no. 440404

Acknowledged by EPD on 14/12/2018

Sa Ling Road (Sandy Ridge Cemetery)

Valid

Ref. no. 440401

Acknowledged by EPD on 14/12/2018

Lin Ma Hang Road (San Uk Ling ¡V Muk Wu Nga Yiu)

Valid

Ref. no. 440402

Acknowledged by EPD on 14/12/2018

Lung Sum Avenue (near Landmark North)

Valid

2

Chemical waste Producer Registration

WPN: 5213-641-S4151-01

Issued by EPD on 04/02/2019

Valid

3

Water Pollution Control Ordinance

License no: WT00032936-2018

Issued date: 16/01/2019

Expire Date: 31/01/2024

Man Kam To Road & Lin Ma Hang Road, Man Kam To

Valid

License no: WT00033335-2019

Issued date: 29/03/2019

Expire Date: 31/03/2024

Columbarium at Sandy Ridge Cemetery

Valid

License no:

WT00034717-2019

Issued date: 9/10/2019

Expire Date: 31/10/2024

Fanling Station Road

Valid

4

Billing Account for Disposal of Construction Waste

Account no.: 7031098

Valid

 

2.4              Summary of Submission Under the Environmental Permit Requirements

2.4.1        Tables 2-3 to 2-4 summarized the submission status under the EP and/or FEP stipulation in the Reporting Month.

Table 2-3        Status of Submission as under FEP

Item

EP and / or FEP Stipulation

Description

Status

1

Condition 2.10 of FEP

Management organization of : i) the main construction companies; ii) ET; and iii) IEC and the supporting team

Submitted and no approval is required.

2

Condition 2.11 of FEP

i) Detailed phasing programme of all construction works; and ii) Location plan of all construction works

Submitted and no approval is required.

3

Condition 2.12 of FEP

Contamination Assessment Plan (CAP)

Approved by EPD on 27 May 2019

4

Condition 2.13 of FEP

Grassland Reinstatement Plan

Pending approval

5

Condition 2.14 to 2.16 of FEP

Vegetation Survey Report and Vegetation Transplantation Proposal for Contract 1

Approved by EPD on 12 October 2018

6

Condition 2.17 of FEP

Woodland Compensation Plan (Rev.05)

Approved by EPD on 30 Jun 2020

7

Condition 2.18 of FEP

Monitoring and Survey Plan for Golden-headed Cisticola for Contract 1 (Rev.02)

Approved by EPD on 22 Oct 2019

8

Condition 2.20 of FEP

Landscape & Visual Mitigation and Tree Preservation Plan(s) Contract 1 (Rev.04)

Pending approval

9

Condition 2.22 of FEP

Traffic Noise Mitigation Plan Contract 1 (Rev. 4)

Pending approval

10

Condition 3.3 of the FEP

Baseline Monitoring Report (Air, Noise and Water)

Approved by EPD on 25 October 2018

11

Condition 4.2 of the FEP

The Contract Internet website

Internet website address has notified EPD on 15 Jun 2018 and no approval is required.

 

Table 2-4        Status of Submission as under EP

Item

EP and / or FEP Stipulation

Description

Status

1

Condition 2.10 of EP

Management organization of : i) the main construction companies; ii) ET; and iii) IEC and the supporting team

Submitted and no approval is required.

2

Condition 2.11 of EP

i) Detailed phasing programme of all construction works; and ii) Location plan of all construction works

Submitted and no approval is required.

3

Condition 2.12 of EP

Layout Plan for the proposed footpath at Lin Ma Hang Road

Approved by EPD on 25 April 2022

4

Condition 2.13 of EP

Contamination Assessment Plan (CAP)

Approved by EPD on 27 May 2019

5

Condition 2.14 of EP

Grassland Reinstatement Plan 

Pending approval

6

Condition 2.15 to 2.17 of EP

Vegetation Survey Report and Vegetation Transplantation Proposal under Contract 2

Approved by EPD on 15 June 2022

7

Condition 2.18 of EP

Woodland Compensation Plan (Rev.05)

Approved by EPD on 30 Jun 2020

8

Condition 2.19 of EP

Monitoring and Survey Plan for Golden-headed Cisticola Contract 2

Approved by EPD on 9 Nov 2022

9

Condition 2.21 ¡V 2.22 of EP

Landscape & Visual Mitigation and Tree Preservation Plan(s) Contract 2

Pending approval

10

Condition 2.23 of EP

Traffic Noise Mitigation Plan Contract 2

Pending approval

11

Condition 3.3 of the EP

Baseline Monitoring Report (Air, Noise and Water)

Approved by EPD on 25 October 2018

12

Condition 4.2 of the EP

The Contract Internet website

Internet website address has notified EPD on 15 June 2018 and no approval is required.


3.      Summary of Impact Monitoring Requirement

3.1              General

3.1.1        The EM&A requirements are set out in the Approved EM&A Manual. Environmental issues such as air quality, construction noise, water quality and ecology were identified as the key issues during the construction phase of the Project.

 

3.1.2        A summary of construction phase EM&A requirements are presented in the sub-sections below.

 

3.2              Monitoring Parameters

3.2.1        The EM&A impact monitoring shall cover the following environmental aspect:

            Air quality;

            Construction noise;

            Water quality;

            Ecology; and

            Landscape and visual

 

3.2.2        A summary of the monitoring parameters is presented in Table 3-1 below

Table 3-1        Summary of EM&A Requirements

Environmental Issue

Parameters

Air Quality

Ÿ  1-hour TSP;

Ÿ  24-hour TSP

Noise

Ÿ  Leq(30min) during normal working hours.; and

Ÿ  Leq(15min) during the construction works undertaken in Restricted Hours

Water Quality

In-situ Measurements

Ÿ  Dissolved Oxygen Concentration (mg/L) & Saturation (% );

Ÿ  Temperature (¢J);

Ÿ  Turbidity (NTU);

Ÿ  Salinity (ppm)

Ÿ  pH unit;

Ÿ  Water depth (m); and

Ÿ  Stream Flow Velocity (m/sec).

Laboratory Analysis

Ÿ  Suspended Solids (mg/L)

Ecology

 Ecologically sensitive habitats (wetland habitats and non-wetland habitats)

 

3.3              Monitoring Locations

3.3.1        According to the Approved EM&A Manual of the Project ¡V Site Formation and Associated Infrastructural Works for Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge Cemetery, the designated monitoring locations for air quality, noise, water quality and ecology under the monitoring programme, is shown in Appendix D.

 

3.3.2        Since the Project was divided into three Works Contracts and all Contracts will be commenced at different time, the construction phase impact monitoring will only be performed at the Contract-related monitoring stations upon commencement of each Contract Works.

 

Air Quality

3.3.3        There were three (3) designated air quality monitoring stations recommended in the Approved EM&A Manual Section 5.6.1.1.  There was proposed relocation of air quality monitoring location ASR-3 in October 2018 since the landlord refused to set up the HVS at his premises and nearby Conservation Area due to noise nuisance and Muk Wu Nga Yiu House No. 2A was proposed as alternative location ASR-3a.  The proposal dated on 9 November 2018 which verified by IEC was submitted to EPD for approval.  Based on rationale in Section 3.3.2, the Contract-related air quality monitoring location for construction phase were summarized in Table 3-2 and illustrated in Appendix D.


Table 3-2        Designated Air Quality Monitoring Location under the Project

Location ID

Description in EM&A Manual

Location

Related Work Contract

ASR-1

Village House along Man Kam To Road

Sha Ling Village House No.6

Contract 1

ASR-2

Village House at San Uk Ling

San Uk Ling Village House No.1

Contract 2

ASR-3

Village House at Muk Wu Nga Yiu

Muk Wu Nga Yiu House No.28

Contract 2

ASR-3a (#)

Village House at Muk Wu Nga Yiu

Muk Wu Nga Yiu House No.2A

Contract 2

                 Remark: (#) There was proposed relocation of air quality monitoring location ASR-3 in October 2018. The proposal dated on 9 November 2018 after verified by IEC was submitted to EPD for approval.

 

3.3.4        If the designated monitoring location is required to relocate, alternative monitoring location shall agree with IEC and seek for EPD approval which shall meet the following criteria:

i)               Be at the site boundary or such locations close to the major dust emission source;

ii)             Close to the sensitive receptors;

iii)           Take into account the prevailing meteorological conditions;

iv)           For monitoring location located in the vicinity of the ASRs, care shall be taken to cause minimal disturbance to the occupants during monitoring.

v)             When positioning the HVS, the following points shall be noted:

a.         a horizontal platform with appropriate support to secure the samples against gusty wind shall be provided;

b.        no two samplers shall be placed less than 2m apart;

c.         the distance between the HVS and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the HVS;

d.        a minimum of 2 m separation from walls, parapets and penthouses is required for HVS at the rooftop;

e.         a minimum of 2 m separation from any supporting structure, measures horizontally is required;

f.         no furnace or incinerator flue is nearby;

g.         airflow around the sampler is unrestricted;

h.        the HVS is more than 20 m from the dripline;

i.          any wire fence and gate to protect the HVS, shall not cause any obstruction during monitoring;

j.          permission must be obtained to set up the HVS and to obtain access to the monitoring stations; and

k.        a secured supply of electricity is needed to operate the HVS.

 

Construction Noise

3.3.5        There were four (4) designated noise monitoring locations recommended in the Approved EM&A Manual Section 6.5.1.1.  Based on rationale in Section 3.3.2, the Contract-related noise quality monitoring location for construction phase were summarized in Table 3-3 and illustrated in Appendix D.

Table 3-3        Designated Construction Noise Monitoring Location under the Project

Location ID

Description in EM&A Manual

Location

Related Work Contract

CN-1

Village house to the west of Sha Ling Road

Village house to the west of Sha Ling Road (free field condition)

Contract 1

CN-2

Village house to the north of Man Kam To Road

Sha Ling Village House No. 25 (free field condition)

Contract 1 & 3

CN-3

Village house near San Uk Ling

San Uk Ling Village House No. 18 (free field condition)

Contract 2

CN-4

Village house of Muk Wu

Muk Wu Village House No. 267 (1m façade from the building)

Contract 2

 

 

Water Quality

3.3.6        There were four (4) water quality monitoring locations recommended in the Approved EM&A Manual Section 7.6.1.2.  The locations and coordinates of water quality monitoring were listed in Table 3-4.  Based on rationale in Section 3.3.2, the Contract-related water quality monitoring location for construction phase were summarized in Table 3-4 and illustrated in Appendix D.

Table 3-4        Designated Water Quality Monitoring Stations under the Project

Proposed Location ID

Co-ordinates

Description

Related Work Contract

North

East

M1

843 431

831 308

Midstream of Nam Hang Stream

Contract 2

M2

843 840

831 101

Downstream of Nam Hang Stream

Contract 2

M3

843 509

830 040

Wetland in the Conservation Area near Yuen Leng Chai

Contract 1

M4

843 997

831 783

Watercourse across Lin Ma Hang Road, running from east of San Uk Ling to Man Kam To Boundary Control Point

Contract 2

 

3.4              Monitoring Frequency and Period

3.4.1        The requirements of impact monitoring were stipulated in Sections 5.8.1.1, 6.7.1.1 and 7.8.1.4 of the approved EM&A Manual and presented as follows.

 

Air Quality Monitoring

3.4.2        Monitoring frequency for air quality impact monitoring is as follows:

Ÿ   1-Hour TSP

3 sets of 1-hour TSP monitoring shall be carried out once every six days during construction periods

Ÿ   24-Hour TSP

24-hour TSP monitoring shall be carried out every six days during construction periods

 

Noise Monitoring

3.4.3        Noise impact monitoring shall be carried out once per week during construction periods.  The noise measurement for the time period between 0700 and 1900 hours shall be measured in terms of Leq (30 minutes) or 6 sets of Leq (5mins).

 

Water Quality Monitoring

3.4.4        The monitoring frequency shall be 3 days per week during construction phase and the interval between two sets of monitoring shall not be less than 36 hours.

 

3.5              Monitoring Equipment

3.5.1        The monitoring equipment using for the EM&A program as proposed by the ET shall be verified by the IEC.

Air Quality Monitoring

3.5.2        The 24-hour and 1-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.  If ET proposes to use a direct reading dust meter to measure 1-hour TSP levels, it shall submit sufficient information to IEC for approval.

 

3.5.3        The filter paper of 24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.

 

3.5.4        All equipment used by ET for air quality monitoring is listed in Table 3-5.

Table 3-5        Air Quality Monitoring Equipment

Equipment

Model

24-hour TSP

High Volume Air Sampler (HVAS)

TISCH High Volume Air Sampler, HVS Model TE-5170

Calibration Kit

TISCH Model TE-5025A

1-Hour TSP

Portable Dust Meter

Laser Dust Monitor, Model AM510

/ Sibata LD-3 Laser Dust monitor Particle Mass Profiler & Counter

 

Wind Data Monitoring Equipment

3.5.5        According to the approved EM&A Manual, wind data monitoring equipment shall also be provided and set up for logging wind speed and wind direction near the dust monitoring locations.  The equipment installation location shall be proposed by the ET and agreed with the IEC.  For installation and operation of wind data monitoring equipment, the following points shall be observed:

1)             The wind sensors should be installed 10 m above ground so that they are clear of obstructions or turbulence caused by buildings.

2)             The wind data should be captured by a data logger. The data shall be downloaded for analysis at least once a month.

3)             The wind data monitoring equipment should be re-calibrated at least once every six months.

4)             Wind direction should be divided into 16 sectors of 22.5 degrees each.

 

3.5.6        ET has liaised with the premises owners/ landlords to grant the permission for the HVS installation.  However, they rejected to set up wind data monitoring equipment installation in their premises.

 

3.5.7        Under this situation, the ET proposed to obtain representative wind data from the Hong Kong Observatory Ta Kwu Ling Weather Station.  Ta Kwu Ling Station is located near the Project site which situated at the sea level above 15mPD and the wind data monitoring equipment is installed 10 m above the existing ground.

 

Noise Monitoring

3.5.8        Sound level meter in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring.  The sound level meter shall be checked using an acoustic calibrator.  The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in ms-1 before each noise monitoring event.  Noise measurements should not be made in fog, rain, wind with a steady speed exceeding 5 m s-1 or wind with gusts exceeding 10 m s-1. 

 

3.5.9        Noise monitoring equipment used for impact monitoring is listed in Table 3-6.

Table 3-6        Noise Monitoring Equipment

Equipment

Model

Integrating Sound Level Meter

Rion NL-52 Sound Level Meter /Rion NL-31 Sound Level Meter

Calibrator

Rion NC-73 Acoustical Calibrator

Portable Wind Speed Indicator

Testo Anemometer

 

3.5.10    Sound level meters listed above comply with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications, as recommended in TM issued under the NCO.  

 

Water Quality Monitoring

3.5.11    Water quality parameters include dissolved oxygen, water temperature & depth, turbidity, salinity, pH and stream flow velocity shall be measured in-situ, and suspended solids shall be analyzed by a HOKLAS-accredited testing laboratory.

 

Dissolved Oxygen and Temperature Measurement

3.5.12    The dissolved oxygen (DO) measuring instruments should be portable and weatherproof. The equipment should also complete with cable and sensor, and DC power source. It should be capable of measuring:

       A DO level in the range of 0 ¡V 20 mg/L and 0 ¡V 200% saturation; and

       A temperature of 0 ¡V 45 degree Celsius.

 

3.5.13    The equipment should have a membrane electrode with automatic temperature compensation complete with a cable.

 

3.5.14    Should salinity compensation not be built-in to the DO equipment, in-situ salinity should be measured to calibrate the DO measuring instruments prior to each measurement.

 

Turbidity Measurement

3.5.15    The turbidity measuring instruments should be a portable and weatherproof with DC power source.  It should have a photoelectric sensor capable of measuring turbidity level between 0¡V1000 NTU (for example, Hach model 2100Q or an approved similar instrument).

 

Salinity Measurement

3.5.16    A portable salinometer capable of measuring salinity in the range of 0¡V40 parts per thousand (ppt) should be provided for measuring salinity of the water at each monitoring location.

 

pH Measurement

3.5.17    A portable pH meter capable of measuring a range between 0.0 and 14.0 should be provided to measure pH under the specified conditions accordingly to the APHA Standard Methods.

 

Water Depth Measurement

3.5.18    A portable, battery-operated echo sounder or an approved similar instrument should be used for water depths determination at each designated monitoring station.

 

Stream Flow Velocity Equipment

3.5.19    Since the EM&A Manuals do not specified instrument to use stream flow velocity measurement, the monitoring of stream flow velocity is therefore proposed to be conducted by using a flow probe which is a digital water velocity meter.

 

Water Sampling Equipment

3.5.20    A water sampler is required for suspended solid (SS) monitoring.  A water sampler e.g. Kahlsico Water Sampler, which is a transparent PVC cylinder with capacity not less than 2 litres, will be used for water sampling if water depth over than 0.5m.

 

3.5.21    For sampling from very shallow water depths e.g. <0.5 m, water sample will be collected from water surface below 100mm using plastic bottle to avoid inclusion of bottom sediment or humus.  Moreover, Teflon/stainless steel bailer or self-made sampling buckets maybe used for water sampling.  The equipment used for sampling will be depended the sampling location and depth situations.

 

Sample Containers and Storage

3.5.22    Water samples for suspended solid should be stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4¢XC without being frozen) and delivered to the laboratory within 24 hours of collection and be analyzed as soon as possible after collection.

 

3.5.23    Analysis of suspended solids should be carried out in a HOKLAS or other accredited laboratory. Water samples of about 1L should be collected at the monitoring stations for carrying out the laboratory suspended solids determination.  The SS determination work should start within 24 hours after collection of the water samples. The SS analyses should follow the APHA Standard Methods 2540D with Limit of Reporting of 2 mg/L.

 

3.5.24    Details of the equipment used for water quality monitoring are listed in Table 3-7 below.

 

Table 3-7        Water Quality Monitoring Equipment

Equipment

Model

Water Depth Detector

Tape measures

Water Sampler

A 2-litre transparent PVC cylinder with latex cups at both ends or Teflon/stainless steel bailer or self-made sampling bucket

Thermometer & DO meter

YSI Professional DSS

pH meter

YSI Professional DSS

Turbidimeter

YSI Professional DSS

Salinometer

YSI Professional DSS

Stream Flow Velocity

FP211 Global Flow Probe  

Sample Container

High density polythene bottles (provided by laboratory)

Storage Container

¡¥Willow¡¦ 33-litter plastic cool box with Ice pad

 

3.5.25    Furthermore, Suspended Solids (SS) analysis was carried out by ALS Technichem (HK) Pty Ltd. Which is one a local HOKLAS-accredited laboratory

 

3.6              Equipment Calibration

3.6.1        The HVAS is operated and calibrated on a regular basis in accordance with the manufacturer¡¦s instruction using Tisch Calibration Kit Model TE-5025A.  Calibration would carry out at fortnightly interval.  The calibration data are properly documented and the records are maintained by ET for future reference.  Furthermore, Tisch Calibration Kit will be calibrated by the manufacturer in yearly basis.

 

3.6.2        The 1-hour TSP meter calibrated by a local HOKLAS-accredited laboratory would be undertaken in yearly basis.  Zero response of the equipment was checked before and after each monitoring event.

 

3.6.3        The sound level meter and acoustic calibrator are calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme at yearly basis.

 

3.6.4        The multi-parameter Water Quality Monitoring System is calibrated by HOKLAS accredited laboratory of three month intervals.

 

3.6.5        All updated calibration certificates of the monitoring equipment used for the impact monitoring program in this Reporting Month are attached in Appendix E.

 

3.7              Data Management and Data QA/QC Control

3.7.1        The impact monitoring data are handled by the ET¡¦s systematic data recording and management, which complies with in-house Quality Management System. Standard Field Data Sheets (FDS) are used in the impact monitoring program.

 

3.7.2        The monitoring data recorded in the equipment e.g. 1-hour TSP meter, noise meter and Multi-parameter Water Quality Monitoring System are downloaded directly from the equipment at the end of each monitoring day.  The downloaded monitoring data are input into a computerized database properly maintained by the ET.  The laboratory results are input directly into the computerized database and QA/QC checked by personnel other than those who input the data.  For monitoring activities require laboratory analysis, the local laboratory follows the QA/QC requirements as set out under the HOKLAS scheme for all laboratory testing.

 

3.8              Determination of Action/Limit (A/L) Levels

3.8.1        The baseline monitoring results form the basis for determining the environmental acceptance criteria for the impact monitoring. The air quality, construction noise and water quality criteria, namely Action and Limit levels were established according to Approved EM&A Manual, and they are listed in Tables 3-8, 3-9 and 3-10 below.

Table 3-8        Action and Limit Levels for Air Quality Monitoring

Monitoring Station

Action Level (mg /m3)

Limit Level (mg/m3)

1-hour TSP

24-hour TSP

1-hour TSP

24-hour TSP

ASR-1

331

181

500

260

ASR-2

316

165

500

260

ASR-3

307

160

500

260

 

Table 3-9        Action and Limit Levels for Construction Noise

Monitoring Location

Action Level

Limit Level in dB(A)

Time Period: 0700-1900 hours on normal weekdays

CN-1,CN-2, CN-3, CN-4

When one or more documented complaints are received

75 dB(A)

Note:    *  Reduces to 70 dB(A) for schools and 65 dB(A) during the school examination periods.

 

Table 3-10      Action and Limit Levels for Water Quality

Parameter

Performance criteria

Monitoring Location

M1

M2

M3

M4

DO (mg/L)

Action Level

3.03

4.99

4.58

3.62

Limit Level

2.97

4.90

4.49

3.52

Turbidity (NTU)

Action Level

7.1

39.7

5.6

5.4

Limit Level

7.6

42.2

5.9

5.9