|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00881/18 & TCS00944/18 |
|
|
||
|
|
|
|
|
||
|
|
Site
Formation and Associated Infrastructural Works for Development of Columbarium,
Crematorium and Related Facilities at Sandy Ridge Cemetery |
|
|
||
|
|
|
|
|
||
|
|
Monthly
Environmental Monitoring and Audit Report (No.37) ¡V August 2021 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Hsin Chong Tsun Yip Joint Venture & Sang Hing Civil Contractors Co., Ltd |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
14 September 2021 |
TCS00881/18/600/R0571v2 |
|
|
Nicola Hon (Environmental Consultant) |
Tam Tak Wing (Environmental
Team Leader) |
Version |
Date |
Remarks |
1 |
9 September 2021 |
First Submission |
2 |
14 September 2021 |
Amended as Per IEC¡¦s comment |
|
|
|
|
|
|
executive summary
ES.01.
This
is the 37th Monthly Environmental
Monitoring and Audit (EM&A) Report summarizing the monitoring results and inspection findings under the
Project for the period from 1st to 31st August 2021 (the Reporting Month).
Environmental
Monitoring and Audit Activities
ES.02.
In the Reporting Month, the major construction works under the
Project included Contract CV/2016/10 (hereinafter named ¡§Contract 1¡¨) and Contract
CV/2017/02 (hereinafter named ¡§Contract 2¡¨). Environmental monitoring activities under the EM&A
programme in this Reporting Month are summarized in the following table.
Table ES-1 Summary of EM&A Programme
in the Reporting Month¡@
Issues |
Environmental Monitoring Parameters /
Inspection |
Monitoring Locations |
Total Occasions/ dates |
|
CV/2016/10 |
CV/2017/02 |
|||
Air
Quality |
1-hour
TSP |
ASR-1 |
ASR-2 ASR-3 |
54 |
24-hour TSP |
18 |
|||
Construction Noise |
Leq
(30min) Daytime |
CN-1 CN-2 |
CN-3 CN-4 |
15 |
Water
Quality |
In-situ
measurement and Water sampling |
M3 |
M1, M2 and M4 |
13 |
Ecology |
Sensitive Habitat |
Transect within site area of CV/2016/10 |
Transect within site area of CV/2017/02 |
10th Aug 2021 |
Landscape
& Visual |
Site Inspection |
Site area of CV/2016/10 |
Site area of CV/2017/02 |
26th Aug 2021 |
Inspection
& Audit |
Environmental
Team (ET) Regular
Environmental Site Inspection |
Site area of CV/2016/10 |
Site area of CV/2017/02 |
4 |
Independent
Environmental Checker (IEC) Monthly Environmental Site Audit |
1 |
Breach of Action and Limit
(A/L) Levels
ES.03.
In the Reporting Month, no exceedance of air quality,
noise monitoring was recorded. For
water quality monitoring, 32 Limit level non-project related
exceedances and no Action Level were recorded. The statistics of environmental exceedance, Notification
of Exceedance
(NOE) issued and
investigation of exceedance are summarized in the following table.
Table ES-2 Breach
of Action and Limit (A/L) Levels in the Reporting Month
Environmental Issues |
Monitoring Parameters |
Action Level |
Limit
Level |
Event & Action |
|
Investigation Findings |
Corrective Actions |
||||
Air
Quality |
1-hour TSP |
0 |
0 |
- |
- |
24-hour
TSP |
0 |
0 |
- |
- |
|
Construction Noise |
Leq30min
Daytime |
0 |
0 |
- |
- |
Water Quality |
DO |
0 |
0 |
- |
- |
Turbidity |
0 |
15 |
Not project
related |
N/A |
|
Suspended Solids (SS) |
0 |
17 |
Not project
related |
N/A |
Note: NOE ¡V
Notification of Exceedance
ES.04.
In the Reporting Month, 32
Limit level water quality exceedances, namely 15
exceedances
of turbidity
and 17 exceedances of SS were
recorded. According to the weather information from the HKO, there was heavy
rainstorm intermittently during the days of exceedance recorded. Under the impact of rainstorm, the water
quality of the watercourse was deteriorated by the stirred up sediment and
runoff from the surrounding environment.
It was concluded that the exceedances were likely
related to the impact of rainstorm and not caused by the work under the
project.
ES.05.
Monthly ecological monitoring for sensitive
habitat for area of Contract 1 and Contract 2 were undertaken on 10th
August 2021.
After analysing
survey results in August from 2018 to 2021, it is found that the species
diversity in Contract 1 reduced in
wetland habitat and the reduction could be due to natural
fluctuation. For Contract 2, there was a drop in species richness and abundance for non-wetland habitats. It could be due to natural fluctuation. It could be due to natural fluctuation. Good practice during construction is required to prevent
environmental contamination as well as unnecessary site clearance. Continuous
monitoring is also recommended to inspect any significant reduction in species diversity.
ES.06.
Landscape and visual inspection at
both Contracts were undertaken on 26th August 2021. The Contractor was reminded
to prevent the construction material pile within Tree Protection Zone and
ensure no works is allowed within the TPZ.
ENVIRONMENTAL COMPLAINT
ES.07.
No environmental
complaint was received in this Reporting Period.
Table ES-3 Environmental
Complaint Summaries in the Reporting Month
Reporting Month |
Environmental Complaint Statistics |
|||
Frequency |
Cumulative |
Complaint Nature |
||
1st ¡V 31st
August 2021 |
Contract 1 |
0 |
1 |
Air Quality |
Contract 2 |
0 |
2 |
Air Quality |
Notification of
Summons and Successful Prosecutions
ES.08.
No
environmental summons or successful prosecution was recorded in this Reporting Month. The statistics of summons or successful
prosecutions are summarized in the following tables.
Table ES-4 Environmental
Summons Summaries in the Reporting Month
Reporting Month |
Environmental Summons Statistics |
|||
Frequency |
Cumulative |
Summons Nature |
||
1st ¡V 31st
August 2021 |
Contract
1 |
0 |
0 |
NA |
Contract
2 |
0 |
0 |
NA |
Table ES-5 Environmental
Prosecution Summaries in the Reporting Month
Reporting Month |
Environmental Prosecution Statistics |
|||
Frequency |
Cumulative |
Prosecution Nature |
||
1st ¡V 31st
August 2021 |
Contract
1 |
0 |
0 |
NA |
Contract
2 |
0 |
0 |
NA |
ES.09.
In addition, no complaint and emergency event
relating to violation of environmental legislation for
illegal dumping and landfilling was received.
Reporting Change
ES.010.
No reporting change was made
in the Reporting Month.
Site Inspection
ES.011. In the Reporting Month, joint site inspections for Contract 1 to evaluate the site
environmental performance were carried out by the Resident
Engineer, ET and the Contractor of the
Contract 1 on 5th,
12th, 19th and 26th August 2021. Moreover, joint site inspections for Contract 2 by the RE, ET and the
Contractor of Contract 2 were carried out on 5th,
12th, 19th and 26th August 2021. IEC attended the both Contract joint site
inspection on 19th August 2021. No non-compliance was noted
during the site inspections.
ES.012. The Contractors are reminded to pay special attention on water quality mitigation measures and should fully implement the measures as recommended
in the EM&A Manual, in
particular to prevent surface runoff and other pollutants from flowing to local
stream and Conservation Area.
ES.013.
During wet season, the Contractors are reminded to pay special attention on water quality mitigation measures and should fully implement the measures as recommended
in the EM&A Manual, in
particular to prevent surface runoff and other pollutants from flowing to local
stream and Conservation Area.
ES.014.
Construction noise mitigation measures such as use
of movable noise barriers and Quality Powered Mechanical Equipment should be properly provided to reduce construction noise impact, where appropriate.
ES.015. The Contractors should
properly maintain the cleanliness
and tidiness
of the site. In addition, mosquito control should be
performed to prevent mosquito breeding on site.
Table of Contents
2. Project Organization
and Construction progress
2.1 Construction Contract Packaging
2.3 Summary of Environmental Submissions
2.4 Summary of Submission Under the Environmental Permit Requirements
3. Summary of
Impact Monitoring Requirement
3.4 Monitoring
Frequency and Period
3.7 Data
Management and Data QA/QC Control
3.8 Determination
of Action/Limit (A/L) Levels
5.2 Noise
Monitoring Exceedance
6.2 Water
Quality Monitoring Exceedance
7.3 Ecological
Monitoring Survey Findings (Contract
1)
7.4 Ecological
Monitoring Survey Findings (Contract
2)
7.5 Monitoring
of Flora Species of Conservation Interest
7.6 Measure
for Protection of Nesting Bird
8.2 Findings
/ Deficiencies During Site Inspection in the Reporting Month
9.2 Records
of Waste Quantities
10.2 Findings
/ Deficiencies During Site Inspection in the Reporting Month
11. Environmental Complaint and
Non-Compliance
11.1 Environmental
Complaint, Summons and Prosecution
12. Implementation Status of
Mitigation Measures
12.2 Tentative
Construction Activities in the Coming Month
12.3 Key
Issues for the Coming Month
13. Conclusions and
Recommentations
List of TABLES
Table 2-1 Status
of Environmental Licenses and Permits for Contract 1
Table 2-2 Status
of Environmental Licenses and Permits for Contract 2
Table 2-3 Status
of Submission as under FEP for Contract 1
Table 2-4 Status
of Submission as under FEP for Contract 2
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Designated
Air Quality Monitoring Location under the Project
Table 3-3 Designated
Construction Noise Monitoring Location under the Project
Table 3-4 Designated
Water Quality Monitoring Stations under the Project
Table 3-5 Air
Quality Monitoring Equipment
Table 3-6 Noise
Monitoring Equipment
Table 3-7 Water
Quality Monitoring Equipment
Table 3-8 Action
and Limit Levels for Air Quality Monitoring
Table 3-9 Action
and Limit Levels for Construction Noise
Table 3-10 Action and Limit
Levels for Water Quality
Table 4-1 Summary
of Air Quality Monitoring Results at ASR-1 under Contract 1
Table 4-2 Summary
of Air Quality Monitoring Results at ASR-2 under Contract 2
Table 4-3 Summary
of Air Quality Monitoring Results at ASR-3a under Contract 2
Table 5-1 Summary
of Construction Noise Monitoring Results under Contract 1
Table 5-2 Summary
of Construction Noise Monitoring Results under Contract 2
Table 6-1 Summary
of Water Quality Monitoring Results ¡V M3 under Contract 1
Table 6-2 Summary
of Water Quality Monitoring Results (M1, M2 and M4) under Contract 2
Table 6-3 Summary
of Field Measurements for Water Quality
Table 6-4 Action
and Limit (A/L) Levels Exceedance Record
Table 6-5 Summary
of Investigation of Water Quality Exceedance in the Reporting Month
Table 7-1 Action
and Limit Levels for Wet Woodland Habitats Monitoring
Table 7-2 Action
and Limit Levels for Non-Wet Woodland Habitats Monitoring
Table 7-3 Schedule
of Faunal Surveys in each year During Construction Phase
Table 7-4 Result
of Faunal Survey under Contract 1
Table 7-5 Result
of Freshwater Communities Survey under Contract 1
Table 7-6 Result
of Faunal Survey under Contract 2
Table 7-7 Result
of Freshwater Communities Survey under Contract 2
Table 8-1 Landscape
& Visual Inspection Finding for Contract 1
Table 8-2 Landscape
& Visual Inspection Finding for Contract 2
Table 9-1 Summary
of Quantities of Inert C&D Materials
Table 9-2 Summary
of Quantities of C&D Wastes
Table 10-1 Site Observations
for the Works of Contract 1
Table 10-2 Site Observations
for the Works of Contract 2
Table 11-1 Statistical
Summary of Environmental Complaints
Table 11-2 Statistical
Summary of Environmental Summons
Table 11-3 Statistical
Summary of Environmental Prosecution
Table 12-1 Environmental
Mitigation Measures
List
of Appendices
Appendix A Layout
Plan of the Project
Appendix B Organization
Structure and Contact Details of Relevant Parties
Appendix C Three
Months rolling Programme
Appendix D Designated
Monitoring Locations
Appendix E Calibration
Certificates of MONITORING EQUIPMENT and Laboratory Certificate
Appendix F Event
and Action Plan of Air Quality, Noise and Water Quality
Appendix G Monitoring
Schedules of the Reporting Month and Coming Month
Appendix H Monitoring
Data of 24-Hour TSP Air Quality, Noise and Water Quality
Appendix I Graphical
Plots of Air Quality, Noise and Water Quality
Appendix J Meteorological
Data of the Reporting Month
Appendix K Ecological
Survey Report
Appendix L Landscape
& Visual Inspection Checklist
Appendix M Monthly
Summary Waste Flow Table
Appendix N Implementation
Schedule for Environmental Mitigation Measures (ISEMM)
Appendix O Implementation
of Water Quality Mitigation Measures
1.1.1
Civil Engineering and Development
Department (CEDD) is the Project
Proponent for the Project
¡§Site Formation and Associated
Infrastructural Works for Development of Columbarium, Crematorium and Related
Facilities at Sandy Ridge Cemetery¡¨. The Project is a Designated Project to be implemented
under Environmental Permit No. EP-534/2017/A and FEP-01/534/2017/A. The layout plan of the Project is shown
in Appendix A. Major works to be executed under the Project shall include to the
following:
A Designated Works under EP-534/2017/A
(i)
Site formation of about 8 hectares of
land and associated drainage, sewerage and landscape works for development of
Columbarium and Crematorium facilities at the Sandy Ridge Cemetery;
(ii)
Construction of a new road (about 600m)
including a section of viaduct connecting the platform for Crematorium and Man
Kam To Road and the pick-up/drop-off point at Man Kam To Road;
(iii)
Widening of about 900m of the existing
Sha Ling Road;
(iv)
Widening of about 1.4km of the existing
Lin Ma Hang Road; and
(v)
Improvement works to the existing
barging point at Siu Lam
Non-Designated Works
(i)
Construction of a sewage detention tank
complete with odour and septicity control mechanism;
(ii)
Construction of noise barriers along Sha
Ling Road;
(iii)
Construction of a new Refuse Collection
Point (RCP) near the junction between Man Kam To Road and Sha Ling Road;
(iv)
Landscaping works (including both hard
and soft landscape works);
(v)
Associated tree felling, transplanting
and compensatory planting works;
(vi)
Associated street lighting, street
furniture and road marking, etc.; and
(vii) Other
works which are specified in PS of the Contract.
1.1.2
To facilitate
the Project management, the Project works were separated into three Contracts to be executed which
are described in below sub-sections.
1.1.3
Contract No. CV/2016/10 ¡V Site
Formation and Associated Infrastructural Works for Development of Columbarium
at Sandy Ridge Cemetery (hereinafter
named ¡§Contract 1¡¨):-
Site formation of about 1.77 ha of land for the proposed pick-up
and drop-off area for shuttle bus operation;
Upgrading of a section of 900m existing Sha Ling Road from 3m wide
carriageway to 7.3m wide carriageway with footpath at both sides;
Construction of one EVA with a total length of about 160m;
Construction of noise barriers along Sha Ling Road;
Modification of junction between Man Kam To Road and Sha Ling
Road;
Construction of a new pick up / drop off point at Man Kam To Road;
Relocation and construction of a new refuse collection point near
junction between Man Kam To Road and Sha Ling Road;
Associated geotechnical works including cut and fill slopes, soil
nailing works and retaining structures;
Associated drainage, sewerage and waterworks along Sha Ling Road;
and
Associated landscaping works.
1.1.4
Contract
No. CV/2017/02 ¡V Infrastructural Works at Man Kam To Road and Lin Ma Hang Road
for Development of Columbarium at Sandy Ridge Cemetery (hereinafter
named ¡§Contract 2¡¨):-
Construction of a new road connecting Columbarium site to
Crematorium site;
Construction of one EVA with a total length of about 300m;
Widening of a section of 1.4 km long Lin Ma Hang Road (between Man
Kam To Road and Ping Yuen River) from 6m wide carriageway to 7.3m with 2m width
footpath on both sides;
Provision of a pair of lay-by at Lin Ma Hang Road;
Construction of a new vehicular access connecting the Sheung Shui Landmark North PTI and Lung Sum Avenue;
Construction of covered walkway along Fanling Station Road;
Removal of planters and central divider along Fanling Station Road
and San Wan Road;
Associated drainage, sewerage, waterworks and utility works along
Man Kam To Road and Lin Ma Hang Road;
Associated geotechnical works including cut and fill slopes, soil
nailing works and retaining structures; and
Associated landscaping works.
1.1.5
CEDD
Contract No. (to be confirmed):-
Site Formation for the platform of the columbarium site;
Construction of two 2 at-grade access roads;
Construction of road junction between Man Kam To Road and the new
access road;
Associated drainage, sewerage and waterworks along the two new
access roads;
Associated geotechnical works including cut and fill slopes, soil
nailing works and retaining structures; and
Associated landscaping works
1.1.6
Hsin Chong Tsun Yip
Joint Venture (hereafter referred as ¡§HCTYJV¡¨) has been awarded Contract 1 on 5 December 2017. According to the
Contract requirement, HCTYJV shall take over the responsibility for part of the Environmental Permit No. EP-534/2017 for ease of management, therefore application for
Further Environmental Permit was submitted
by HCTYJV to
EPD on 26 January 2018 and
Further Environmental Permit No. FEP-01/534/2017 was granted to HCTYJV by EPD on 23 February 2018. Furthermore, EPD issued Environmental Permit No. FEP-01/534/2017/A
on 24 December 2018.
1.1.7
Sang Hing Civil Contractors Company Limited (hereinafter referred as ¡§Sang Hing¡¨) was awarded Contract 2 on
23 May 2018.
The Contract Works is a Designated Project as under Environmental Permit
(EP) No. EP-534/2017.
Furthermore, EPD issued Environmental
Permit No. EP-534/2017/A on
24 December 2018.
1.1.8
Action-United Environmental Services &
Consulting (AUES) has been commissioned by the Contractors as an
Environmental Team (ET) to implement the Environmental Monitoring
and Audit (EM&A) programme in
accordance with the approved EM&A Manual as well as the associated duties.
As part of
the EM&A programme, baseline monitoring to determine the ambient environmental
conditions was completed before construction work commencement. The Baseline Monitoring Report
(air, noise and water) certified by ET Leader (ETL) and verified by
Independent Environmental Checker (IEC) was submitted to Environmental
Protection Department (EPD) and it was approved by EPD on 25 October
2018.
1.1.9
Major construction work of Contract 1 and
Contract 2 was
commenced on 16 August 2018 and 5 November 2018 respectively.
1.1.10 This is the 37th Monthly EM&A Report summarizing the monitoring results and inspection findings for
the period
from 1st to 31st August 2021.
1.2.1
The
Monthly EM&A Report is
structured into the following sections:-
Section 1 Introduction
Section 2 Project Organization and Construction Progress
Section 3 Summary of Monitoring Requirements
Section 4 Air Quality Monitoring Results
Section 5 Noise Monitoring Results
Section 6 Water Quality Monitoring Results
Section 7 Ecology Monitoring Results
Section 8 Landscape & Visual
Section 9 Waste Management
Section 10 Site Inspections
Section 11 Environmental Complaints and Non-Compliance
Section 12 Implementation Status of Mitigation Measures
Section 13 Conclusions and Recommendation
2.1.1
To facilitate the project management and implementation, the
Project was divided
by the following contracts:
Contract
1 (Contract No.
CV/2016/10)
Contract
2 (Contract No.
CV/2017/02)
Contract
3 (Contract No. TBA)
2.1.2
Organization
structure and contact details of relevant parties with respect to on-site
environmental management are shown in Appendix B.
2.2.1
The
three-month rolling construction programme for Contract
1 and Contract 2 are enclosed
in Appendix C. Construction activities of the Contract 1 and Contract
2 undertaken in the Reporting Month are presented
below.
Contract 1
(CV/2016/10)
l General site housekeeping
l Bulk excavation
l Construction of
cut slope, installation of soil nailing and construction of surface channel and
planter wall
l Construction
of fill slope and surface channel
l Construction
of pick-up and drop-off Point near Man Kam To Road
l Construction
of storm/ sewer drain
l Laying
of street lighting ducts
l Laying
of watermains
l Construction
of Refuse Collection Point
l Construction
of Concrete Pavement
Contract
2 (CV/2017/02)
l Construction
of Manhole, gullies, drainage pipe at Lin Ma Hang Road between CH50-160 Southbound & CH780-890 Northbound
l Construction
of Jacking Pit for DN400 watermain by trenchless
method at Man Kam To Road
l DN400
DI Watermain works in approx. CH300-1040 at Man Kam
To Road North Slow Lane
l Construction
of Manhole, gullies, drainage pipe at Sandy Ridge Road E CH0-300 (~300m)
l Construction
of Manhole, gullies, drainage pipe at Sandy Ridge Road F CH640-730 (~80m)
l Construction
of Manhole, gullies, drainage pipe at Sandy Ridge Road F CH30-130 (~100m)
l Backfilling
of Retaining Wall 12
l Fanling
Station Road Covered Walkway
l Lung
Sum Avenue road surface modification works
2.3.1
Summary of the relevant permits, licenses,
and/or notifications on environmental protection for the Project in this Reporting
Month is presented in Tables 2-1 and 2-2.
Table
2-1 Status of Environmental Licenses and Permits for Contract 1
Item |
Description |
License/ Permit ref
no. |
License/ Permit Status |
1 |
Air
Pollution Control (Construction Dust) Regulation |
Ref. no. 428909 Acknowledged by EPD on 20/12/2017 |
Valid |
2 |
Chemical
waste Producer Registration |
WPN:
5231-641-H3937-01 Issued by EPD on 27/03/2018 |
Valid |
3 |
Water
Pollution Control Ordinance |
License no. WT00030795-2018 Issued
date: 9/5/2018 Expire
Date: 31/5/2023 |
Valid |
4 |
Billing
Account for Disposal of Construction Waste |
Account
no.:
7029769 |
Valid |
Table
2-2 Status of Environmental Licenses and Permits for Contract 2
Item |
Description |
License/ Permit ref
no. |
License/ Permit Status |
||
1 |
Air
Pollution Control (Construction Dust) Regulation |
Ref. no. 440406 Acknowledged by EPD on 14/12/2018 |
Man Kam To Road (near Sha Ling Road to Kong Nga
Po Road |
Valid |
|
Ref. no. 440405 Acknowledged by EPD on 14/12/2018 |
Fanling Station Road |
Valid |
|||
Ref. no. 440404 Acknowledged by EPD on 14/12/2018 |
Sa Ling Road (Sandy Ridge Cemetery) |
Valid |
|||
Ref. no. 440401 Acknowledged by EPD on 14/12/2018 |
Lin Ma Hang Road (San Uk
Ling ¡V Muk Wu Nga Yiu) |
Valid |
|||
Ref. no. 440402 Acknowledged by EPD on 14/12/2018 |
Lung Sum Avenue (near Landmark North) |
Valid |
|||
2 |
Chemical
waste Producer Registration |
WPN:
5213-641-S4151-01 Issued by EPD on 04/02/2019 |
Valid |
||
3 |
Water
Pollution Control Ordinance |
License no: WT00032936-2018 Issued date: 16/01/2019 Expire Date: 31/01/2024 |
Man Kam To Road & Lin Ma Hang Road, Man Kam
To |
Valid |
|
License no: WT00033335-2019 Issued date: 29/03/2019 Expire Date: 31/03/2024 |
Columbarium at Sandy Ridge Cemetery |
Valid |
|||
License no: WT00034717-2019 Issued date: 9/10/2019 Expire Date: 31/10/2024 |
Fanling Station Road |
Valid |
|||
4 |
Billing
Account for Disposal of Construction Waste |
Account
no.: 7031098 |
Valid |
||
5 |
Construction
Noise Permit |
GW-RN0226-21
(1
May 2021 ¡V 30 Oct 2021) |
Valid |
||
2.4.1
Tables 2-3 to 2-4 summarized the
submission status under the EP and/or FEP stipulation in the Reporting Month.
Table
2-3 Status of Submission as under FEP
Item |
EP and / or FEP
Stipulation |
Description |
Status |
1 |
Condition 2.10 of FEP |
Management
organization of : i) the main construction companies; ii) ET; and iii) IEC
and the supporting team |
Submitted and no approval is required. |
2 |
Condition 2.11 of FEP |
i) Detailed
phasing programme of all construction works; and ii) Location plan of all
construction works |
Submitted and no approval is required. |
3 |
Condition 2.12 of FEP |
Contamination
Assessment Plan (CAP) |
Approved
by EPD on 27 May 2019 |
4 |
Condition 2.13 of FEP |
Grassland
Reinstatement Plan |
Pending approval |
5 |
Condition 2.14 to 2.16 of FEP |
Vegetation Survey Report and Vegetation Transplantation Proposal for Contract
1 |
Approved by EPD on 12 October 2018 |
6 |
Condition 2.17 of FEP |
Woodland Compensation Plan (Rev.05) |
Approved by EPD on 30 Jun 2020 |
7 |
Condition 2.18 of FEP |
Monitoring and Survey Plan for
Golden-headed Cisticola for Contract 1 (Rev.02) |
Approved by EPD on 22 Oct 2019 |
8 |
Condition 2.20 of FEP |
Landscape & Visual
Mitigation and Tree Preservation Plan(s) Contract 1 (Rev.04) |
Pending approval |
9 |
Condition 2.22 of FEP |
Traffic Noise Mitigation Plan Contract 1 (Rev. 4) |
Pending approval |
10 |
Condition 3.3 of the
FEP |
Baseline Monitoring Report (Air, Noise
and Water) |
Approved by EPD on 25 October 2018 |
11 |
Condition 4.2 of the
FEP |
The Contract Internet
website |
Internet website address has notified
EPD on 15 Jun
2018 and no approval is required. |
Table
2-4 Status of Submission as under EP
Item |
EP and / or FEP
Stipulation |
Description |
Status |
1 |
Condition 2.10 of EP |
Management
organization of : i) the main construction companies; ii) ET; and iii) IEC
and the supporting team |
Submitted and no approval is required. |
2 |
Condition 2.11 of EP |
i) Detailed
phasing programme of all construction works; and ii) Location plan of all
construction works |
Submitted and no approval is required. |
3 |
Condition 2.12 of EP |
Layout Plan for the proposed footpath at
Lin Ma Hang Road |
Pending approval |
4 |
Condition 2.13 of EP |
Contamination
Assessment Plan (CAP) |
Approved
by EPD on 27 May 2019 |
5 |
Condition 2.14 of EP |
Grassland Reinstatement
Plan |
Pending approval |
6 |
Condition 2.15 to 2.17 of EP |
Vegetation Survey Report and Vegetation Transplantation Proposal under
Contract 2 |
Pending approval |
7 |
Condition 2.18 of EP |
Woodland Compensation Plan (Rev.05) |
Approved by EPD on 30 Jun 2020 |
8 |
Condition 2.19 of EP |
Monitoring and Survey Plan for
Golden-headed Cisticola Contract 2 |
Pending approval |
9 |
Condition 2.21 ¡V 2.22
of EP |
Landscape & Visual
Mitigation and Tree Preservation Plan(s) Contract 2 |
Pending approval |
10 |
Condition 2.23 of EP |
Traffic Noise Mitigation Plan Contract 2 |
Pending approval |
11 |
Condition 3.3 of the
EP |
Baseline Monitoring Report (Air, Noise
and Water) |
Approved by EPD on 25 October 2018 |
12 |
Condition 4.2 of the
EP |
The Contract
Internet website |
Internet website address has notified
EPD on 15 June 2018 and no approval is required. |
3.1.1
The EM&A requirements are set out in the Approved EM&A Manual.
Environmental issues such as air quality, construction noise, water quality and
ecology were identified as the key issues during the construction phase of the
Project.
3.1.2
A summary of construction phase EM&A
requirements are presented in the sub-sections below.
3.2.1
The EM&A impact monitoring shall cover the following
environmental aspect:
•
Air quality;
•
Construction noise;
•
Water quality;
•
Ecology; and
•
Landscape and visual
3.2.2
A summary of the monitoring parameters is presented in Table
3-1 below
Table 3-1 Summary
of EM&A Requirements
Environmental Issue |
Parameters |
Air Quality |
1-hour
TSP; 24-hour
TSP |
Noise |
Leq(30min) during normal working
hours.; and
Leq(15min) during the
construction works undertaken in Restricted Hours |
Water Quality |
In-situ Measurements Dissolved
Oxygen Concentration (mg/L) & Saturation (% ); Temperature
(¢J); Turbidity
(NTU); Salinity
(ppm) pH
unit; Water
depth (m); and Stream
Flow Velocity (m/sec). |
Laboratory Analysis Suspended
Solids (mg/L) |
|
Ecology |
Ecologically sensitive habitats
(wetland habitats and non-wetland habitats) |
3.3.1
According to the
Approved EM&A Manual of the Project ¡V Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge
Cemetery, the designated monitoring
locations for air quality, noise, water quality and ecology under the monitoring programme, is shown in Appendix D.
3.3.2
Since the Project was divided
into three Works Contracts and all Contracts will be
commenced at different time, the
construction phase impact monitoring will only be performed at the
Contract-related monitoring stations upon commencement of each
Contract Works.
Air Quality
3.3.3
There were three (3) designated
air quality monitoring
stations recommended in the Approved EM&A Manual
Section 5.6.1.1. There was proposed
relocation of air quality monitoring location ASR-3 in October 2018 since the
landlord refused to set up the HVS at his premises and nearby Conservation Area
due to noise nuisance and Muk Wu Nga Yiu House No. 2A
was proposed as alternative location ASR-3a. The proposal
dated on 9 November 2018 which verified by IEC was submitted to EPD for
approval. Based on rationale in Section 3.3.2, the Contract-related air quality monitoring location
for construction
phase were summarized in Table 3-2 and illustrated in Appendix D.
Table 3-2 Designated
Air Quality Monitoring Location under the Project
Location ID |
Description in EM&A Manual |
Location |
Related
Work Contract |
ASR-1 |
Village
House along Man Kam To Road |
Sha Ling Village House No.6 |
Contract
1 |
ASR-2 |
Village House at San Uk Ling |
San Uk
Ling Village House No.1 |
Contract
2 |
ASR-3 |
Village
House at Muk Wu Nga Yiu |
Muk Wu Nga Yiu House No.28 |
Contract
2 |
ASR-3a (#) |
Village
House at Muk Wu Nga Yiu |
Muk Wu Nga Yiu House No.2A |
Contract
2 |
Remark: (#) There was proposed relocation of air quality monitoring
location ASR-3 in October 2018. The proposal dated
on 9 November 2018 after verified by IEC was submitted to EPD for approval.
3.3.4
If the designated monitoring location
is required to relocate, alternative monitoring location shall agree with IEC and seek for EPD approval which
shall meet the following
criteria:
i)
Be at the site boundary or such locations
close to the major dust emission source;
ii)
Close to the sensitive receptors;
iii)
Take into account the prevailing meteorological conditions;
iv)
For monitoring location located in the vicinity of the ASRs, care
shall be taken to cause minimal disturbance to the occupants during monitoring.
v)
When positioning the HVS, the following points shall be noted:
a.
a horizontal platform with appropriate support to secure the
samples against gusty wind shall be provided;
b.
no two samplers shall be placed less than 2m apart;
c.
the distance between the HVS and an obstacle, such as buildings,
must be at least twice the height that the obstacle protrudes above the HVS;
d.
a minimum of 2 m separation from walls,
parapets and penthouses is required for HVS at the rooftop;
e.
a minimum of 2 m separation from any
supporting structure, measures horizontally is required;
f.
no furnace or incinerator flue is nearby;
g.
airflow around the sampler is unrestricted;
h.
the HVS is more than 20 m from the dripline;
i.
any wire fence and gate to protect the HVS, shall not cause any
obstruction during monitoring;
j.
permission must be obtained to set up the HVS and to obtain access
to the monitoring stations; and
k.
a secured supply of electricity is needed
to operate the HVS.
Construction
Noise
3.3.5
There were four (4) designated noise monitoring
locations recommended in the Approved EM&A Manual
Section 6.5.1.1. Based on rationale in Section 3.3.2, the Contract-related noise quality monitoring location for construction
phase were summarized in Table 3-3 and illustrated in Appendix D.
Table 3-3 Designated Construction
Noise Monitoring Location under the Project
Location ID |
Description in EM&A Manual |
Location |
Related
Work Contract |
CN-1 |
Village house to the west of
Sha Ling Road |
Village house to the west of
Sha Ling Road (free field condition) |
Contract
1 |
CN-2 |
Village house to the north of Man Kam To
Road |
Sha Ling
Village House No. 25 (free field condition) |
Contract
1 & 3 |
CN-3 |
Village house near San Uk Ling |
San Uk Ling
Village House No. 18 (free field condition) |
Contract
2 |
CN-4 |
Village house of Muk Wu |
Muk Wu Village House No. 267
(1m façade from the building) |
Contract
2 |
Water Quality
3.3.6
There were four (4) water quality monitoring
locations recommended in the Approved EM&A
Manual Section 7.6.1.2. The locations and coordinates of water quality monitoring were listed in Table 3-4. Based on rationale in Section 3.3.2, the Contract-related water quality monitoring location
for construction
phase were summarized in Table 3-4 and illustrated in Appendix D.
Table 3-4 Designated Water Quality Monitoring
Stations under the Project
Proposed Location ID |
Co-ordinates |
Description |
Related
Work Contract |
|
North |
East |
|||
M1 |
843 431 |
831 308 |
Midstream
of Nam Hang Stream |
Contract
2 |
M2 |
843 840 |
831 101 |
Downstream
of Nam Hang Stream |
Contract
2 |
M3 |
843 509 |
830 040 |
Wetland
in the Conservation Area near Yuen Leng Chai |
Contract
1 |
M4 |
843 997 |
831 783 |
Watercourse across Lin Ma
Hang Road, running from east of San Uk Ling to Man
Kam To Boundary Control Point |
Contract
2 |
3.4.1
The requirements of impact monitoring were stipulated in Sections 5.8.1.1, 6.7.1.1 and
7.8.1.4 of the approved EM&A
Manual and presented as follows.
Air Quality
Monitoring
3.4.2
Monitoring frequency for air quality impact monitoring is as follows:
1-Hour TSP |
3 sets of 1-hour TSP monitoring shall be
carried out once every six days during construction periods |
24-Hour TSP |
24-hour TSP monitoring shall be carried
out every six days during construction periods |
Noise Monitoring
3.4.3
Noise impact monitoring shall be carried out once per week during
construction periods. The noise measurement
for the time period between 0700 and 1900 hours shall be measured in terms of Leq (30 minutes) or 6 sets of Leq (5mins).
Water Quality Monitoring
3.4.4
The monitoring frequency shall be 3 days per week during
construction phase and the interval between two sets of monitoring shall not be less
than 36 hours.
3.5.1
The
monitoring equipment using for the EM&A program as proposed by the ET shall
be verified by the IEC.
Air Quality
Monitoring
3.5.2
The 24-hour and 1-hour TSP levels shall be measured by following
the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. If ET proposes to use a direct reading
dust meter to measure 1-hour TSP levels, it shall submit sufficient information
to IEC for approval.
3.5.3
The filter paper
of 24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.
3.5.4
All equipment used by ET for air quality monitoring is listed in Table
3-5.
Table 3-5 Air
Quality Monitoring Equipment
Equipment |
Model |
24-hour TSP |
|
High Volume Air
Sampler (HVAS) |
TISCH High Volume Air Sampler, HVS Model
TE-5170 |
Calibration
Kit |
TISCH Model TE-5025A |
1-Hour TSP |
|
Portable Dust Meter |
Sibata LD-3 Laser Dust monitor
Particle Mass Profiler & Counter |
Wind Data Monitoring Equipment
3.5.5
According to the approved EM&A Manual, wind data monitoring
equipment shall also be provided and set up for logging wind speed and wind
direction near the dust monitoring locations. The equipment installation location shall
be proposed by the ET and agreed with the IEC. For installation and operation of wind
data monitoring equipment, the following points shall be observed:
1)
The wind sensors should be installed 10 m above ground so that
they are clear of obstructions or turbulence caused by buildings.
2)
The wind data should be captured by a data logger. The data shall
be downloaded for analysis at least once a month.
3)
The wind data monitoring equipment should be re-calibrated at
least once every six months.
4)
Wind direction should be divided into 16 sectors of 22.5 degrees
each.
3.5.6
ET has liaised with the premises owners/ landlords to grant the permission
for the HVS installation. However, they rejected to set
up wind data
monitoring equipment installation in their premises.
3.5.7
Under this situation, the ET proposed to obtain representative
wind data from the Hong Kong Observatory Ta Kwu Ling Weather Station. Ta Kwu Ling Station is located near the Project site which situated at the sea level above 15mPD and
the wind data
monitoring equipment is installed 10 m above the existing ground.
Noise Monitoring
3.5.8
Sound level meter in
compliance with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1)
specifications shall be used for carrying out the noise monitoring. The sound level meter shall be checked
using an acoustic calibrator. The
wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in ms-1 before each noise monitoring event. Noise measurements should not be made
in fog, rain, wind with a steady speed exceeding 5 m s-1 or wind
with gusts exceeding 10 m s-1.
3.5.9
Noise monitoring equipment used for impact monitoring is listed in
Table
3-6.
Table 3-6 Noise
Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
Rion NL-52 Sound Level Meter |
Calibrator |
Rion NC-73 Acoustical Calibrator |
Portable Wind Speed Indicator |
Testo Anemometer |
3.5.10
Sound level meters listed above comply with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications, as recommended in TM issued
under the NCO.
Water Quality
Monitoring
3.5.11 Water
quality parameters include dissolved oxygen, water
temperature & depth, turbidity, salinity, pH and stream flow velocity shall
be measured in-situ, and suspended solids shall be analyzed by a HOKLAS-accredited
testing laboratory.
Dissolved Oxygen and Temperature Measurement
3.5.12 The dissolved oxygen (DO)
measuring instruments should be portable and weatherproof. The equipment should
also complete with cable and sensor, and DC power source. It should be capable
of measuring:
• A DO level in the range of 0 ¡V
20 mg/L and 0 ¡V 200% saturation; and
• A
temperature of 0 ¡V 45 degree Celsius.
3.5.13
The equipment should have a
membrane electrode with automatic temperature compensation complete with a
cable.
3.5.14
Should salinity compensation not
be built-in to the DO equipment, in-situ salinity should be measured to
calibrate the DO measuring instruments prior to each measurement.
Turbidity Measurement
3.5.15
The turbidity measuring instruments should be a portable and
weatherproof with DC power source. It
should have a photoelectric sensor capable of measuring turbidity level between
0¡V1000 NTU (for example, Hach model 2100Q or an approved similar
instrument).
Salinity Measurement
3.5.16
A portable salinometer capable of measuring
salinity in the range of 0¡V40 parts per thousand (ppt)
should be provided for measuring salinity of the water at each monitoring
location.
pH Measurement
3.5.17
A portable pH meter capable of measuring a
range between 0.0 and 14.0 should be provided to measure pH under the specified
conditions accordingly to the APHA Standard Methods.
Water Depth Measurement
3.5.18
A portable, battery-operated echo sounder or an approved similar
instrument should be used for water depths determination at each designated
monitoring station.
Stream Flow Velocity Equipment
3.5.19 Since the EM&A Manuals do
not specified instrument to use stream flow velocity measurement, the
monitoring of stream flow velocity is therefore proposed to be conducted by
using a flow probe which is a digital water velocity meter.
Water Sampling Equipment
3.5.20
A water sampler is required for suspended solid (SS) monitoring. A water sampler e.g. Kahlsico
Water Sampler, which is a transparent PVC cylinder with capacity not less than
2 litres, will be used for water sampling if water
depth over than 0.5m.
3.5.21
For sampling from very shallow water depths e.g. <0.5 m, water
sample will be collected from water surface below 100mm using plastic bottle to avoid
inclusion of bottom sediment or humus.
Moreover, Teflon/stainless steel bailer or self-made sampling buckets maybe
used for water sampling. The
equipment used for sampling will be depended the sampling location and depth
situations.
Sample Containers and Storage
3.5.22
Water samples for suspended solid should be stored in high density
polythene bottles with no preservative added, packed in ice (cooled to 4¢XC
without being frozen) and delivered to the laboratory within 24 hours of
collection and be analyzed as soon as possible after collection.
3.5.23
Analysis of suspended solids should be carried out in a HOKLAS or
other accredited laboratory. Water samples of about 1L should be collected at
the monitoring stations for carrying out the laboratory suspended solids
determination. The SS determination
work should start within 24 hours after collection of the water samples. The SS
analyses should follow the APHA Standard
Methods 2540D with Limit of Reporting of 2 mg/L.
3.5.24
Details
of the equipment used for water quality monitoring are listed in Table 3-7 below.
Table 3-7 Water
Quality Monitoring Equipment
Equipment |
Model |
Water Depth Detector |
Tape measures |
Water Sampler |
A
2-litre transparent PVC cylinder with latex cups at both ends or Teflon/stainless
steel bailer or self-made sampling bucket |
Thermometer & DO meter |
YSI Professional DSS/ YSI 550A |
pH meter |
AZ8685 pH meter /
YSI Professional DSS |
Turbidimeter |
Hach 2100Q/ YSI Professional DSS |
Salinometer |
Atago refractometer Atago S
Salinity Meter / YSI Professional DSS |
Stream Flow Velocity |
FP211 Global Flow Probe |
Sample Container |
High density polythene
bottles (provided by laboratory) |
Storage Container |
¡¥Willow¡¦ 33-litter plastic
cool box with Ice pad |
3.5.25
Furthermore, Suspended
solids (SS) analysis was carried out by ALS Technichem (HK) Pty Ltd. Which is one a local HOKLAS-accredited
laboratory
3.6.1
The HVAS is operated and calibrated on a regular basis in
accordance with the manufacturer¡¦s instruction using Tisch
Calibration Kit Model TE-5025A.
Calibration would carry out at fortnightly interval. The calibration data are properly
documented and the records are maintained by ET for future reference. Furthermore, Tisch Calibration Kit will be
calibrated by the manufacturer in yearly basis.
3.6.2
The 1-hour TSP meter calibrated by a local HOKLAS-accredited
laboratory would be undertaken in yearly basis. Zero response of the equipment was
checked before and after each monitoring event.
3.6.3
The sound level meter and acoustic calibrator are
calibrated and certified by a laboratory accredited under HOKLAS or any other
international accreditation scheme at yearly basis.
3.6.4
The multi-parameter Water Quality Monitoring
System is calibrated by HOKLAS accredited laboratory of three month intervals.
3.6.5
All updated calibration certificates of
the monitoring equipment used for the impact monitoring program in this
Reporting Month are attached in Appendix E.
3.7.1
The
impact monitoring data are handled by the ET¡¦s systematic data recording and
management, which complies with in-house Quality Management System. Standard
Field Data Sheets (FDS) are used in the impact monitoring program.
3.7.2
The
monitoring data recorded in the equipment e.g. 1-hour TSP meter, noise meter
and Multi-parameter Water
Quality Monitoring System are downloaded
directly from the equipment at the end of each monitoring day. The downloaded monitoring data are input
into a computerized database properly maintained by the ET. The laboratory results are input
directly into the computerized database and QA/QC checked by personnel other
than those who input the data. For
monitoring activities require laboratory analysis, the local laboratory follows
the QA/QC requirements as set out under the HOKLAS scheme for all laboratory
testing.
3.8.1
The baseline monitoring results form the basis for
determining the environmental acceptance criteria for the impact monitoring. The air quality, construction noise and
water quality criteria, namely Action and Limit levels were established according to
Approved EM&A Manual, and they are listed in Tables 3-8, 3-9 and
3-10 below.
Table 3-8 Action and Limit Levels for Air
Quality Monitoring
Monitoring Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
ASR-1 |
331 |
181 |
500 |
260 |
ASR-2 |
316 |
165 |
500 |
260 |
ASR-3 |
307 |
160 |
500 |
260 |
Table 3-9 Action
and Limit Levels for Construction Noise
Monitoring Location |
Action Level |
Limit Level in dB(A) |
Time Period: 0700-1900 hours
on normal weekdays |
||
CN-1,CN-2, CN-3, CN-4 |
When
one or more documented complaints are received |
75 dB(A) |
Note: * Reduces to 70 dB(A)
for schools and 65 dB(A) during the school examination periods.
Table 3-10 Action and Limit
Levels for Water Quality
Parameter |
Performance criteria |
Monitoring Location |
|||
M1 |
M2 |
M3 |
M4 |
||
DO (mg/L) |
Action Level |
3.03 |
4.99 |
4.58 |
3.62 |
Limit Level |
2.97 |
4.90 |
4.49 |
3.52 |
|
Turbidity (NTU) |
Action Level |
7.1 |
39.7 |
5.6 |
5.4 |
Limit Level |
7.6 |
42.2 |
5.9 |
5.9 |
|
SS (mg/L) |
Action Level |
8.5 |
29.0 |
9.3 |
4.8 |
Limit Level |
10.1 |
31.0 |
9.5 |
5.0 |
|
Notes: •
For DO,
non-compliance of the water quality limits occurs when monitoring result is
lower than the limits •
For turbidity
and SS, non-compliance of the water quality limits occurs when monitoring
result is higher than the limits. |
3.8.2
Should
non-compliance of the environmental quality criteria occurs, remedial actions will
be triggered according to the Event and Action Plan enclosed in Appendix F.
4.1.1
In the Reporting Month, air quality monitoring was
performed at all designated locations. Impact monitoring schedule provided to all relevant parties was shown in Appendix G.
4.1.2
In this Reporting Month, there were 5 sessions of 24-hour TSP and 18 sessions of 1-hour TSP undertaken
at each designated station for air quality monitoring. The air quality monitoring results are summarized in Tables 4-1 to 4-3.
The database of 24-hour TSP is shown in Appendix
H and the graphical
plots of monitoring result are shown in Appendix
I.
Table
4-1 Summary
of Air
Quality
Monitoring Results at ASR-1 under Contract 1
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st hour
measured |
2nd hour
measured |
3rd hour
measured |
||
6-Aug-21 |
30 |
2-Aug-21 |
13:30 |
72 |
69 |
77 |
12-Aug-21 |
30 |
7-Aug-21 |
9:11 |
69 |
73 |
78 |
18-Aug-21 |
34 |
13-Aug-21 |
9:32 |
53 |
51 |
48 |
24-Aug-21 |
36 |
19-Aug-21 |
9:21 |
74 |
70 |
61 |
30-Aug-21 |
46 |
25-Aug-21 |
9:06 |
58 |
63 |
61 |
|
31-Aug-21 |
13:04 |
83 |
80 |
71 |
|
Average (Range) |
35 (30
¡V 46) |
Average (Range) |
67 (48 ¡V
83) |
Table
4-2 Summary
of Air
Quality
Monitoring Results at ASR-2 under Contract 2
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st hour
measured |
2nd hour
measured |
3rd hour
measured |
||
6-Aug-21 |
26 |
2-Aug-21 |
13:42 |
63 |
69 |
65 |
12-Aug-21 |
16 |
7-Aug-21 |
9:16 |
74 |
73 |
70 |
18-Aug-21 |
20 |
13-Aug-21 |
9:39 |
43 |
49 |
46 |
24-Aug-21 |
13 |
19-Aug-21 |
9:16 |
67 |
63 |
70 |
30-Aug-21 |
14 |
25-Aug-21 |
9:13 |
61 |
58 |
55 |
|
31-Aug-21 |
13:11 |
76 |
64 |
71 |
|
Average (Range) |
18 (13
¡V 26) |
Average (Range) |
63 (43 ¡V
76) |
Table
4-3 Summary
of Air
Quality
Monitoring Results at ASR-3a under Contract 2
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st hour
measured |
2nd hour
measured |
3rd hour
measured |
||
6-Aug-21 |
21 |
2-Aug-21 |
13:56 |
58 |
65 |
61 |
12-Aug-21 |
17 |
7-Aug-21 |
9:20 |
68 |
71 |
70 |
18-Aug-21 |
20 |
13-Aug-21 |
9:46 |
43 |
46 |
44 |
24-Aug-21 |
16 |
19-Aug-21 |
9:10 |
59 |
60 |
68 |
30-Aug-21 |
27 |
25-Aug-21 |
9:20 |
57 |
52 |
60 |
|
31-Aug-21 |
13:18 |
88 |
74 |
70 |
|
Average (Range) |
20 (16 ¡V 27) |
Average (Range) |
62 (43 ¡V
88) |
4.2.1
As
shown in Tables 4-1 to
4-3, the monitoring results of 24-hour and 1-hour TSP monitoring in the Reporting Month were below the Action/ Limit Level.
No Notification of Exceedance (NOE) of air quality monitoring criteria was issued and therefore corrective action was not required. The
meteorological data during the impact monitoring days are summarized in Appendix J.
5.1.1
In the Reporting Month, noise monitoring was performed at
all designated locations.
Impact monitoring
schedule provided to all relevant
parties
was shown in Appendix G.
5.1.2
In
this Reporting
Month, 5 sessions of noise monitoring were undertaken at each designated
noise monitoring location. The sound level were set in a free field
situation for CN1, CN2 and CN3
and therefore a façade correction of
+3dB(A) has been added according to acoustical
principles and EPD guidelines. The monitoring result of noise monitoring is show in Tables 5-1 and 5-2 and the graphical plots are shown in Appendix
I.
Table
5-1 Summary of Construction Noise Monitoring Results under Contract 1
Construction
Noise Level (Leq30min), dB(A) |
||||
Date |
Start Time |
CN1(*) |
Start Time |
CN2(*) |
2-Aug-21 |
13:50 |
64 |
14:32 |
61 |
13-Aug-21 |
13:55 |
63 |
14:31 |
65 |
19-Aug-21 |
9:24 |
59 |
9:44 |
61 |
25-Aug-21 |
9:56 |
61 |
10:33 |
61 |
31-Aug-21 |
13:04 |
69 |
13:46 |
68 |
Limit Level |
75 dB(A) |
(*) A façade correction of +3dB(A) has been added according to acoustical principles and
EPD guidelines.
Table
5-2 Summary of Construction Noise Monitoring Results under Contract 2
Construction
Noise Level (Leq30min), dB(A) |
||||
Date |
Start Time |
CN3 (*) |
Start Time |
CN4 |
2-Aug-21 |
15:38 |
61 |
16:11 |
58 |
13-Aug-21 |
15:06 |
58 |
15:11 |
53 |
19-Aug-21 |
13:57 |
60 |
14:15 |
54 |
25-Aug-21 |
11:07 |
58 |
13:38 |
56 |
31-Aug-21 |
14:33 |
64 |
15:09 |
65 |
Limit Level |
75 dB(A) |
(*) A façade correction of +3dB(A) has been added according to acoustical principles and
EPD guidelines.
5.1.3
Prior and after noise monitoring, the accuracy of the sound level meter
has been checked by
an acoustic calibrator to ensure the measurement within acceptance
range of ¡Ó0.5dB. Moreover, wind speed checked by portable wind speed meter has been performed before noise monitoring.
No noise
measurement was performed in fog, rain, wind with a steady speed exceeding 5 m
s-1 or wind with gusts exceeding 10 m s-1.
5.2.1
As
shown in Tables 5-1 and
5-2, no Limit Level exceedance for noise monitoring exceedance was recorded in the Reporting Month. Moreover, no noise complaint (which triggered Action Level) was received. No
Notification of Exceedance (NOE) of construction noise criterion was issued and no corrective action was therefore required.
6.1.1
In the Reporting Month, water
quality monitoring was performed at all designated
locations. Impact monitoring schedule provided to all relevant
parties was shown in
Appendix G.
6.1.2
In the Reporting Month,
a total of 13 monitoring days were
carried
out for
water quality impact monitoring. The
monitoring result
of key parameters including Dissolved Oxygen, Turbidity and Suspended Solids are summarized in Tables 6-1 and 6-2. Detailed monitoring
results including in-situ measurements and laboratory analysis data are shown
in Appendix H and graphical plots for monitoring result are shown in Appendix
I.
Table
6-1 Summary
of Water Quality Monitoring Results ¡V M3
under Contract 1
Date |
Parameters |
||
DO (Averaged) (mg/L) |
Turbidity (Averaged) (NTU) |
Suspended
Solids
(Averaged) (mg/L) |
|
2-Aug-21 |
5.32 |
5.1 |
5.5 |
4-Aug-21 |
6.25 |
5.3 |
7.0 |
6-Aug-21 |
6.10 |
45.2
|
37.0
|
9-Aug-21 |
7.18 |
40.6
|
32.5
|
11-Aug-21 |
5.62 |
5.5 |
8.5 |
13-Aug-21 |
5.78 |
5.5 |
6.0 |
16-Aug-21 |
6.08 |
5.1 |
5.5 |
18-Aug-21 |
6.00 |
5.5 |
5.0 |
20-Aug-21 |
6.00 |
49.6
|
33.5
|
23-Aug-21 |
6.07 |
39.5
|
30.5
|
25-Aug-21 |
4.61 |
5.1 |
8.5 |
27-Aug-21 |
6.93 |
5.1 |
5.5 |
30-Aug-21 |
6.39 |
1.7 |
5.5 |
Note: Bold and underlined value
indicated Limit Level exceedance
Table
6-2 Summary of Water Quality
Monitoring Results (M1, M2
and M4) under Contract 2
Date |
Parameters |
||||||||
DO (Averaged) (mg/L) |
Turbidity (Averaged) (NTU) |
Suspended
Solids
(Averaged) (mg/L) |
|||||||
M1 |
M2 |
M4 |
M1 |
M2 |
M4 |
M1 |
M2 |
M4 |
|
2-Aug-21 |
5.96 |
5.20 |
5.88 |
6.5 |
26.7 |
2.4 |
3.5 |
28.0 |
3.0 |
4-Aug-21 |
8.04 |
6.90 |
6.41 |
19.5
|
9.1 |
5.2 |
14.5
|
12.5 |
3.5 |
6-Aug-21 |
7.43 |
7.67 |
7.13 |
15.2
|
162.0
|
4.7 |
13.5
|
99.5
|
4.0 |
9-Aug-21 |
6.09 |
7.18 |
6.06 |
17.3
|
134.0
|
5.2 |
8.0 |
99.0
|
2.0 |
11-Aug-21 |
6.06 |
5.84 |
6.13 |
18.8
|
125.5
|
3.3 |
14.0
|
110.0
|
2.0 |
13-Aug-21 |
6.37 |
5.77 |
6.56 |
6.3 |
28.5 |
3.7 |
6.5 |
26.5 |
2.0 |
16-Aug-21 |
6.35 |
6.01 |
6.34 |
7.1 |
29.7 |
2.9 |
8.0 |
28.5 |
2.5 |
18-Aug-21 |
6.35 |
6.40 |
6.53 |
6.6 |
10.7 |
5.4 |
4.0 |
21.0 |
2.0 |
20-Aug-21 |
6.48 |
6.18 |
6.40 |
1.7 |
104.0
|
4.6 |
7.5 |
100.0
|
3.0 |
23-Aug-21 |
6.16 |
6.08 |
6.61 |
4.3 |
15.2 |
4.8 |
7.5 |
32.5
|
2.5 |
25-Aug-21 |
6.16 |
5.93 |
6.32 |
7.0 |
25.7 |
3.0 |
8.0 |
13.0 |
<2 |
27-Aug-21 |
7.52 |
6.94 |
7.65 |
110.5
|
38.7 |
74.5
|
143.0
|
52.5
|
82.0 |
30-Aug-21 |
5.01 |
6.25 |
6.54 |
40.6
|
18.0 |
1.5 |
129.0
|
45.0
|
<2 |
Note: Bold and underlined value
indicated Limit Level exceedance
6.1.3
During the Reporting Month, field measurements including
temperature of stream water, salinity
concentrations, pH values and the stream
flow velocity for all monitoring locations are summarized in Table 6-3.
Table
6-3 Summary of Field Measurements for
Water Quality
Monitoring Location |
Parameters of field measurements |
|||||||
pH (Averaged) (unit) |
Salinity (Averaged) (ppt) |
Temp (Averaged) (oC) |
Water Flow (Averaged) (m/s) |
|||||
min |
max |
min |
max |
min |
max |
min |
max |
|
M1 |
7.1 |
8.7 |
0.06 |
0.07 |
25.4 |
28.0 |
<0.1 |
0.1 |
M2 |
7.0 |
8.0 |
0.05 |
0.08 |
26.2 |
29.2 |
<0.1 |
0.1 |
M3 |
7.0 |
8.0 |
0.01 |
0.03 |
26.4 |
28.9 |
<0.1 |
0.1 |
M4 |
6.6 |
7.6 |
0.04 |
0.1 |
26.0 |
28.6 |
<0.1 |
0.1 |
6.2.1
In this Reporting Month, a total of 32 Limit
level exceedances, namely 15 exceedance of Turbidity and 17 exceedances of SS were recorded. The non-compliance of water quality performance
is summarized in Table 6-4.
Table
6-4 Action and Limit (A/L) Levels Exceedance Record
Station |
DO |
Turbidity |
SS |
Total Exceedance |
Project Related exceedance |
|||||
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
|
M1 |
0 |
0 |
0 |
6 |
0 |
5 |
0 |
11 |
0 |
0 |
M2 |
0 |
0 |
0 |
4 |
0 |
7 |
0 |
11 |
0 |
0 |
M3 |
0 |
0 |
0 |
4 |
0 |
4 |
0 |
8 |
0 |
0 |
M4 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
2 |
0 |
0 |
6.2.2
Notification of Exceedance (NOE) and the investigation for exceedance in
the Reporting Month is
summarized in Table 6-5.
Table 6-5 Summary
of Investigation of Water Quality Exceedance in the Reporting Month
Date of Exceedance |
Exceeded Location |
Exceeded Parameter |
Cause of Water Quality Exceedance |
4,6 & 11 Aug 2021 |
M1 |
Turbidity
& SS |
According to the weather information from the
HKO, there was rainstorm intermittently on 4 to 11 August 2021. Under the
impact of rainstorm, the water quality of the watercourse was deteriorated by
the stirred up sediment and runoff from the surrounding environment. However,
there was no construction
site under the project at upstream. Weekly site inspection was
conducted and no adverse water quality impact observed on the works area on Man Kam To Road and Lin Ma Hang Road. No works under the Project
was carried out near Locations M1 and M2. Since there were no works undertaken
near Locations M1 and M2, it was considered that the exceedances were related
to the rainstorm and unlikely caused by the work under the project. |
9 Aug 2021 |
M1 |
Turbidity |
|
6, 9 & 11 Aug 2021 |
M2 |
Turbidity
& SS |
|
6 & 9 Aug 2021 |
M3 |
Turbidity
& SS |
According to the weather data
from Observatory,
there were heavy
rainstorms on 19 August 2021 and Special Announcement on Flooding in the
northern New Territories was issued on 19 August 2021. Under the influence of rain, the water
quality of seasonal watercourse was inevitably be affected by the stirred up sediment and erosion from the surrounding
environment even outside
the construction site. In our investigation, HCTY-JV had implemented water quality mitigation measures. In view of the
implementation of water quality mitigation measures, the site was generally
in good order and no water quality impact was observed, it
is considered that the exceedances were likely caused by impact of rain and not related to the works
under the Project. |
|
|
|
|
20 & 23 Aug 2021 |
M2 |
Turbidity
& SS |
According to the weather information from the
HKO, there was heavy rainstorm on 19 August 2021 and Special Announcement on Flooding in the
northern New Territories was announced on 19 August 2021. Under the impact of
rainstorm, the water quality of the watercourse was deteriorated by the
stirred up sediment and runoff from the surrounding environment. Weekly site
inspection was conducted and no adverse water quality impact observed on the
works area on Man Kam To
Road and Lin Ma Hang Road. No works under
the Project was carried out near Location M2. Since there were no works undertaken
near Location M2, it was considered that the exceedances were related to the
rainstorm and unlikely caused by the work under the project. |
20 & 23 Aug 2021 |
M3 |
Turbidity
& SS |
According to the weather information from the
HKO, there was heavy rainstorm on 19 August 2021 and Special Announcement on Flooding in the
northern New Territories was announced on 19 August 2021. Under the influence of rain, the water quality of seasonal watercourse was inevitably
be affected
by the stirred up sediment
and erosion from the surrounding environment even outside the construction site. In
our investigation, HCTY-JV had implemented water quality mitigation measures. In view of the
implementation of water quality mitigation measures, the site was generally
in good order and no water quality impact was observed, it
is considered that the exceedances were likely caused by impact of rain and not related to the works
under the Project. |
27 & 30 Aug 2021 |
M1 |
Turbidity
& SS |
According to the weather information from the
HKO, there was heavy rainstorm on 27 to 30 August 2021 and Amber Rainstorm Warning Signal was
announced on 29 August 2021. Under the impact of rainstorm, the
water quality of the watercourse was deteriorated by the stirred up sediment
and runoff from the surrounding environment. Weekly site inspection was
conducted and no adverse water quality impact observed on the works area on Man Kam To Road and Lin Ma Hang Road. No works under the Project
was carried out near Locations M1, M2 and M4. Since there were no works undertaken
near Locations M1, M2 and M4, it was
considered that the exceedances were related to the rainstorm and unlikely
caused by the work under the project. |
27 & 30 Aug 2021 |
M2 |
SS |
|
27 Aug
2021 |
M4 |
Turbidity
& SS |
7.1.1
According
to approved EIA report (AEIAR-198/2016), habitat types within project boundary
comprise of watercourse, grassland, upland grassland, plantation, woodland and
developed area. Natural habitats were of moderate ecological value in terms of
species diversity, species rarity, species abundance, ecological linkage as
well as nursery. Moreover, 0.3ha of wet woodland on the northern side of Sandy
Ridge was deemed habitat with high ecological value. Four types of habitats were regarded as
ecologically sensitive habitats, namely wet woodland, watercourses, upland
grassland and woodland. Considering human disturbance in upcoming construction
and operation phases, ecologically sensitive habitats shall be monitored in
accordance with EM&A Manual.
7.1.2
The objective of ecologically
sensitive habitats monitoring is to evaluate the effectiveness of measures to
minimize impacts on concerned habitats from disturbance and pollution. In order
to monitor the effectiveness of the measures to the minimize impact on
ecologically sensitive habitats from disturbance and pollution, monthly
monitoring during construction and operation phases is required as specified in
EM&A Manual. Standard faunal transect and sampling surveys cover both
wetland habitats
(wet woodland and watercourse)
and non-wetland habitats (upland
grassland and woodland).
7.2.1
Wetland
habitats include wet woodland and watercourses. Monitoring surveys using
standardized quantitative methodology will conduct at fixed points. For seasonal watercourse, the survey
will be conducted whenever the habitat appears. Measures
to respond to decreases in numbers of aquatic fauna using the wetland habitats
and Action/Limit levels to trigger these measures are detailed in Table
7-1.
Table 7-1 Action and Limit Levels for Wet Woodland Habitats
Monitoring
Action
Level |
Response |
Limit
Level |
Response |
Reduction
in taxa diversity by 30% |
Investigate
cause and if cause identified as related to the project instigate remedial
action to remove or reduce source of disturbance. |
Reduction
in taxa diversity by 50% |
Investigate
cause and if cause identified as related to the project instigate remedial
action. |
Remarks:
Action and Limit Levels and Responses to Evidence of Declines in Aquatic Fauna
7.2.2
Non-wetland
habitats consist of upland grassland and woodland. Monthly quantitative surveys
of non-aquatic fauna will be conducted using standard route transect
counts. Measures to respond to
decreases in numbers of non-aquatic fauna using the non-wetland habitats and
Action/Limit levels to trigger these measures are detailed in Table
7-2.
Table 7-2 Action and Limit Levels for Non-Wet Woodland
Habitats Monitoring
Action
Level |
Response |
Limit
Level |
Response |
Reduction
in species diversity by 30% |
Investigate
cause and if cause identified as related to the project instigate remedial
action to remove or reduce source of disturbance. |
Reduction
in species diversity by 50% |
Investigate
cause and if cause identified as related to the project instigate remedial
action. |
Remarks:
Action and Limit Levels and Responses to Evidence of Declines in Non-Aquatic
Fauna
7.2.3
The ecological survey includes all taxa being
investigated in accordance with EIA report. Schedule of faunal surveys in each year
during construction phase is presented in Table 7-3.
Table 7-3 Schedule of Faunal Surveys in each year During Construction
Phase
Month |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
Aug |
Sep |
Oct |
Nov |
Dec |
Mammals |
Ö |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
Birds (day) |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
Birds (night) |
|
|
|
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
|
|
Herpetofauna |
|
|
|
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
|
|
Dragonflies |
|
|
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
|
|
Butterflies |
|
|
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
|
|
Aquatic fauna |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
Mammal
Survey
7.2.4
Mammal surveys will be conducted along the proposed transects (shown
in Appendix
K - Ecological Survey Reports)
in during both daytime and night time
periods. Along with direct observations, other field signs, such as scats and
tracks, will be searched and recorded if present.
Bird
Survey
7.2.5
Bird surveys will be conducted along the transects
(shown in Appendix
K - Ecological Survey Reports) during the surveys, species and their vocalizing individuals
recorded will be enumerated and recorded according to the habitat(s) they are
utilizing.
Herpetofauna Survey
7.2.6
Reptile and amphibian surveys will be conducted along transects (shown
in Appendix
K - Ecological Survey Reports) during surveys careful searches of appropriate microhabitats and refugia for reptiles and their vocalizing individuals will
be undertaken and all reptiles observed will be identified and counted.
Dragonfly
and Butterfly Survey
7.2.7
Dragonfly and Butterfly surveys will be conducted along transects (shown
in Appendix
K - Ecological Survey Reports) during surveys all dragonflies and Butterflies seen will be
identified and counted as accurately as possible.
Aquatic
Fauna Survey
7.2.8
Freshwater fishes and macro-invertebrates will be recorded by
direct observation. All species trapped/recorded will be enumerated and
identified (to the lowest taxonomic level possible), and the species of
conservation importance photographed.
7.2.9
After
each ecological monitoring survey, a monthly report of the survey result and
data collected will be provided with reference to EM&A Manual. An
annual analysis of data will be carried out in order to study if there is any
significant reduction in taxa diversity and abundance.
7.3.1
In the Reporting Month, ecological monitoring was undertaken on 10th August 2021 at work area of Contract 1. A sunny day. The day and night survey covered wetland
and non-wetland areas. The survey was
conducted by transect and at fixed points. All
species seen will be identified and counted as accurately as possible. Results of
the monitoring survey are presented below:
Monitoring
Result for Contract 1
Mammal
7.3.2
There was no mammal recorded in the
monitoring area
Birds
7.3.3
There were a total of 11 bird individuals from 6 species recorded in the
monitoring area. No Golden-headed
Cisticola was observed during the bird survey. Two conservation interests were
recorded in the monitoring area: Ardea alba Great
Egret ¤j¥ÕÆO, Halcyon smyrnensis White-throated Kingfisher ¥Õ¯Ý»B»A.
Herpetofauna
7.3.4
There was no reptile species recorded
in monitoring area. There was 1 amphibian specie recorded
in the monitoring area.
Butterfly
7.3.5
There
were a total of 5 butterfly
individuals from 2 species
recorded in the monitoring area.
Dragonfly
7.3.6
There were a total of 11 odonate
individuals from 7 species recorded in the monitoring area. Two conservation
interests were recorded in the monitoring area: Gynacantha
subinterrupta, Dingy Dusk-hawker ²Ó¸yªø§À¸» and Urothemis signata, Scarlet Basker ¨ª´³¦±鈎¯ß»f.
Aquatic Fauna Survey (Freshwater communities)
7.3.7
There
was no freshwater community recorded in the monitoring area.
7.3.8
The summaries
of faunal survey result are shown in Tables 7-4 and 7-5.
Table 7-4 Result
of Faunal Survey under
Contract 1
Scientific Name |
Common / Engineer Name |
Chinese Name |
Conservation Status |
Non- wetland |
Wetland |
Mammal Survey |
|||||
-- |
-- |
-- |
-- |
-- |
-- |
Avifauna Survey |
|||||
Ardea
alba |
Great Egret |
¤j¥ÕÆO |
|
1 |
|
Apus nipalensis
|
House Swift |
¤p¥Õ¸y«B¿P |
|
|
4 |
Halcyon smyrnensis
|
White-throated
Kingfisher |
¥Õ¯Ý»B»A |
|
|
1 |
Lanius schach |
Long-tailed
Shrike |
´ÄI§B³Ò |
|
|
1 |
Corvus macrorhynchos |
Large-billed
Crow |
¤j¼L¯Q¾~ |
|
2 |
|
Motacilla
alba |
White Wagtail |
¥ÕöÀÀo |
|
2 |
|
Reptile
Survey |
|||||
-- |
-- |
-- |
-- |
-- |
-- |
Amphibian
Survey |
|||||
Fejervarya limnocharis |
Paddy Frog |
¿Aµì |
|
|
+ |
Butterfly
Survey |
|||||
Abisara echerius |
Plum Judy |
³D¥Ø½Å¸Ã½º |
|
2 |
1 |
Catopsilia pomona |
Lemon Emigrant |
¾E¯»½º |
|
|
2 |
Odonate Survey |
|||||
Brachydiplax chalybea |
Blue Dasher |
ÂÅÃB²¨¯ß»f |
|
|
1 |
Ceriagrion auranticum |
Orange-tailed Sprite |
¯[²y¾ï¶Àîe |
|
|
2 |
Gynacantha subinterrupta |
Dingy Dusk-hawker |
²Ó¸yªø§À¸» |
Fellowes et
al. (2002): LC |
|
1 |
Neurothemis tullia |
Pied Percher |
ºI´³¯ß»f |
|
|
2 |
Orthetrum sabina |
Green Skimmer |
¯U¸¡¦Ç»f |
|
|
1 |
Prodasineura autumnalis |
Black Threadtail |
¯Q¾¦ìîe |
|
|
2 |
Urothemis signata |
Scarlet Basker |
¨ª´³¦±鈎¯ß»f |
Fellowes et
al. (2002): LC |
1 |
1 |
+ Species counted by vocal identification
Table 7-5 Result
of Freshwater Communities Survey under Contract
1
Scientific
Name |
Common Name |
Chinese
Name |
Conservation
Status |
10-Aug-21 |
|
Non- wetland |
Wetland |
||||
-- |
-- |
-- |
-- |
-- |
-- |
Discussion
7.3.9
After analysing survey results in August from 2018 to 2021, it is found that the species diversity
reduced in both wetland
and non-wetland habitat. The reduction could be due to natural
fluctuation. Good practice during construction is
required to prevent environmental contamination as well as unnecessary site
clearance. Continuous monitoring is also recommended to inspect any significant
decrease in species diversity.
7.4.1
In the Reporting Month, ecological monitoring was undertaken on 10th August 2021 at work area of Contract 2. A sunny day. The
day and night survey covered wetland and non-wetland areas. The survey was
conducted by transect and at fixed point. All species seen will be identified
and counted as accurately as possible. Results of the monitoring survey are
presented below:
Monitoring
Result for Contract 2
Mammal
7.4.2
There was no mammal recorded in the
monitoring area
Birds
7.4.3
There were total of 15 bird individuals from 5 species recorded in the monitoring area. Golden-headed Cisticola
was not observed during the bird survey.
Herpetofauna
7.4.4
There was no reptile recorded in the
monitoring area. There was no
amphibian recorded in the monitoring area.
Butterfly
7.4.5
There were a total of 2 butterfly individuals
from 1 specie recorded in the monitoring area.
Dragonfly
7.4.6
There were a total of 10 odonate individuals from 2 species recorded in the
monitoring area.
Aquatic Fauna Survey (Freshwater communities)
7.4.7
There were 2 species of freshwater fish
were recorded in the monitoring area.
7.4.8
The summaries
of faunal survey result are shown in Tables 7-6 and 7-7.
Table 7-6 Result
of Faunal Survey under
Contract 2
Scientific Name |
Common / Engineer Name |
Chinese Name |
Conservation Status |
Non- wetland |
Wetland |
Mammal Survey |
|||||
-- |
-- |
-- |
-- |
-- |
-- |
Avifauna Survey |
|||||
Spilopelia chinensis |
Spotted Dove |
¯]ÀV´³¹§ |
|
1 |
2 |
Parus cinereus |
Cinereous Tit |
»aI¤s³¶ |
|
|
2 |
Pycnonotus jocosus |
Red-whiskered
Bulbul |
¬õ¦Õóí |
|
|
2 |
Prinia flaviventris
|
Yellow-bellied
Prinia |
¶À¸¡økÅa |
|
|
2 |
Zosterops japonicus |
Japanese
White-eye |
·tºñ¸²´³¾ |
|
2 |
4 |
|
|||||
-- |
-- |
-- |
-- |
-- |
-- |
Amphibian
Survey |
|||||
-- |
-- |
-- |
-- |
-- |
-- |
Butterfly Survey |
|||||
Ariadne
ariadne |
Angled Castor |
ªißæ½º |
|
|
2 |
Odonate Survey |
|||||
Trithemis aurora |
Crimson Dropwing |
¾å½Å»f |
|
|
2 |
Pantala flavescens |
Wandering Glider |
¶À»f |
|
2 |
6 |
Table 7-7 Result of Freshwater
Communities Survey under Contract 2
Scientific Name |
Common Name |
Chinese Name |
Conservation Status |
10-Aug-2021 |
Gambusia affinis |
Mosquito fish |
¹°A³½ |
|
+ |
Puntius
semifasciolatus |
Chinese Barb |
¤½uµLŽ䰾 |
|
+ |
+: Species appeared but uncountable.
Discussion
7.4.9
After analysing
survey results in August 2019 to 2021, there was a drop in species richness
and abundance for non-wetland habitats. It
could be due to natural fluctuation. However, a good
practice during construction is required to prevent environmental contamination
as well as unnecessary site clearance. Moreover, continuous monitoring is
required to inspect any significant reduction of species diversity.
7.4.10 The detailed Ecological Survey Reports for Contract 1
and Contract 2 are attached in Appendix
K.
7.4.11 The tentative ecology
inspection and monitoring in the next Reporting Month (September 2021) is scheduled on 7th
September 2021.
7.5.1
According to the approved vegetation
survey report and transplantation proposal under FEP-01/534/2017/A, an individual of flora species of conservation interest (the
transplanted T-2928) was
identified and transplanted to the receptor site.
7.5.2
According to approved vegetation survey report and transplantation proposal, post-transplantation monitoring was conducted
once per week in the first three months after the transplantation in Oct 2018
and once in each of the following month in the remaining establishment period
for 12 month. During the remaining
construction phase of the project, the transplanted T-2928 would be monitored
on quarterly basis.
7.5.3
A landscape sub-contractor was employed
by the Contractor to monitor the health condition of transplanted species and provide advice on necessary
weeding, fertilizing and pest control. The monitoring records were submitted to
ET and IEC for review and record. Moreover,
inspection of the transplanted T-2928 was undertaken by ET as part of the weekly
site inspection. No construction
activity and disturbance were observed at the location of the transplanted
T-2928. The health condition of the
transplanted T-2928 was fair with normal foliage color and density.
7.6.1
Pursuant
to FEP-01/534/2017/A condition 2.19 and EP-534/2017/A condition 2.20, precautionary checks for the presence of nesting birds shall be carried out in the
breeding season (February to July) before vegetation clearance.
7.6.2
As advised by both Contractors, there were no
vegetation clearance conducted within the site in the Reporting
Month and therefore precautionary check for the presence
of nesting birds was not required.
8.1.1
The EIA has recommended EM&A for landscape and visual
resources to be undertaken during the design, construction and operational
stages of the project. The design, implementation and maintenance of landscape
mitigation measures is a key aspect of this and should be checked to ensure
that they are fully realized and that potential conflicts between the proposed
landscape measures and any other project works let its are resolved at the earliest
possible date and without compromise to the intention of the mitigation
measures. In addition, implementation of the mitigation measures recommended by
the EIA will be monitored through the site audit programme.
8.1.2
A number of mitigation measures to ameliorate the landscape and
visual impacts of the Project implementation is
summarized in the EMIS of Appendix 13.1 of the EIA Report.
8.1.3
The landscape and visual
mitigation measures proposed should be incorporated in the landscape and
engineering design. Mitigation
measures to be implemented during construction should be adopted from the start
of construction and be in place throughout the entire construction period. Mitigation measures to be implemented
during operation should be integrated into the detailed design and built as
part of the construction works so that they are in place on commissioning of
the Project. Tree transplantation
and compensatory planting should be carried out as early as possible in the
Project with transplantation carried
out prior to construction starting in any particular area.
8.1.4
During
construction phase, Landscape & Visual Monitoring of the contractor¡¦s operations should be conducted monthly and
reported by ET, and countersigned by IEC.
8.2.1
In the Reporting Month, landscape & visual inspection was carried out by the Registered Landscape Architect
(RLA) for works area
of Contract 1 and Contract 2 on 26th August 2021. The findings / reminders recorded
during the inspection are presented in Tables 8-1 and 8-2.
Table 8-1 Landscape
& Visual Inspection Finding for Contract 1
Date |
Findings and Reminder |
Follow-Up Status |
26th
August 2021 |
1.
The Contractor is reminded to set up
TPZ of proper size and with appropriate material around retain trees
according to approved method statement. |
•
Reminder only |
2.
The Contractor is reminded to prevent
the construction material pile within TPZ and ensure no works is allowed within the TPZ. |
•
Reminder only |
|
3.
Transplanted trees
T2465, T2468 and T2928 were in fair health condition with normal foliage color
and density. Contractor is reminded to provide proper maintenance according
to approved method statement. |
•
Reminder only |
Table 8-2 Landscape
& Visual Inspection Finding for Contract 2
Date |
Findings and Reminder |
Follow-Up Status |
26th
August 2021 |
1.
Contractor is reminded to set up TPZ
of proper size and with appropriate material around retain trees according to
approved method statement. Contractor should prevent any construction material
pile within TPZ and ensure no works is allowed within the TPZ. |
• Reminder
only |
8.2.2
Inspection checklist of Landscape & Visual signed by RLA is attached in Appendix L.
9.1.1
Waste management was carried out by an on-site Environmental
Officer or an Environmental Supervisor from time to time in accordance with the
Waste Management Plan (WMP).
9.2.1
All
types of waste arising from the construction work are classified into the
following:
l Construction & Demolition (C&D)
Material;
l Chemical Waste;
l General Refuse; and
l Excavated Soil.
9.2.2
The
quantities of waste for disposal in this Reporting Month are summarized in Table 9-1 and 9-2 and
the Monthly Summary Waste Flow Table is shown in
Appendix M. Whenever possible, materials were reused
on-site as far as practicable.
Table 9-1 Summary
of Quantities of Inert C&D Materials
Type of Waste |
Contract 1 |
Contract 2 |
||
Quantity |
Disposal Location |
Quantity |
Disposal Location |
|
Total generated C&D Materials (Inert) (¡¥000m3) |
5.674 |
-- |
2258.880 (#) |
-- |
Reused
in this Contract (Inert) (¡¥000m3) |
0 |
-- |
0 |
-- |
Reused
in other Projects (Inert) (¡¥000m3) |
0 |
-- |
0 |
-- |
Disposal
as Public Fill (Inert) (¡¥000m3) |
5.563 |
Tuen Mun Area 38 |
2258.880 (#) |
Tuen Mun Area 38 |
Remark:
the unit is ¡¥000kg
Table 9-2 Summary
of Quantities of C&D Wastes
Type of Waste |
Contract 1 |
Contract 2 |
||
Quantity |
Disposal Location |
Quantity |
Disposal Location |
|
Recycled
Metal (¡¥000kg) |
0 |
-- |
0 |
-- |
Recycled Paper / Cardboard Packing (¡¥000kg) |
0 |
-- |
0 |
-- |
Recycled Plastic (¡¥000kg) |
0 |
-- |
0 |
-- |
Chemical Wastes (¡¥000kg) |
0 |
-- |
0 |
-- |
General Refuses (¡¥000m3) |
0.035 |
NENT Landfill |
9.340 (#) |
NENT Landfill |
Remark:
the unit is ¡¥000kg
9.2.3
Since
canteen and/or kitchen are not allowed setting on the Project site,
no domestic wastewater was generated
from the Project.
10.1.1 According to the approved EM&A Manual, environmental
site inspection should be led by RE and attended by the Contractor and ET at
least once per week. Regular environmental site inspections shall
be carried out to assess the environmental performance.
Contract 1
10.2.1 In the Reporting Month, joint site
inspections for
Contract 1 to evaluate the site
environmental performance were carried out by the RE, ET and the Contractor on
5th,
12th, 19th and 26th August 2021 and IEC attended joint site inspection on 19th August 2021. No non-compliance
was noted.
10.2.2 The findings / deficiencies
that observed during the weekly site inspection are listed in Table
10-1.
Table 10-1 Site
Observations for the Works of Contract 1
Date |
Findings / Deficiencies |
Follow-Up Status |
5th Aug 2021 |
Stockpile of cement bags were observed
without proper covering at DPA area. The Contractor was advised to cover it
properly. |
Stockpile of cement bags were covered
properly. |
The Contractor was reminded to clean
stagnant water within site area after rainstorm. |
Reminder only. |
|
12th Aug
2021 |
Chemical containers were observed on the ground at CS1. The Contractor
was advised to place chemical containers inside drip tray. |
Chemical containers were
removed from site area. |
19th Aug
2021 |
The Contractor was advised to place
chemical
containers inside drip tray. |
Chemical containers were
removed at CS13. |
The Contractor was advised to block
culvert/channel near sedimentaion tank next to wheel washing facility. |
The waste water from wheel washing facility was pumped to the sedimentation
tank. |
|
The Contractor was reminded to dispose
construction waste regularly. |
Reminder
only. |
|
The Contractor was reminded to provide
drip tray for air compressor. |
Reminder
only. |
|
26th Aug
2021 |
Chemical container was observed on the ground at CS1. The Contractor was
advised to place chemical container inside drip tray. |
Chemical containers were
removed at CS1. |
The Contractor was reminded to dispose construction waste regularly at
PDA and CS13. |
Reminder only. |
Contract 2
10.2.3 In the Reporting Month, joint
site inspections for
Contract 2 to evaluate the site
environmental performance carried out by the RE, ET and the Contractor was on
5th, 12th, 19th
and 26th August 2021 and IEC attended joint site inspection on 19th August 2021
non-compliance was noted.
10.2.4 The findings / deficiencies
that observed during the weekly site inspection are listed in Table
10-2.
Table 10-2 Site Observations
for the Works of Contract 2
Date |
Findings / Deficiencies |
Follow-Up Status |
5th Aug 2021 |
No adverse environmental issue was observed. |
N/A |
12th Aug
2021 |
No adverse environmental issue was observed. |
N/A |
19th Aug
2021 |
The Contractor was advised to clean the slurry on the ground at
Jacking Pit. |
The sludge on the ground was cleaned |
The Contractor was advised to place sandbags for the gully at Jacking
Pit. |
Sandbags was provided for gully. |
|
The Contractor was advised to clean the muddy trails at entrance of
work area at Lin Ma Hang Road. |
Muddy trails on the ground was cleaned. |
|
26th Aug
2021 |
No adverse environmental issue was observed. |
N/A |
11.1.1 In
the Reporting Month,
no environmental complaint was received for the project. No summons and prosecution was lodged for the Contract.
The
statistical summary table of the environmental complaint, summons and
prosecution are presented in Tables 11-1, 11-2 and 11-3.
Table
11-1 Statistical
Summary of Environmental Complaints
Reporting Month |
Environmental Complaint
Statistics |
|||
Frequency |
Cumulative |
Complaint Nature |
||
1st ¡V 31st
August 2021 |
Contract 1 |
0 |
1 |
Air Quality |
1st ¡V 31st
August 2021 |
Contract 2 |
0 |
2 |
Air Quality |
Table 11-2 Statistical
Summary of Environmental Summons
Reporting Month |
Environmental Summons
Statistics |
|||
Frequency |
Cumulative |
Complaint Nature |
||
1st ¡V 31st
August 2021 |
Contract 1 |
0 |
0 |
NA |
1st ¡V 31st
August 2021 |
Contract 2 |
0 |
0 |
NA |
Table 11-3 Statistical
Summary of Environmental Prosecution
Reporting Month |
Environmental Prosecution
Statistics |
|||
Frequency |
Cumulative |
Complaint Nature |
||
1st ¡V 31st
August 2021 |
Contract 1 |
0 |
0 |
NA |
1st ¡V 31st
August 2021 |
Contract 2 |
0 |
0 |
NA |
11.1.2 In addition, no complaints received and emergency event relating to violation of
environmental legislation for illegal dumping and landfilling were received.
12.1.1 The environmental mitigation
measures that recommended in the Implementation Schedule for Environmental Mitigation Measures (ISEMM) in
the approved EM&A Manual covered the issues of dust, noise, water and waste
and they are summarized presented in Appendix
N.
12.1.2 The Works of Contract 1
and Contract 2 under the Project shall be implementing
the required environmental mitigation measures according to the approved EM&A Manual
subject to the site condition.
Environmental mitigation measures implemented in this Reporting Month is summarized in Table 12-1.
Table 12-1 Environmental
Mitigation Measures
Issues |
Environmental Mitigation Measures |
Water
Quality |
¡P Provided efficient silt removal facilities to reduce SS level before effluent discharge. ¡P Provided ditches, earth bunds or sand bag
barriers to minimize polluted runoff. ¡P Temporary drainage was provided
to prevent runoff going through site
surface and minimize polluted runoff. ¡P Provided perimeter cut-off drains at site
boundaries to intercept storm runoff from crossing the site. ¡P Exposed
slopes surface were compacted and covered with tarpaulin
or similar means. ¡P Provided portable chemical toilets on site. |
Air
Quality |
¡P Maintain
damp / wet surface on access road. ¡P Maintain low vehicular speed within the works areas. ¡P Provided vehicle wheel washing facilities at each
construction site
exit; ¡P Provided water spraying for all active works area. ¡P Stockpiles of dusty material were covered with
impervious sheeting. ¡P Provided workers to clear dusty materials at
the vehicle entrance or exit regularly. ¡P Stockpile
more than 20 bags of cement or dry pulverized fuel ash (PFA) has been covered entirely by impervious
sheeting or placed in an area sheltered on the top and the 3 sides. |
Noise |
¡P Restricted operation time of plants from 07:00
to 19:00 on any working day except for Public Holiday and Sunday. ¡P Keep
good maintenance of plants. ¡P Placed noisy plants away from residence and school. ¡P Provided noise barriers or hoarding to
enclose the noisy plants or works. ¡P Shut
down the plants when not in used. |
Waste
and Chemical Management |
¡P Provided on-site sorting prior to disposal. ¡P Followed requirements and procedures of the
¡§Trip-ticket System¡¨ ¡P Predicted required quantity of concrete
accurately. ¡P Collected the unused fresh concrete at
designated locations in the sites for subsequent disposal. |
Ecology |
¡P
Implementing
water control measures (ETWB TCW No. 5/2005) to avoid direct or indirect
impacts any watercourses and impact to any aquatic fauna during the
construction phase. ¡P
Demarcation
fencing has been erected to prevent unauthorised
encroachment into the riparian corridor by constructions works and traffic. ¡P
The
construction work and site formation have been phased in order to reduce
overall noise disturbance impacts in particular areas. ¡P
Works have
been restricted to daytime and any construction lighting was designed and
positioned as to not impact on adjacent ecologically sensitive areas. |
General |
¡P The
site was generally kept tidy and clean. |
12.2.1
According to the
information provided by HCTYJV, the
forthcoming construction activities for Contract 1
are listed below:
General site housekeeping
Bulk Excavation
Construction of cut slope, installation of soil
nailing and construction of surface channel and planter wall.
Construction of fill slope and surface channel
Construction of pick-up and drop-off point near Man
Kam To Road
Construction of sewer and storm drain
Laying of street lighting ducts
Construction of watermains
Construction of Refuse Collection Point
Construction of Concrete Pavement
12.2.2
According to the
information provided by Sang Hing, the
forthcoming construction activities for Contract 2
are listed below:
Construction of Manhole, gullies, drainage pipe at
Lin Ma Hang Road between CH50-160 Southbound & CH780-890 Northbound.
Construction of Dia.1200mm Concrete Sleeve tunnel for
DN400 watermain by trenchless method at Man Kam To
Road
DN400 DI Watermain works
in approx. CH300-1040 at Man Kam To Road North Slow Lane
Construction of Manhole, gullies, drainage pipe at
Sandy Ridge Road E CH0-300 (~300m)
Construction of Manhole, gullies, drainage pipe at Sandy
Ridge Road F CH640-720 (~80m)
Construction of Manhole, gullies, drainage pipe at
Sandy Ridge Road F CH30-130 (~100m)
Backfilling of Retaining Wall 12, FS19 & FS20
Soil Nail Works at Lin Ma Hang Road Slope C231
& C224
Fanling Station Road Covered Walkway
Lung Sum Avenue road surface modification works
12.3.1 Key issues to be considered in the coming
month for the works of Contract 1 include:
Implementation of control measures for
rainstorm;
Regular clearance of stagnant water during
wet season;
Implementation of dust suppression measures
at all times;
Potential wastewater quality impact due to
surface runoff;
Potential fugitive dust quality impact due
from the dry/loose/exposure soil surface/dusty material;
Ensure dust suppression measures are
implemented properly;
Sediment catch-pits and silt removal
facilities should be regularly maintained;
Discharge of site effluent to the nearby
wetland is prohibited;
Nearby wetland prohibited stockpiling
and/or disposal of materials;
Follow-up of improvement on general waste
management issues; and
Implementation of construction noise
preventative control measures.
12.3.2 The
Contractors are reminded to pay special attention on water quality
mitigation measures and should fully
implement the measures as
recommended in the EM&A Manual, in particular to prevent surface runoff and other pollutants
from flowing to local stream and Conservation Area. The implementation of water quality mitigation
measures conducted by the Contractors is shown in Appendix O.
12.3.3 During wet
season, the Contractors are reminded to pay special attention on water quality
mitigation measures and should fully
implement the measures as
recommended in the EM&A Manual, in particular to prevent surface runoff and other pollutants
from flowing to local stream and Conservation Area.
13.1.1 This is the 37th Monthly EM&A Report presenting the
monitoring results and inspection findings for the period of 1st to 31st August 2021.
13.1.2 No 24-hour or 1-hour TSP monitoring result
that triggered the Action or Limit Levels was recorded. No NOEs or the associated corrective action was
therefore required.
13.1.3 No noise complaint (which is an Action
Level exceedance) was received and no construction noise measurement result
that exceeded the Limit Level was
recorded in this Reporting Month. No NOEs or the associated
corrective actions were therefore issued.
13.1.4 In
the Reporting Month, 32 Limit level water quality exceedances,
namely 15 exceedances of turbidity and 17 exceedances of SS were
recorded. According to
the weather information from the HKO, there was heavy rainstorm intermittently
during the days of exceedance recorded. Under the impact of rainstorm, the water
quality of the watercourse was deteriorated by the stirred up sediment and
runoff from the surrounding environment.
It was concluded
that the exceedances were likely related to the impact of rainstorm and not
caused by the work under the project.
13.1.5 Monthly ecological monitoring for sensitive habitat for area of Contract
1 and Contract 2 were undertaken
on 10th August 2021. After analysing
survey results in August from
2018
to 2021, it is found that the species diversity in Contract 1 reduced
in wetland habitat and the reduction could be due to natural
fluctuation. For Contract 2, there
was a drop in species richness and abundance for non-wetland
habitats. It could be due to natural fluctuation. It
could be due to natural fluctuation. Good practice during construction is required to prevent
environmental contamination as well as unnecessary site clearance. Continuous
monitoring is also recommended to inspect any significant reduction in species diversity.
13.1.6 As advised
by both Contractors, there were no vegetation clearance conducted within
the site in the Reporting Month and therefore precautionary check for the presence
of nesting birds was not required.
13.1.7
Landscape and visual inspection at both Contracts were undertaken on 26th August 2021.
The Contractor was reminded to prevent the
construction material pile within Tree Protection Zone and ensure no works is
allowed within the TPZ.
13.1.8
In the Reporting Month, no environmental complaints, summons and prosecution were
received. In addition, no
complaints received and emergency events relating to violation of environmental legislation for
illegal dumping and landfilling were received.
13.1.9 In the Reporting Month, joint site
inspections for
Contract 1 to evaluate the site
environmental performance were carried out by the Resident
Engineer, ET and the
Contractor of the Contract 1 on 5th, 12th, 19th
and 26th August 2021.
Moreover, joint site inspections for Contract 2 by the RE, ET and the Contractor of Contract 2 were carried out on 5th,
12th, 19th and 26th August 2021.
IEC attended the both Contract
joint site inspection on 19th August 2021. No
non-compliance was noted
during the site inspections.
13.2.1
The Contractors are reminded to pay special
attention on water quality mitigation measures and should fully implement the measures as recommended in the
EM&A Manual, in particular to prevent surface runoff and other pollutants
from flowing to local stream and Conservation Area.
13.2.2
During wet season, the
Contractors are reminded to pay special attention on water quality mitigation
measures and should fully implement the
measures as recommended in the EM&A Manual, in particular to prevent
surface runoff and other pollutants from flowing to local stream and
Conservation Area.
13.2.3 Construction
noise would be a key environmental issue during construction phase of the Project. Noise mitigation measures such as using
quiet plants and mobile noise barriers should be implemented in accordance with
the EM&A requirement.
13.2.4 Since some of the construction site under the Project is
located near villages, both
Contractors should fully implement
air quality mitigation measures to reduce construction dust emission.
13.2.5 Furthermore, daily cleaning and weekly tidiness shall be properly performed and maintained. In
addition, mosquito control should be performed to prevent mosquito
breeding on site.