|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
Job No.: TCS00881/18 & TCS00944/18 |
|
|
||
|
|
|
|
|
||
|
|
Site
Formation and Associated Infrastructural Works for Development of Columbarium,
Crematorium and Related Facilities at Sandy Ridge Cemetery |
|
|
||
|
|
|
|
|
||
|
|
Monthly
Environmental Monitoring and Audit Report (No.5) ¡V December 2018 |
|
|
||
|
|
Prepared For |
|
|
||
|
|
Hsin Chong Tsun Yip Joint Venture & Sang Hing Civil Contractors Co., Ltd |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
14 January 2019 |
TCS00881/18/600/R0218v2 |
|
|
Nicola Hon (Environmental
Consultant) |
Tam Tak Wing (Environmental
Team Leader) |
Version |
Date |
Remarks |
1 |
9 January 2019 |
First Submission |
2 |
14 January 2019 |
Amended against IEC¡¦s comment |
|
|
|
|
|
|
executive summary
ES.01.
Civil Engineering and
Development Department (hereafter referred as ¡§CEDD¡¨) is the Project
Proponent for the Project
¡§Site Formation and Associated
Infrastructural Works for Development of Columbarium, Crematorium and Related
Facilities at Sandy Ridge Cemetery¡¨ (hereafter referred as ¡§the
Project¡¨). The Project is a Designated Project to be implemented
under Environmental Permit No. EP-534/2017 and FEP-01/534/2017. On 24 December
2018 EPD issued Environmental Permit No. EP-534/2017/A and FEP-01/534/2017/A for the
Project. To facilitate the Project management, the Project works were separated into three different Contracts and they
are listed below.
CEDD Contract No.
CV/2016/10 - Site Formation and Associated Infrastructural Works for
Development of Columbarium at Sandy Ridge Cemetery (hereafter referred as ¡§Contract
1¡¨)
CEDD Contract No.
CV/2017/02 - Infrastructural Works at Man Kam To Road and Lin Ma Hang Road for
Development of Columbarium at Sandy Ridge Cemetery (hereafter referred as ¡§Contract
2¡¨)
Other CEDD¡¦s Contract as related Development of Columbarium at
Sandy Ridge Cemetery (hereafter referred as ¡§Contract
3¡¨)
ES.02.
Action-United
Environmental Services & Consulting (hereinafter
referred as ¡§AUES¡¨) has been commissioned by the Contractors as an Environmental Team (hereinafter referred as ¡§the ET¡¨) to implement the Environmental Monitoring & Audit (EM&A) programme in accordance with the approved EM&A Manual as well as
the associated duties.
ES.03.
The Construction
works of Contract CV/2016/01 - Contract 1 implemented under FEP-01/534/2017 was commenced on 16 August 2018 and
construction phase impact
monitoring has been started on 16 August 2018. Furthermore, EPD issued Environmental Permit No. FEP-01/534/2017/A on 24 December 2018. The construction works of Contract
CV/2017/02 - Contract 2 implemented under EP-534-2017
was commenced on 5 November
2018 and construction phase
impact monitoring has been started on 5 November 2018. Furthermore,
EPD issued Environmental Permit No.
EP-534/2017/A on
24 December 2018.
ES.04.
This
is the 5th monthly
Environmental Monitoring and Audit Report reporting the monitoring results and
inspection findings under the Project for
the period
from 1 to 31 December 2018 (the Reporting Month).
Environmental
Monitoring and Audit Activities
ES.05.
In the Reporting Month, the major construction works under the Project included Contract 1 and Contract 2. Environmental monitoring activities under
the EM&A programme in this Reporting Month
are summarized in the following table.
Issues |
Environmental Monitoring Parameters /
Inspection |
Monitoring Locations |
Total Occasions |
|
CV/2016/10 |
CV/2017/12 |
|||
Air
Quality |
1-hour
TSP |
ASR-1 |
ASR-2 ASR-3 |
45 |
24-hour TSP |
15 |
|||
Construction Noise |
Leq (30min) Daytime |
CN-1 |
CN-3 CN-4 |
12 |
Water
Quality |
In-situ
measurement and Water sampling |
M3 |
M1, M2 and M4 |
13 |
Ecology |
Monthly Monitoring |
Transect within site area of CV/2016/10 |
Transect within site area of CV/2017/12 |
1 |
Landscape
& Visual |
Site Inspection |
Site area of CV/2016/10 |
Site area of CV/2017/12 |
1 |
Inspection
& Audit |
ET
Regular Environmental Site Inspection |
Site area of CV/2016/10 |
Site area of CV/2017/12 (#) |
4 |
IEC
Monthly Environmental Site Audit |
3 |
# The 1st
site inspection was arranged on 10 December 2018 which attended by CEDD, RE,
IEC, Contractor and ET.
Breach of Action and Limit (A/L) Levels
ES.06.
No exceedance
of air quality, construction noise and
water quality monitoring was recorded in this Reporting Month. Notification of
Exceedance (NOE) of water quality was issued. The statistics of
environmental exceedance, NOE issued and investigation of exceedance are
summarized in the following table.
Table ES-5 Breach
of Action and Limit (A/L) Levels in the Reporting Period
Environmental Issues |
Monitoring Parameters |
Action Level |
Limit
Level |
Event & Action |
||
NOE Issued |
Investigation findings |
Corrective Actions |
||||
Air
Quality |
1-hour TSP |
0 |
0 |
0 |
- |
- |
24-hour
TSP |
0 |
0 |
0 |
- |
- |
|
Construction Noise |
Leq30min
Daytime |
0 |
0 |
0 |
- |
- |
Water Quality |
DO |
0 |
0 |
0 |
- |
- |
Turbidity |
0 |
0 |
0 |
- |
- |
|
SS |
0 |
0 |
0 |
- |
- |
Note: NOE
¡V Notification of Exceedance
ES.07.
No
environmental complaint was recorded or received in this Reporting Month. The statistics of environmental complaint
are summarized in the following table.
Table ES-6 Environmental
Complaint Summaries in the Reporting Month
Reporting Period |
Environmental Complaint Statistics |
|||
Frequency |
Cumulative |
Complaint Nature |
||
1 ¡V
31 Dec
2018 |
Contract 1 |
0 |
0 |
NA |
1 ¡V 31 Dec
2018 |
Contract 2 |
0 |
0 |
NA |
ES.08.
In addition, no complaints and emergency events
relating to violation of environmental legislation for illegal dumping and landfilling was
received.
Notification of Summons
and Successful Prosecutions
ES.09.
No
environmental summons or successful prosecution was recorded in this Reporting Month. The statistics of summons or successful
prosecutions are summarized in the following tables.
Table ES-7 Environmental
Summons Summaries in the Reporting Month
Reporting Period |
Environmental Complaint Statistics |
|||
Frequency |
Cumulative |
Summons Nature |
||
1 ¡V 31 Dec 2018 |
Contract
1 |
0 |
0 |
NA |
1 ¡V 31 Dec 2018 |
Contract
2 |
0 |
0 |
NA |
Table ES-8 Environmental
Prosecution Summaries in the Reporting Month
Reporting Period |
Environmental Complaint Statistics |
|||
Frequency |
Cumulative |
Prosecution Nature |
||
1 ¡V 31 Dec 2018 |
Contract
1 |
0 |
0 |
NA |
1 ¡V 31 Dec 2018 |
Contract
2 |
0 |
0 |
NA |
Reporting Change
ES.010.
In the Reporting Month, EPD issued Environmental Permit No. EP-534/2017/A and FEP-01/534/2017/A on 24
December 2018 for the Project.
Site Inspection
ES.011. In this Reporting Month,
joint site inspections to evaluate the site environmental
performance at Contract 1 have been carried out by the RE, ET and
the Contractor on
6th,
13th, 20th and 27th December 2018. No
non-compliance was noted during the site inspection. Furthermore, IEC attended a joint site inspection on 13th December
2018. No non-compliance was noted.
ES.012. The 1st site
inspection was arranged on 10 December 2018 which attended by CEDD, RE, IEC,
Contractor and ET. In the Reporting Period, joint
site inspections for Contract 2 to evaluate the site environmental performance
carried out by the RE, ET and the Contractor was on
10th, 20th and 27th December 2018. Moreover, IEC attended a joint site inspection on 10th
December 2018. No non-compliance was noted.
ES.013. The Contractors should pay special attention on water quality
mitigation measures and fully implement according to the ISEMM
of the EM&A Manual, in particular to prevent surface runoff with high SS
content and other pollutants from flowing to local stream and Conservation Area
(CA).
ES.014.
Moreover,
air quality and construction noise are the major environmental issues as under
the Project Works. Air quality mitigation measures such as wheel
wash facilities, watering of haul roads and covering of dusty materials with
tarpaulin sheet should be implemented as far as practicable. Construction noise
mitigation measures such as use of movable noise barriers and Quality Powered
Mechanical Equipment (QPME) should be properly provided
to reduce construction noise impact.
ES.015.
Furthermore,
daily cleaning and weekly tidiness shall be properly performed and maintained.
In addition, mosquito control should be performed to prevent mosquito
breeding on site.
Table of Contents
2 Project Organization and Construction
progress
2.1 Construction Contract Packaging
2.3 Summary of Environmental Submissions
2.4 Summary of Submission Under the Environmental Permit Requirements
3 Summary
of Impact Monitoring Requirement
3.4 Monitoring
Frequency and Period
3.7 Data
Management and Data QA/QC Control
3.8 Determination
of Action/Limit (A/L) Levels
5.2 Noise
Monitoring Exceedance
6.2 Water
Quality Monitoring Exceedance
7.3 Ecological
Monitoring Survey Findings
8.2 Findings
/ Deficiencies During Site Inspection in the Reporting Month
9.2 Records
of Waste Quantities
10.2 Findings
/ Deficiencies During Site Inspection in the Reporting Month
11 Environmental
Complaint and Non-Compliance
11.1 Environmental
Complaint, Summons and Prosecution
12 Implementation Status of Mitigation Measures
12.2 Tentative
Construction Activities in the Coming Month
12.3 Key
Issues for the Coming Month
13 Conclusions
and Recommentations
List of TABLES
Table 2-1 Status
of Environmental Licenses and Permits for Contract 1
Table 2-2 Status
of Environmental Licenses and Permits for Contract 2
Table 2-3 Status
of Submission as under FEP for Contract 1
Table 2-4 Status
of Submission as under FEP for Contract 2
Table 3-1 Summary
of EM&A Requirements
Table 3-2 Designated
Air Quality Monitoring Location under the Project
Table 3-3 Designated
Construction Noise Monitoring Location under the Project
Table 3-4 Designated
Water Quality Monitoring Stations under the Project
Table 3-5 Air
Quality Monitoring Equipment
Table 3-6 Noise
Monitoring Equipment
Table 3-7 Water
Quality Monitoring Equipment
Table 3-8 Action
and Limit Levels for Air Quality Monitoring
Table 3-9 Action
and Limit Levels for Construction Noise
Table 3-10 Action and Limit
Levels for Water Quality
Table 4-1 Summary
of Air Quality Monitoring Results at ASR-1 under Contract 1
Table 4-2 Summary
of Air Quality Monitoring Results at ASR-2 under Contract 2
Table 4-3 Summary
of Air Quality Monitoring Results at ASR-3a under Contract 2
Table 5-1 Summary
of Construction Noise Monitoring Results under Contract 1
Table 5-2 Summary
of Construction Noise Monitoring Results under Contract 2
Table 6-1 Summary
of Water Quality Monitoring Results ¡V M3 under Contract 1
Table 6-2 Summary
of Water Quality Monitoring Results (M1, M2 and M4) under Contract 2
Table 6-3 Summary
of Field Measurements for Water Quality
Table 6-4 Action
and Limit (A/L) Levels Exceedance Record
Table 6-5 Summary
of Investigation of Water Quality Exceedance in the Reporting Period
Table 7-1 Action
and Limit Levels for Wet Woodland Habitats Monitoring
Table 7-2 Action
and Limit Levels for Non-Wet Woodland Habitats Monitoring
Table 7-3 Schedule
of Faunal Surveys in each year During Construction Phase
Table 7-4 Result
of Avifauna Survey under Contract 1
Table 7-5 Result
of Reptile Survey under Contract 1
Table 7-6 Result
of Amphibian Survey under Contract 1
Table 7-7 Result
of Butterfly Survey under Contract 1
Table 7-8 Result
of Odonate Survey under Contract 1
Table 7-9 Result
of Freshwater Communities Survey under Contract 1
Table 7-10 Result of
Avifauna Survey under Contract 2
Table 7-11 Result of Reptile
Survey under Contract 2
Table 7-12 Result of
Amphibian Survey under Contract 2
Table 7-13 Result of
Butterfly Survey under Contract 2
Table 7-14 Result of Odonate
Survey under Contract 2
Table 7-15 Result of
Freshwater Communities Survey under Contract 2
Table 8-1 Landscape
& Visual Inspection Finding for Contract 1
Table 8-2 Landscape
& Visual Inspection Finding for Contract 2
Table 9-1 Summary
of Quantities of Inert C&D Materials
Table 9-2 Summary
of Quantities of C&D Wastes
Table 10-1 Site Observations
for the Works of Contract-1
Table 11-1 Statistical
Summary of Environmental Complaints
Table 11-2 Statistical
Summary of Environmental Summons
Table 11-3 Statistical
Summary of Environmental Prosecution
Table 12-1 Environmental
Mitigation Measures
List
of Appendices
Appendix A Layout Plan of the Project
Appendix B Organization
Structure and Contact Details of Relevant
Parties
Appendix C Three Months rolling Programme
Appendix D Designated Monitoring Locations
Appendix E Calibration Certificates of MONITORING EQUIPMENT and Laboratory Certificate
Appendix F Event
and Action Plan of Air Quality, Noise and Water Quality
Appendix G Monitoring
Schedules of the Reporting Month and Coming Month
Appendix H Monitoring
Data of 24-Hour TSP Air Quality, Noise and Water
Quality
Appendix I Graphical
Plots of Air Quality, Noise and Water Quality
Appendix J Meteorological
Data of the Reporting Period
Appendix K Ecology Survey Report
Appendix L Landscape & Visual
Inspection Checklist
Appendix M Monthly
Summary Waste Flow Table
Appendix N Implementation Schedule for Environmental Mitigation Measures (ISEMM)
1.1.1
Civil Engineering
and Development Department is the Project Proponent for the Project ¡§Site Formation and Associated
Infrastructural Works for Development of Columbarium, Crematorium and Related
Facilities at Sandy Ridge Cemetery¡¨. The Project
is a Designated Project to be implemented under Environmental Permit No. EP-534/2017/A and FEP-01/534/2017/A. The layout plan of the Project is shown in Appendix
A. Major works to be executed under the Project shall include to the
following:
A Designated Works under EP-534/2017/A
(i)
Site formation of about 8 hectares of
land and associated drainage, sewerage and landscape works for development of
Columbarium and Crematorium facilities at the Sandy Ridge Cemetery;
(ii)
Construction of a new road (about 600m) including
a section of viaduct connecting the platform for Crematorium and Man Kam To
Road and the pick-up/drop-off point at Man Kam To Road.;
(iii)
Widening of about 900m of the existing
Sha Ling Road;
(iv)
Widening of about 1.4km of the existing
Lin Ma Hang Road; and
(v)
Improvement works to the existing
barging point at Siu Lam
Non-Designated Works
(i)
Construction of a sewage detention tank
complete with odour and septicity control mechanism;
(ii)
Construction of noise barriers along Sha
Ling Road;
(iii)
Construction of a new Refuse Collection
Point (RCP) near the junction between Man Kam To Road and Sha Ling Road;
(iv)
Landscaping works (including both hard
and soft landscape works);
(v)
Associated tree felling, transplanting
and compensatory planting works;
(vi)
Associated street lighting, street
furniture and road marking, etc.; and
(vii) Other
works which are specified in PS of the Contract.
1.1.2
To facilitate the Project management, the Project works were separated into three different Contracts which are
described below sub-sections.
1.1.3
Contract No. CV/2016/10 - Site
Formation and Associated Infrastructural Works for Development of Columbarium
at Sandy Ridge Cemetery:-
Site formation of about 1.77 ha of land for the proposed pick-up
and drop-off area for shuttle bus operation;
Upgrading of a section of 900m existing Sha Ling Road from 3m wide
carriageway to 7.3m wide carriageway with footpath at both sides;
Construction of one EVA with a total length of about 160m;
Construction of noise barriers along Sha Ling Road;
Modification of junction between Man Kam To Road and Sha Ling
Road;
Construction of a new pick up / drop off point at Man Kam To Road;
Relocation and construction of a new refuse collection point near
junction between Man Kam To Road and Sha Ling Road;
Associated geotechnical works including cut and fill slopes, soil
nailing works and retaining structures;
Associated drainage, sewerage and waterworks along Sha Ling Road;
and
Associated landscaping works.
1.1.4
Contract
No. CV/2017/02 - Infrastructural Works at Man Kam To Road and Lin Ma Hang Road
for Development of Columbarium at Sandy Ridge Cemetery:-
Construction of a new road connecting Columbarium site to
Crematorium site;
Construction of one EVA with a total length of about 300m;
Widening of a section of 1.4 km long Lin Ma Hang Road (between Man
Kam To Road and Ping Yuen River) from 6m wide carriageway to 7.3m with 2m width
footpath on both sides;
Provision of a pair of lay-by at Lin Ma Hang Road;
Construction of a new vehicular access connecting the Sheung Shui
Landmark North PTI and Lung Sum Avenue;
Construction of covered walkway along Fanling Station Road;
Removal of planters and central divider along Fanling Station Road
and San Wan Road;
Associated drainage, sewerage, waterworks and utility works along
Man Kam To Road and Lin Ma Hang Road;
Associated geotechnical works including cut and fill slopes, soil
nailing works and retaining structures; and
Associated landscaping works.
1.1.5
CEDD
Contract No. (to be advised):-
Site Formation for the platform of the columbarium site;
Construction of two 2 at-grade access roads;
Construction of road junction between Man Kam To Road and the new
access road;
Associated drainage, sewerage and waterworks along the two new
access roads;
Associated geotechnical works including cut and fill slopes, soil
nailing works and retaining structures; and
Associated landscaping works
1.1.6
Hsin Chong Tsun Yip Joint Venture (hereafter referred as ¡§HCTYJV¡¨) has been awarded Contract 1 on 5 December 2017. According to the Contract requirement, HCTYJV shall take over the responsibility for part of the Environmental Permit No. EP-534/2017 for ease of management, therefore application for Further Environmental Permit was submitted by HCTYJV to EPD on 26 January 2018 and Further Environmental Permit No. FEP-01/534/2017
was granted to
HCTYJV by EPD on
23 February 2018. Furthermore, EPD issued Environmental Permit No. FEP-01/534/2017/A on 24 December 2018.
1.1.7
Sang Hing Civil Contractors Company Limited
(hereinafter
referred as ¡§Sang Hing¡¨) was awarded Contract 2 on 23 May 2018.
The Contract Works is a Designated Project as under Environmental Permit
(EP) No. EP-534/2017. Furthermore, EPD issued Environmental Permit No. EP-534/2017/A on 24 December 2018.
1.1.8
Action-United
Environmental Services & Consulting has been commissioned by the Contractors as an Environmental Team to implement the EM&A programme in accordance with the
approved EM&A Manual as well as the associated duties. As part of the
EM&A programme, baseline monitoring
to determine the ambient environmental conditions was completed before construction work commencement. The Baseline Monitoring Report (air, noise and water) certified
by ET Leader (ETL) and verified by Independent Environmental Checker (IEC) was
submitted to Environmental Protection Department (EPD) and it was approved by EPD on 25 October 2018.
1.1.9
This
is the 5th monthly
Environmental Monitoring and Audit Report to reporting the monitoring results
and inspection findings for the period from 1 to 31 December 2018.
1.2.1
The
Monthly Environmental Monitoring and Audit (EM&A) Report is structured into
the following sections:-
Section 1 Introduction
Section 2 Project Organization and Construction Progress
Section 3 Summary of Monitoring Requirements
Section 4 Air Quality Monitoring Results
Section 5 Noise Monitoring Results
Section 6 Water Quality Monitoring Results
Section 7 Ecology Monitoring Results
Section 8 Landscape & Visual
Section 9 Waste Management
Section 10 Site Inspections
Section 11 Environmental Complaints and Non-Compliance
Section 12 Implementation Status of Mitigation Measures
Section 13 Conclusions and Recommendation
2.1.1
To facilitate the project management and implementation, the
Project would be divided by the following contracts:
Contract
1 (Contract No.
CV/2016/10)
Contract
2 (Contract No.
CV/2017/02)
Contract
3 (Contract No. TBA)
2.1.2
Organization
structure and contact details of relevant parties with respect to on-site
environmental management are shown in Appendix B.
2.1.3
The
three-month rolling construction programme for Contract
1 and Contract 2 are enclosed
in Appendix C. The construction activities undertaken in
this Reporting Month are listed below:-
Contract 1
(CV/2016/10)
2.1.4
Contract
1 was awarded in December 2017
and major
construction work was
commenced on 16 August 2018. The construction activities undertaken in this Reporting Month is listed below:
l General site clearance;
l Bulk Excavation
l Construction of Cut Slope,
installation of soil nailing and construction of surface channel;
l Construction of retaining wall; and
l Construction of fill
slope.
Contract 2
(CV/2017/12)
2.1.5
Contract
2 was awarded in May 2018 and construction work was tentatively commenced on 5 November 2018. The construction activities undertaken in this Reporting Month is listed below:
l Initial Survey at Fanling
Station (Part D)
l Tree Survey at Part C1, C2, A1
and A3
l Site Patrol and daily cleaning
within the site boundary including the anti-mosquito measures.
l Site preparation of PM¡¦s Office
l Utilities Detection along Lin
Ma Hang Road and Man Kam To Road.
l Liaison with Contract 1 Contractor
regarding the access road
l Construction of Manhole,
gullies, drainage pipe at Lin Ma Hang Road between CH240-280 & CH640-690
Southbound.
l Construction of Temporary haul
road at Part A1
l Excavation at Slope CS22
l Construction of step channel of
CS22 at Part A1
2.1.6
Summary of the relevant permits, licences,
and/or notifications on environmental protection for this Project in this
Reporting Month is presented in Tables 2-1 and 2-2.
Table
2-1 Status of Environmental Licenses and Permits for Contract 1
Item |
Description |
License/ Permit ref
no. |
License/ Permit Status |
1 |
Air
Pollution Control (Construction Dust) Regulation |
Ref. no. 428909 Acknowledged by EPD on 20/12/2017 |
Valid |
2 |
Chemical
waste Producer Registration |
WPN:
5231-641-H3937-01 Issued by EPD on 27/03/2018 |
Valid |
3 |
Water
Pollution Control Ordinance |
License no. WT00030795-2018 Issued
date: 9/5/2018 Expire
Date: 31/5/2023 |
Valid |
4 |
Billing
Account for Disposal of Construction Waste |
Account
no.: 7029769 |
Valid |
Table
2-2 Status of Environmental Licenses and Permits for Contract 2
Item |
Description |
License/ Permit ref
no. |
License/ Permit Status |
1 |
Chemical
waste Producer Registration |
Pending approval from EPD |
|
2 |
Water
Pollution Control Ordinance |
Pending approval from EPD |
|
3 |
Billing
Account for Disposal of Construction Waste |
Account
no.: 7031098 |
Valid |
2.1.7
Tables 2-3 to 2-4 summarized the
submission status under the EP and/or FEP stipulation in the Reporting Month.
Table
2-3 Status of Submission as under FEP for Contract 1
Item |
EP and / or FEP
Stipulation |
Description |
Status |
1 |
Condition 2.10 of FEP |
Management organization of : i) the main construction companies; ii) ET;
and iii) IEC and the supporting team |
Submitted on 11 April
2018 |
2 |
Condition 2.11 of FEP |
i) Detailed phasing programme of all construction works; and ii)
Location plan of all construction works |
Submitted on 12 April
2018 |
3 |
Condition 2.12 of
FEP |
Contamination
Assessment Plan (CAP) |
Submitted on 11
October 2018 |
4 |
Condition 2.13 of FEP |
Grassland Reinstatement Plan |
Submitted on 28 May 2018 |
5 |
Condition 2.14 of FEP |
Vegetation Survey
Report for Contract 1 |
Approved by EPD on 12 October
2018 |
6 |
Condition 2.15 of FEP |
Vegetation Transplantation Proposal
Contract 1 |
Approved by EPD on 12 October
2018 |
7 |
Condition 2.17 of FEP |
Woodland
Compensation Plan |
Submitted on 15 May 2018 |
8 |
Condition 2.18 of FEP |
Monitoring and
Survey Plan for Golden-headed Cisticola
Contract 1 |
Submitted on 9 May 2018 |
9 |
Condition 2.20 of FEP |
Landscape
& Visual Mitigation and Tree Preservation Plan(s)
Contract 1 |
Submitted on 18 May 2018 |
10 |
Condition 2.22 of FEP |
Traffic Noise
Mitigation Plan Contract 1 |
Submitted on 17 July 2018 |
11 |
Condition 3.3 of the FEP |
Baseline Monitoring
Report (Air, Noise and Water) |
Approved by EPD on 25 October
2018 |
12 |
Condition 4.2 of the FEP |
The Contract Internet website |
Internet website address has notified EPD on 15 Jun 2018 |
Table
2-4 Status of Submission as under EP for Contract 2
Item |
EP and / or FEP
Stipulation |
Description |
Status |
1a |
Condition 2.10 of EP |
Management organization of : i) the main construction companies; ii) ET;
and iii) IEC and the supporting team |
Submitted on 24 September 2018 |
2a |
Condition 2.11 of EP |
i) Detailed phasing programme of all construction works; and ii)
Location plan of all construction works |
Submitted on 26 September 2018 |
3 |
Condition 2.13 of
EP |
Contamination
Assessment Plan (CAP) |
Submitted on 11
October 2018 |
4 |
Condition 2.14 of EP |
Grassland Reinstatement Plan |
Submitted on 28 May 2018 |
5 |
Condition 2.15 of EP and |
Vegetation Survey
Report Contract 2 |
Submitted on 28 September 2018 |
6 |
Condition 2.16 of EP |
Vegetation Transplantation Proposal
Contract 2 |
Submitted on 28 September 2018 |
7 |
Condition 2.18 of EP |
Woodland
Compensation Plan |
Submitted on 15 May 2018 |
8 |
Condition 2.19 of EP |
Monitoring and
Survey Plan for Golden-headed Cisticola Contract
2 |
Submitted on 4
October 2018 |
9 |
Condition 2.22 of EP |
Landscape
& Visual Mitigation and Tree Preservation Plan(s)
Contract 2 |
Submitted on 5
October 2018 |
10 |
Condition 2.24 of EP |
Traffic Noise
Mitigation Plan Contract 2 |
Submitted on 4
October 2018 |
11 |
Condition 3.3 of the EP |
Baseline Monitoring
Report (Air, Noise and Water) |
Approved by EPD on 25 October
2018 |
12 |
Condition 4.2 of the EP |
The Contract Internet website |
Internet website address has notified EPD on 15 June 2018 |
3.1.1
The Environmental Monitoring and Audit requirements are set out in
the Approved EM&A Manual. Environmental issues such as air quality, construction
noise, water quality and ecology were identified as the key issues during the
construction phase of the Project.
3.1.2
A summary of construction phase EM&A
requirements are presented in the sub-sections below.
3.2.1
The EM&A impact monitoring shall cover the following
environmental aspect:
•
Air quality;
•
Construction noise;
•
Water quality; and
•
Ecology
3.2.2
A summary of the monitoring parameters is presented in Table
3-1 below
Table 3-1 Summary
of EM&A Requirements
Environmental
Issue |
Parameters |
Air Quality |
1-hour TSP; 24-hour TSP |
Noise |
Leq(30min) during normal
working hours.; and
Leq(15min)
during the construction works is undertaken in Restricted Hours |
Water Quality |
In-situ
Measurements Dissolved Oxygen Concentration
(mg/L) & Saturation (% ); Temperature (¢J); Turbidity (NTU); Salinity
(ppm) pH unit; Water depth (m); and Stream
Flow Velocity (m/sec). |
Laboratory Analysis Suspended Solids (mg/L) |
|
Ecology |
Ecologically sensitive habitats (wetland
habitats and non-wetland habitats) |
3.3.1
According to
the Approved EM&A Manual of the Project - Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge Cemetery, the designated monitoring locations for air
quality, noise, water quality and ecology under the monitoring programme, is shown in Appendix D.
3.3.2
Since the Project was divided
into three Works Contracts and all Contracts will be
commenced at different time, the
construction phase impact monitoring will only be performed at the
Contract-related monitoring stations upon commencement of each
Contract Works.
Air Quality
3.3.3
There were three (3) designated
air quality monitoring stations
recommended in the Approved EM&A Manual Section 5.6.1.1. There was proposed
relocation of air quality monitoring location ASR-3 in October 2018 since the
landlord refused to set up the HVS at his premises and nearby area due to noise
nuisance and Muk Wu Nga Yiu House No. 2A was proposed as alternative location ASR-3a. The proposal dated on 9 November 2018
which verified by IEC was submitted to EPD for approval. Based on
rationale in
Section 3.3.2, the
Contract-related air
quality monitoring location for construction phase were summarized in Table 3-2 and illustrated in Appendix D.
Table 3-2 Designated
Air Quality Monitoring Location under the Project
Location
ID |
Description in EM&A
Manual |
Location |
Related Work Contract |
ASR-1 |
Village House along Man Kam To Road |
Sha Ling
Village House No.6 |
Contract 1 |
ASR-2 |
Village
House at San Uk Ling |
San Uk
Ling Village House No.1 |
Contract 2 |
ASR-3 |
Village House at Muk Wu Nga Yiu |
Muk Wu
Nga Yiu House No.28 |
Contract 2 |
ASR-3a (#) |
Village House at Muk Wu Nga Yiu |
Muk Wu
Nga Yiu House No.2A |
Contract 2 |
Remark: (#)
There was
proposed relocation of air quality monitoring location ASR-3 in October 2018. The proposal dated on 9 November 2018 after verified by
IEC was submitted to EPD for approval.
3.3.4
If the designated monitoring
location is required to relocate, alternative monitoring location shall agree with IEC and seek for EPD approval
which shall meet the following criteria:
i)
Be at the site
boundary or such locations close to the major dust emission source;
ii)
Close to the sensitive receptors;
iii)
Take into account the prevailing
meteorological conditions;
iv)
For monitoring location located in the vicinity
of the ASRs, care shall be taken to cause minimal disturbance to the occupants
during monitoring.
v)
When positioning the HVS, the following
points shall be
noted:
a.
a horizontal platform with appropriate
support to secure the samples against gusty wind shall be provided;
b.
no two samplers shall be placed less than 2m
apart;
c.
the distance between the HVS and an obstacle,
such as buildings, must be at least twice the height that the obstacle
protrudes above the HVS;
d.
a minimum of 2 m separation from walls, parapets and
penthouses is required for HVS at the rooftop;
e.
a minimum of 2 m separation from any supporting structure,
measures horizontally is required;
f.
no furnace or incinerator flue is nearby;
g.
airflow around the sampler is unrestricted;
h.
the HVS is more than 20 m from the dripline;
i.
any wire fence and gate to protect the HVS,
shall not cause any obstruction during monitoring;
j.
permission must be obtained to set up the HVS
and to obtain access to the monitoring stations; and
k.
a secured supply of electricity is needed to
operate the HVS.
Construction
Noise
3.3.5
There were are four (4) designated
noise monitoring locations recommended in the Approved EM&A Manual Section
6.5.1.1. Based on rationale in Section 3.3.2, the Contract-related noise quality monitoring location for construction
phase were summarized in Table 3-3 and illustrated in Appendix D.
Table 3-3 Designated
Construction Noise Monitoring Location under the Project
Location
ID |
Description in EM&A
Manual |
Location |
Related Work Contract |
CN-1 |
Village
house to the west of Sha Ling Road |
Village
house to the west of Sha Ling Road (free
field condition) |
Contract 1 |
CN-2 |
Village house to
the north of Man Kam To Road |
Sha Ling Village House No. 25 (free field condition) |
Contract 1 & 3 |
CN-3 |
Village house near
San Uk Ling |
San Uk Ling Village
House No. 18 (free field condition) |
Contract 2 |
CN-4 |
Village
house of Muk Wu |
Muk Wu
Village House No. 267 (1m façade from
the building) |
Contract 2 |
Water Quality
3.3.6
There were four (4) water quality monitoring
locations recommended in the Approved EM&A Manual Section
7.6.1.2. The locations and coordinates of water quality monitoring were listed in Table 3-4. Based on rationale in Section 3.3.2, the Contract-related noise quality monitoring location for construction
phase were summarized in Table 3-4 and illustrated in Appendix D.
Table 3-4 Designated
Water Quality Monitoring Stations under the Project
Proposed Location ID |
Co-ordinates |
Description |
Related Work Contract |
|
North |
East |
|||
M1 |
843 431 |
831 308 |
Midstream
of Nam Hang Stream |
Contract 2 |
M2 |
843 840 |
831 101 |
Downstream
of Nam Hang Stream |
Contract 2 |
M3 |
843 509 |
830 040 |
Wetland
in the Conservation Area (CA) near Yuen Leng Chai |
Contract 1 |
M4 |
843 997 |
831 783 |
Watercourse across Lin Ma
Hang Road, running from east of San Uk Ling to Man Kam To Boundary Control
Point |
Contract 2 |
3.4.1
The requirements of impact monitoring were stipulated in Sections 5.8.1.1, 6.7.1.1 and
7.8.1.4 of the approved EM&A
Manual and presented as follows.
Air Quality
Monitoring
3.4.2
Monitoring frequency for air quality impact monitoring is as follows:
1-Hour TSP |
3 sets of 1-hour TSP monitoring shall be carried
out once every six days during construction periods |
24-Hour TSP |
24-hour TSP monitoring shall be
carried out every six days during construction periods |
Noise Monitoring
3.4.3
Noise impact monitoring shall be carried out once per week during construction
periods. The noise measurement for
the time period between 0700 and 1900 hours shall be measured in terms of Leq
(30 minutes) or 6 sets of Leq (5mins).
Water Quality Monitoring
3.4.4
The monitoring frequency shall be 3 days per week during construction
phase and
the interval between two sets of monitoring shall not be less than 36 hours.
3.5.1
The
monitoring equipment using for the EM&A program as proposed by the ET shall
be verified by the IEC.
Air Quality
Monitoring
3.5.2
The 24-hour and 1-hour TSP levels shall be measured by following
the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. If ET proposes to use a direct reading
dust meter to measure 1-hour TSP levels, it shall submit sufficient information
to IEC for approval.
3.5.3
The filter paper
of 24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.
3.5.4
All equipment used by ET for air quality monitoring is listed in Table
3-5.
Table 3-5 Air
Quality Monitoring Equipment
Equipment |
Model |
24-hour TSP |
|
High Volume Air
Sampler (HVAS) |
TISCH High Volume Air Sampler, HVS Model
TE-5170 |
Calibration
Kit |
TISCH Model TE-5025A |
1-Hour TSP |
|
Portable Dust Meter |
Sibata LD-3 Laser Dust monitor Particle
Mass Profiler & Counter |
Wind Data Monitoring Equipment
3.5.5
According to the approved EM&A Manual, wind data monitoring
equipment shall also be provided and set up for logging wind speed and wind direction
near the dust monitoring locations.
The equipment installation location shall be proposed by the ET and
agreed with the IEC. For
installation and operation of wind data monitoring equipment, the following
points shall be observed:
1)
The wind sensors should be installed 10 m above ground so that
they are clear of obstructions or turbulence caused by buildings.
2)
The wind data should be captured by a data logger. The data shall
be downloaded for analysis at least once a month.
3)
The wind data monitoring equipment should be re-calibrated at
least once every six months.
4)
Wind direction should be divided into 16 sectors of 22.5 degrees
each.
3.5.6
ET has liaised with the premises owners/ landlords to grant the permission
for the HVS installation. However, they rejected to set
up wind data
monitoring equipment installation in their premises.
3.5.7
Under this situation, the ET proposed to obtain representative
wind data from the Hong Kong Observatory Ta Kwu Ling Weather Station. Ta Kwu Ling Station is located near the Project site which situated at the sea level above 15mPD and
the wind data
monitoring equipment is installed 10 m above the existing ground.
Noise Monitoring
3.5.8
Sound level meter in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring. The sound level meter shall be checked
using an acoustic calibrator. The
wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in ms-1 before each noise
monitoring event.
Noise measurements should not be made in fog, rain, wind with a steady speed
exceeding 5 m s-1 or wind with gusts exceeding 10 m s-1.
3.5.9
Noise monitoring equipment used for impact monitoring is listed in
Table
3-6.
Table 3-6 Noise
Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
B&K
Type 2238 |
Calibrator |
B&K
Type 4231 |
Portable Wind Speed Indicator |
Testo
Anemometer |
3.5.10 Sound level meters listed above
comply with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications, as
recommended in TM issued under the NCO.
Water Quality
Monitoring
3.5.11 Water
quality parameters include dissolved oxygen, water
temperature & depth, turbidity, salinity, pH and stream flow velocity shall
be measured in-situ, and suspended solids shall be analyzed by a HOKLAS-accredited
testing laboratory.
Dissolved Oxygen and Temperature Measurement
3.5.12 The dissolved oxygen (DO)
measuring instruments should be portable and weatherproof. The equipment should
also complete with cable and sensor, and DC power source. It should be capable
of measuring:
• A DO level
in the range of 0 ¡V 20 mg/L and 0 ¡V 200% saturation; and
• A temperature of 0 ¡V 45 degree Celsius.
3.5.13
The
equipment should have a membrane electrode with automatic temperature
compensation complete with a cable.
3.5.14
Should
salinity compensation not be built-in to the DO equipment, in-situ salinity
should be measured to calibrate the DO measuring instruments prior to each
measurement.
Turbidity Measurement
3.5.15
The turbidity measuring instruments should be
a portable and weatherproof with DC power source. It should have a photoelectric sensor
capable of measuring turbidity level between 0¡V1000 NTU (for example, Hach
model 2100Q or an approved
similar instrument).
Salinity Measurement
3.5.16
A portable salinometer capable of measuring
salinity in the range of 0¡V40 parts per thousand (ppt) should be provided for
measuring salinity of the water at each monitoring location.
pH Measurement
3.5.17
A portable pH meter capable of measuring a
range between 0.0 and 14.0 should be provided to measure pH under the specified
conditions accordingly to the APHA Standard Methods.
Water Depth Measurement
3.5.18
A portable, battery-operated echo sounder or
an approved similar instrument should be used for water depths determination at
each designated monitoring station.
Stream Flow Velocity Equipment
3.5.19
Since the EM&A Manuals do not specified instrument to use
stream flow velocity measurement, the monitoring of stream flow velocity is
therefore proposed to be conducted by using a flow probe which is a digital
water velocity meter.
Water Sampling Equipment
3.5.20
A water sampler is required for suspended
solid (SS) monitoring. A water sampler e.g. Kahlsico
Water Sampler, which is a transparent PVC cylinder with capacity not less than
2 litres, will be used for water sampling if water depth over than 0.5m.
3.5.21
For sampling from very shallow water depths e.g. <0.5 m, water
sample will be collected from water surface below 100mm using plastic bottle to avoid
inclusion of bottom sediment or humus.
Moreover, Teflon/stainless steel bailer or self-made sampling buckets
maybe used for water sampling. The
equipment used for sampling will be depended the sampling location and depth
situations.
Sample Containers and Storage
3.5.22
Water samples for suspended solid should be
stored in high density polythene bottles with no preservative added, packed in
ice (cooled to 4¢XC without being frozen) and delivered to the laboratory within 24
hours of collection and be analyzed as soon as possible after collection.
3.5.23 Analysis of suspended solids should
be carried out in a HOKLAS or other accredited laboratory. Water samples of
about 1L should be collected at the monitoring stations for carrying out the
laboratory suspended solids determination.
The SS determination work should start within 24 hours after collection
of the water samples. The SS analyses should follow the APHA Standard Methods 2540D with Limit of Reporting of 2 mg/L.
3.5.24 Details of the equipment used for water
quality monitoring are listed in Table 3-7 below.
Table 3-7 Water
Quality Monitoring Equipment
Equipment |
Model |
Water Depth Detector |
Tape measures |
Water Sampler |
A
2-litre transparent PVC cylinder with latex cups at both ends or
teflon/stainless steel bailer or self-made sampling bucket |
Thermometer & DO meter |
YSI 550A / YSI Pro 20 |
pH meter |
AZ8685 pH meter |
Turbidimeter |
Hach
2100Q |
Salinometer |
Atago refractometer Atago S Salinity Meter /
AZ8371 Salinity Mete/ YSI Professional Plus |
Stream Flow Velocity |
FP211 Global Flow Probe |
Sample Container |
High density polythene
bottles (provided by laboratory) |
Storage Container |
¡¥Willow¡¦ 33-litter plastic
cool box with Ice pad |
3.5.25 Furthermore, Suspended solids (SS) analysis was carried out by ALS Technichem (HK) Pty Ltd, he is one a
local HOKLAS-accredited laboratory
3.6.1
The HVAS is operated and calibrated on a regular basis in
accordance with the manufacturer¡¦s instruction using Tisch Calibration Kit
Model TE-5025A. Calibration would
carry out in two month interval. The calibration data are properly
documented and the records are maintained by ET for future reference. Furthermore, Tisch Calibration Kit will be calibrated
by the manufacturer in yearly basis.
3.6.2
The 1-hour TSP meter calibrated by a local HOKLAS-accredited
laboratory would be undertaken in yearly basis. Zero response of the equipment was
checked before and after each monitoring event.
3.6.3
The sound level meter and acoustic calibrator are
calibrated and certified by a laboratory accredited under HOKLAS or any other
international accreditation scheme at yearly basis.
3.6.4
The multi-parameter Water Quality Monitoring
System is calibrated by HOKLAS accredited laboratory of three month intervals.
3.6.5
All updated calibration certificates of the
monitoring equipment used for the impact monitoring program in this Reporting
Month are attached in Appendix E.
3.7.1
The
impact monitoring data are handled by the ET¡¦s systematic data recording and
management, which complies with in-house Quality Management System. Standard
Field Data Sheets (FDS) are used in the impact monitoring program.
3.7.2
The
monitoring data recorded in the equipment e.g. 1-hour TSP meter, noise meter
and Multi-parameter Water
Quality Monitoring System are downloaded directly from the equipment at
the end of each monitoring day. The
downloaded monitoring data are input into a computerized database properly
maintained by the ET. The
laboratory results are input directly into the computerized database and QA/QC
checked by personnel other than those who input the data. For monitoring activities require
laboratory analysis, the local laboratory follows the QA/QC requirements as set
out under the HOKLAS scheme for all laboratory testing.
3.8.1
The baseline monitoring results form the basis for
determining the environmental acceptance criteria for the impact monitoring. the air quality, construction noise and
water quality criteria, namely Action and Limit levels were established according to
Approved EM&A Manual, and they are listed in Tables 3-8, 3-9 and
3-10 below.
Table 3-8 Action and Limit Levels for Air
Quality Monitoring
Monitoring Station |
Action Level (mg /m3) |
Limit Level (mg/m3) |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
|
ASR-1 |
331 |
181 |
500 |
260 |
ASR-2 |
316 |
165 |
500 |
260 |
ASR-3 |
307 |
160 |
500 |
260 |
Table 3-9 Action
and Limit Levels for Construction Noise
Monitoring Location |
Action Level |
Limit Level in dB(A) |
Time Period: 0700-1900 hours
on normal weekdays |
||
CN-1,CN-2, CN-3, CN-4 |
When
one or more documented complaints are received |
75 dB(A) |
Note: * Reduces to 70 dB(A) for schools and
65 dB(A) during the school examination periods.
Table 3-10 Action and Limit
Levels for Water Quality
Parameter |
Performance criteria |
Monitoring Location |
|||
M1 |
M2 |
M3 |
M4 |
||
DO (mg/L) |
Action Level |
3.03 |
4.99 |
4.58 |
3.62 |
Limit Level |
2.97 |
4.90 |
4.49 |
3.52 |
|
Turbidity (NTU) |
Action Level |
7.1 |
39.7 |
5.6 |
5.4 |
Limit Level |
7.6 |
42.2 |
5.9 |
5.9 |
|
SS (mg/L) |
Action Level |
8.5 |
29.0 |
9.3 |
4.8 |
Limit Level |
10.1 |
31.0 |
9.5 |
5.0 |
|
Notes: •
For DO, non-compliance of the water quality
limits occurs when monitoring result is lower than the limits •
For turbidity and SS, non-compliance of
the water quality limits occurs when monitoring result is higher than the
limits. |
3.8.2
Should
non-compliance of the environmental quality criteria occurs, remedial actions
will be triggered according to the Event and Action Plan enclosed in Appendix F.
4.1.1
In the Reporting Month, construction works under the project
have been commenced in Contract 1 and Contract 2. Air quality monitoring was performed at all
designated locations.
Air quality impact monitoring schedule was submitted to all relevant parties which shown in Appendix G.
4.1.2
In
this Reporting
Month, 15 occasions of 24-hour TSP and 45 occasions of 1-hour
TSP were
undertaken for air quality
monitoring. The air quality
monitoring results including 24-hour and 1-hour TSP are summarized in Tables 4-1 to 4-3.
The database of 24-hour TSP is shown in Appendix
H and the graphical
plots of 24-hour and 1-hour TSP result are shown in Appendix I.
Table
4-1 Summary
of Air
Quality
Monitoring Results at ASR-1 under Contract 1
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st hour measured |
2nd hour
measured |
3rd hour
measured |
||
5-Dec-18 |
86 |
6-Dec-18 |
9:09 |
41 |
43 |
46 |
11-Dec-18 |
105 |
12-Dec-18 |
9:43 |
28 |
31 |
34 |
17-Dec-18 |
86 |
18-Dec-18 |
9:16 |
87 |
90 |
81 |
22-Dec-18 |
175 |
24-Dec-18 |
9:23 |
27 |
30 |
33 |
28-Dec-18 |
98 |
29-Dec-18 |
9:13 |
74 |
86 |
88 |
Average (Range) |
110 (86
- 175) |
Average (Range) |
55 (27
¡V 90) |
Table
4-2 Summary
of Air
Quality
Monitoring Results at ASR-2 under Contract 2
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st hour
measured |
2nd hour
measured |
3rd hour
measured |
||
5-Dec-18 |
73 |
6-Dec-18 |
9:14 |
30 |
33 |
36 |
11-Dec-18 |
84 |
12-Dec-18 |
9:38 |
25 |
23 |
28 |
17-Dec-18 |
65 |
18-Dec-18 |
9:21 |
41 |
44 |
48 |
22-Dec-18 |
67 |
24-Dec-18 |
9:19 |
27 |
28 |
31 |
28-Dec-18 |
75 |
29-Dec-18 |
9:18 |
31 |
34 |
38 |
Average (Range) |
73 (65
- 84) |
Average (Range) |
33 (23
¡V 48) |
Table
4-3 Summary
of Air
Quality Monitoring
Results at ASR-3a under Contract 2
Date |
24-hour
TSP (mg/m3) |
1-hour
TSP (mg/m3) |
||||
Date |
Start Time |
1st hour
measured |
2nd hour
measured |
3rd hour
measured |
||
5-Dec-18 |
29 |
6-Dec-18 |
9:17 |
33 |
36 |
39 |
11-Dec-18 |
45 |
12-Dec-18 |
9:35 |
22 |
26 |
27 |
17-Dec-18 |
75 |
18-Dec-18 |
9:25 |
44 |
46 |
49 |
22-Dec-18 |
48 |
24-Dec-18 |
9:15 |
23 |
26 |
29 |
28-Dec-18 |
52 |
29-Dec-18 |
9:21 |
39 |
32 |
35 |
Average (Range) |
50 (29
- 75) |
Average (Range) |
34 (22
¡V 49) |
4.2.1
As
shown in Tables 4-1 to
4-3, the monitoring results of 24-hour and 1-hour TSP monitoring in the Reporting Month were well below the Action Level. No Notification of Exceedance (NOE) of air quality monitoring criteria was issued and therefore corrective action was not required. The
meteorological data during the impact monitoring days are summarized in Appendix J.
5.1.1
In the Reporting Month, construction works under the
project have been commenced in Contract 1 and Contract 2. Noise quality monitoring was performed at
designated locations CN1, CN3 and CN4. Noise
impact monitoring schedule was submitted to
all relevant parties which shown in Appendix G.
5.1.2
In
this Reporting
Month, 12 occasions of noise monitoring were
undertaken at designated noise monitoring location. The sound level were set in a free field situation for CN1 and CN3 and therefore a façade correction of +3dB(A) has been added
according to acoustical principles and EPD guidelines. Since the distance of current construction works of Contract 1 over 300m from CN-2,
noise monitoring was not performed at that
location in this Reporting Month. The monitoring result of noise monitoring is show in Tables 5-1 and 5-2 and the graphical plots are shown in Appendix
I.
Table
5-1 Summary of Construction Noise Monitoring Results under Contract 1
Construction Noise Level (Leq30min),
dB(A) |
||
Date |
Start Time |
CN1(*) |
6-Dec-18 |
10:42 |
67 |
12-Dec-18 |
14:18 |
68 |
18-Dec-18 |
9:17 |
66 |
24-Dec-18 |
9:27 |
64 |
Limit
Level |
75 dB(A) |
(*) A façade correction of +3dB(A) has been added according to
acoustical principles and EPD guidelines.
Table
5-2 Summary of Construction Noise Monitoring Results under Contract 2
Construction Noise Level (Leq30min),
dB(A) |
||||
Date |
Start Time |
CN3 (*) |
Start Time |
CN4 |
6-Dec-18 |
9:56 |
62 |
9:18 |
60 |
12-Dec-18 |
14:14 |
62 |
13:36 |
59 |
18-Dec-18 |
10:13 |
60 |
10:50 |
59 |
24-Dec-18 |
9:59 |
59 |
9:21 |
60 |
Limit
Level |
75 dB(A) |
(*) A façade correction of +3dB(A) has been added according to
acoustical principles and EPD guidelines.
5.1.3
Prior and after noise monitoring, the accuracy of the sound level meter
has been checked by
an acoustic calibrator to
ensure the measurement within acceptance range of ¡Ó0.5dB. Moreover, wind speed checked
by portable wind speed meter has
been performed before noise monitoring. No
noise measurement was performed in fog, rain, wind with a steady speed
exceeding 5 m s-1 or wind with gusts exceeding 10 m s-1.
5.2.1
As
shown in Tables 5-1 and
5-2, no noise monitoring results exceeded the Limit Level in the Reporting Month. No Notification of Exceedance (NOE) of
construction noise criterion was issued and no corrective action was therefore required.
6.1.1
Water quality impact monitoring schedule was submitted to all relevant
parties which shown in Appendix G.
6.1.2
In the Reporting
Month, a total of 13 monitoring days were
carried
out for
water quality impact monitoring. The
monitoring result
of key parameters including Dissolved Oxygen, Turbidity and Suspended Solids are summarized in Tables 6-1 and 6-2. Detailed monitoring
results including in-situ measurements and laboratory analysis data are shown
in Appendix H and graphical plots for monitoring result are shown in Appendix
I.
Table
6-1 Summary
of Water Quality Monitoring Results ¡V M3
under Contract 1
Date |
Parameters |
||
DO (Averaged) (mg/L) |
Turbidity (Averaged) (NTU) |
Suspended
Solids
(Averaged) (mg/L) |
|
4-Dec-18 |
6.28 |
4.3 |
4.0 |
6-Dec-18 |
6.75 |
3.7 |
5.0 |
8-Dec-18 |
8.11 |
3.2 |
8.0 |
11-Dec-18 |
8.63 |
2.9 |
<2 |
13-Dec-18 |
8.31 |
5.0 |
9.0 |
15-Dec-18 |
8.16 |
4.7 |
8.5 |
18-Dec-18 |
8.71 |
2.5 |
<2 |
20-Dec-18 |
8.44 |
2.6 |
<2 |
22-Dec-18 |
7.90 |
2.9 |
<2 |
24-Dec-18 |
9.38 |
1.8 |
3.5 |
27-Dec-18 |
8.27 |
3.1 |
5.0 |
29-Dec-18 |
8.72 |
1.7 |
2.0 |
31-Dec-18 |
8.66 |
3.4 |
2.5 |
Table
6-2 Summary of Water Quality Monitoring Results (M1,
M2 and M4) under Contract 2
Date |
Parameters |
||||||||
DO (Averaged) (mg/L) |
Turbidity (Averaged) (NTU) |
Suspended
Solids
(Averaged) (mg/L) |
|||||||
M1 |
M2 |
M4 |
M1 |
M2 |
M4 |
M1 |
M2 |
M4 |
|
4-Dec-18 |
7.37 |
# |
7.47 |
1.4 |
# |
1.8 |
2.0 |
# |
<2 |
6-Dec-18 |
7.91 |
# |
8.27 |
1.7 |
# |
1.0 |
2.0 |
# |
<2 |
8-Dec-18 |
8.58 |
# |
8.65 |
3.9 |
# |
2.7 |
2.0 |
# |
<2 |
11-Dec-18 |
9.12 |
# |
8.77 |
1.5 |
# |
2.0 |
2.0 |
# |
4.5 |
13-Dec-18 |
9.20 |
# |
9.12 |
1.7 |
# |
1.2 |
2.0 |
# |
<2 |
15-Dec-18 |
8.99 |
# |
8.72 |
1.9 |
# |
3.0 |
2.0 |
# |
<2 |
18-Dec-18 |
10.04 |
# |
8.75 |
1.8 |
# |
0.8 |
2.0 |
# |
<2 |
20-Dec-18 |
8.55 |
# |
8.63 |
0.8 |
# |
0.3 |
2.0 |
# |
2.0 |
22-Dec-18 |
8.26 |
# |
8.29 |
2.1 |
# |
3.7 |
2.0 |
# |
<2 |
24-Dec-18 |
8.97 |
7.32 |
8.65 |
2.5 |
5.1 |
1.2 |
2.0 |
8.0 |
4.0 |
27-Dec-18 |
7.99 |
# |
9.13 |
1.6 |
# |
3.9 |
2.0 |
# |
4.0 |
29-Dec-18 |
9.20 |
# |
9.61 |
1.6 |
# |
0.7 |
2.0 |
# |
<2 |
31-Dec-18 |
10.01 |
# |
10.46 |
1.6 |
# |
0.5 |
2.0 |
# |
<2 |
Remarks:
(#) During the water
monitoring, the channel of M2 was observed dried up and
water sampling was unable be carried out.
6.1.3
During the Reporting Month, field measurements including
temperature of stream water, salinity
concentrations, pH values and the stream
flow velocity for all monitoring locations are summarized in Table 6-3.
Table
6-3 Summary of Field Measurements for
Water Quality
Monitoring Location |
Parameters of field measurements |
|||||||
pH (unit) |
Salinity (ppt) |
Temp
(oC) |
Water Flow (m/s) |
|||||
min |
max |
min |
max |
min |
max |
min |
max |
|
M1 |
7.0 |
8.2 |
0.0 |
0.8 |
15.5 |
23.5 |
<0.1 |
0.1 |
M2 |
# |
# |
# |
# |
# |
# |
# |
# |
M3 |
6.7 |
7.2 |
0.0 |
0.0 |
15.5 |
23.5 |
<0.1 |
0.1 |
M4 |
6.7 |
8.8 |
0.0 |
0.2 |
16.0 |
23.9 |
<0.1 |
<0.1 |
Note
#: only one monitoring event was conducted at M2 due to dried up stream and no
statistical information provided.
6.2.1
In this Reporting Period, no exceedance was triggered for water quality monitoring.
The non-compliance of water quality performance is summarized in Table 6-4. The
investigation of exceedance is summarized in Table 6-5.
Table
6-4 Action and Limit (A/L) Levels Exceedance
Record
Station |
DO |
Turbidity |
SS |
Total Exceedance |
Project
Related exceedance |
|||||
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
|
M1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
M2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
M3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
M4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Table 6-5 Summary
of Investigation of Water Quality Exceedance in the Reporting Period
Date of Exceedance |
Exceeded Location |
Exceeded Parameter |
Cause of Water Quality Exceedance In
Brief |
-- |
-- |
-- |
-- |
7.1.1
According
to approved EIA report (AEIAR-198/2016), habitat types within project boundary
comprise of watercourse, grassland, upland grassland, plantation, woodland and
developed area. Natural habitats were of moderate ecological value in terms of
species diversity, species rarity, species abundance, ecological linkage as
well as nursery. Moreover, 0.3ha of wet woodland on the northern side of Sandy
Ridge was deemed habitat with high ecological value. Four types of habitats were regarded as
ecologically sensitive habitats, namely wet woodland, watercourses, upland
grassland and woodland. Considering human disturbance in upcoming construction
and operation phases, ecologically sensitive habitats shall be monitored in
accordance with EM&A Manual.
7.1.2
The objective of ecologically
sensitive habitats monitoring is to evaluate the effectiveness of measures to
minimize impacts on concerned habitats from disturbance and pollution. In order
to monitor the effectiveness of the measures to the minimize impact on
ecologically sensitive habitats from disturbance and pollution, monthly
monitoring during construction and operation phases is required as specified in
EM&A Manual. Standard faunal transect and sampling surveys cover both
wetland habitats
(wet woodland and watercourse)
and non-wetland habitats (upland
grassland and woodland).
7.2.1
Wetland
habitats include wet woodland and watercourses. Monitoring surveys using
standardized quantitative methodology will conduct at fixed points. For seasonal watercourse, the survey
will be conducted whenever the habitat appears. Measures to respond to
decreases in numbers of aquatic fauna using the wetland habitats and
Action/Limit levels to trigger these measures are detailed in Table
7-1.
Table 7-1 Action and Limit Levels for Wet Woodland Habitats
Monitoring
Action
Level |
Response |
Limit
Level |
Response |
Reduction
in taxa diversity by 30% |
Investigate
cause and if cause identified as related to the project instigate remedial
action to remove or reduce source of disturbance. |
Reduction
in taxa diversity by 50% |
Investigate
cause and if cause identified as related to the project instigate remedial
action. |
Remarks:
Action and Limit Levels and Responses to Evidence of Declines in Aquatic Fauna
7.2.2
Non-wetland
habitats consist of upland grassland and woodland. Monthly quantitative surveys
of non-aquatic fauna will be conducted using standard route transect counts. Measures to respond to decreases in
numbers of non-aquatic fauna using the non-wetland habitats and Action/Limit
levels to trigger these measures are detailed in Table 7-2.
Table 7-2 Action and Limit Levels for Non-Wet Woodland
Habitats Monitoring
Action
Level |
Response |
Limit
Level |
Response |
Reduction
in species diversity by 30% |
Investigate
cause and if cause identified as related to the project instigate remedial
action to remove or reduce source of disturbance. |
Reduction
in species diversity by 50% |
Investigate
cause and if cause identified as related to the project instigate remedial
action. |
Remarks:
Action and Limit Levels and Responses to Evidence of Declines in Non-Aquatic
Fauna
7.2.3
The ecological survey includes all taxa being
investigated in accordance with EIA report. Schedule of faunal surveys in each year
during construction phase is presented in Table 7-3.
Table 7-3 Schedule of
Faunal Surveys in each year During Construction Phase
Month |
Jan |
Feb |
Mar |
Apr |
May |
Jun |
Jul |
Aug |
Sep |
Oct |
Nov |
Dec |
Mammals |
Ö |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
Birds (day) |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
Birds (night) |
|
|
|
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
|
|
Herpetofauna |
|
|
|
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
|
|
Dragonflies |
|
|
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
|
|
Butterflies |
|
|
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
|
|
Aquatic fauna |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
¡Ô |
Mammal
Survey
7.2.4
Mammal surveys will be conducted along the proposed transects
(shown in Appendix D of the survey report) during both daytime and night time
periods. Along with direct observations, other field signs, such as scats and
tracks, will be searched and recorded if present.
Bird
Survey
7.2.5
Bird surveys will be conducted along the transects (shown in
Appendix D of the survey report) during the surveys, species and
their vocalizing individuals recorded will be enumerated and recorded according
to the habitat(s) they are utilizing.
Herpetofauna
Survey
7.2.6
Reptile and amphibian surveys will be conducted along transects
(shown in Appendix D of the survey report) during surveys careful searches of
appropriate microhabitats and refugia for reptiles and their vocalizing
individuals will be undertaken and all reptiles observed will be identified and
counted.
Dragonfly
and Butterfly Survey
7.2.7
Dragonfly and Butterfly surveys will be conducted along transects
(shown in Appendix D of the survey report) during surveys all dragonflies and
Butterflies seen will be identified and counted as accurately as possible.
Aquatic
Fauna Survey
7.2.8
Freshwater fishes and macro-invertebrates will be recorded by
direct observation. All species trapped/recorded will be enumerated and identified
(to the lowest taxonomic level possible), and the species of conservation
importance photographed.
7.2.9
After
each ecological monitoring survey, a monthly report of the survey result and
data collected will be provided with reference to EM&A Manual. An annual
analysis of data will be carried out in order to study if there is any
significant reduction in taxa diversity and abundance.
7.3.1
In the Reporting Month,
ecological monitoring was undertaken on 13th December 2018 at work area of Contract 1 and
Contract 2. The weather of
monitoring day was fine. The
monitoring survey was included day and night sections, covering wetland and
non-wetland areas. The survey was
conducted by transect and fixed points.
All species seen will be identified and counted as accurately as
possible. Results of the monitoring
survey are presented below:
Monitoring
Result for Contract 1
Mammal
7.3.2
There was no
mammal recorded in the monitoring area
Birds
7.3.3
There were a total
of 60 bird individuals from 10 species recorded during the survey.
Herpetofauna
7.3.4
There were no
reptiles recorded in the monitoring area.
There was no amphibian recorded in the monitoring area.
Dragonfly
7.3.5
There
was no odonate individual in the monitoring area.
Butterfly
7.3.6
There
was no butterfly individual in the monitoring area.
Aquatic Fauna Survey (Freshwater
communities)
7.3.7
There
were no freshwater community recorded in the monitoring area.
7.3.8
The summaries
of faunal survey result are shown in Tables 7-4, 7-5, 7-6, 7-8 and 7-9.
Table 7-4 Result
of Avifauna Survey under Contract 1
Scientific Name |
English Name |
Chinese Name |
Conservation Status |
Non- wetland |
Wetland |
Ardea
cinerea |
Grey Heron |
»aÆO |
Fellowes et al. (2002): PRC |
|
1 |
Milvus
migrans |
Black Kite |
¶Â»ð |
Fellowes et al. (2002): RC; Appendix 2 of CITES |
1 |
|
Parus
cinereus |
Cinereous Tit |
»aI¤s³¶ |
|
|
1 |
Phylloscopus
fuscatus |
Dusky Warbler |
½Å¬hÅa |
|
2 |
|
Phylloscopus
inornatus |
Yellow-browed Warbler
|
¶À¬Ü¬hÅa |
|
|
1 |
Prinia
flaviventris |
Yellow-bellied
Prinia |
¶À¸¡økÅa |
|
3 |
1 |
Garrulax
perspicillatus |
Masked
Laughingthrush |
¶ÂÁy¾¸鶥 |
|
4 |
|
Zosterops
japonicus |
Japanese
White-eye |
·tºñ¸²´³¾ |
|
30 |
12 |
Acridotheres
cristatellus |
Crested Myna |
¤Kô |
|
3 |
|
Phoenicurus
auroreus |
Daurian
Redstart |
¥_¬õ§Àì© |
|
1 |
|
Table 7-5 Result
of Reptile Survey under Contract 1
Scientific
Name |
Common Name |
Chinese
Name |
Non-wetland |
Wetland |
-- |
-- |
-- |
-- |
-- |
Table 7-6 Result
of Amphibian Survey under Contract 1
Scientific
Name |
Common Name |
Chinese
Name |
Conservation
Status |
Non- wetland |
Wetland |
-- |
-- |
-- |
-- |
-- |
-- |
Table 7-7 Result
of Butterfly Survey under Contract 1
Scientific Name |
Common Name |
Chinese Name |
Non- wetland |
Wetland |
-- |
-- |
-- |
-- |
-- |
Table 7-8 Result
of Odonate Survey under Contract 1
Scientific
Name |
Common Name |
Chinese
Name |
Conservation
Status |
Non- wetland |
Wetland |
-- |
-- |
-- |
-- |
-- |
-- |
Table 7-9 Result
of Freshwater Communities Survey under Contract 1
Scientific
Name |
Common Name |
Chinese
Name |
Conservation
Status |
13-Dec-18 |
-- |
-- |
-- |
-- |
-- |
Monitoring
Result for Contract 2
Mammal
7.3.9
There was no mammal
recorded in the monitoring area
Birds
7.3.10 There were a total of 31 bird individuals from 13 species recorded
during the survey.
Herpetofauna
7.3.11 There were no reptiles recorded in the monitoring area. There was no amphibian
recorded in the monitoring
area.
Dragonfly
7.3.12 There was a total of 1 odonate individuals from 1 species.
Butterfly
7.3.13 There were a total of 2 butterfly individuals from 2 species recorded.
Aquatic Fauna Survey (Freshwater
communities)
7.3.14 There were two species of freshwater fish were recorded.
7.3.15 The summaries of faunal survey result are shown in Tables 7-10, 7-11, 7-12, 7-13 and 7-14.
Table 7-10 Result
of Avifauna Survey under Contract 2
Scientific Name |
English Name |
Chinese Name |
Conservation Status |
Non- wetland |
Wetland |
Spilopelia
chinensis |
Spotted Dove |
¯]ÀV´³¹§ |
|
|
1 |
Lanius
schach |
Long-tailed
Shrike |
´ÄI§B³Ò |
|
1 |
|
Pycnonotus
jocosus |
Red-whiskered
Bulbul |
¬õ¦Õóí |
|
1 |
|
Pycnonotus
sinensis |
Chinese Bulbul
|
¥ÕÀYóí |
|
3 |
|
Pycnonotus
aurigaster |
Sooty-headed
Bulbul |
¥Õ³ï¬õÁvóí |
|
2 |
|
Phylloscopus
inornatus |
Yellow-browed
Warbler |
¶À¬Ü¬hÅa |
|
1 |
|
Orthotomus
sutorius |
Common
Tailorbird |
ªø§ÀÁ_¸Åa |
|
1 |
|
Zosterops
japonicus |
Japanese
White-eye |
·tºñ¸²´³¾ |
|
15 |
|
Turdus
hortulorum |
Grey-backed
Thrush |
¦ÇIóð |
|
1 |
|
Phoenicurus
auroreus |
Daurian
Redstart |
¥_¬õ§Àì© |
|
2 |
|
Aethopyga
christinae |
Fork-tailed
Sunbird |
¤e§À¤Ó¶§³¾ |
|
1 |
|
Motacilla
alba |
White Wagtail |
¥ÕöÀÀo |
|
|
1 |
Anthus
godlewskii |
Olive-backed
Pipit |
¾ð÷º |
|
1 |
|
Table 7-11 Result
of Reptile Survey under Contract 2
Scientific
Name |
Common Name |
Chinese
Name |
Non-wetland |
Wetland |
-- |
-- |
-- |
-- |
-- |
Table 7-12 Result
of Amphibian Survey under Contract 2
Scientific
Name |
Common Name |
Chinese
Name |
Conservation
Status |
Non- wetland |
Wetland |
-- |
-- |
-- |
-- |
-- |
-- |
Table 7-13 Result
of Butterfly Survey under Contract 2
Scientific
Name |
Common Name |
Chinese
Name |
Non- wetland |
Wetland |
Abisara
echerius echerius |
Plum Judy |
³D¥Ø½Å¸Ã½º |
1 |
|
Delias
pasithoe pasithoe, Delias aglaja alaja (Linnaeus) |
Red-base
Jezebel, Common Black Jezebel |
³ø³ß´³¯»½º |
1 |
|
Table 7-14 Result
of Odonate Survey under Contract 2
Scientific
Name |
Common Name |
Chinese
Name |
Conservation
Status |
Non- wetland |
Wetland |
Orthetrum
sabina sabina |
Green Skimmer |
¯U¸¡¦Ç»f |
|
1 |
|
Table 7-15 Result
of Freshwater Communities Survey under Contract 2
Scientific Name |
Common Name |
Chinese Name |
Conservation Status |
15-Nov-18 |
Gambusia
affinis |
Mosquito fish |
¹°A³½ |
|
+ |
Puntius
semifasciolatus |
Chinese Barb |
¤½uµLŽ䰾 |
|
+ |
+: Species appeared but uncountable.
7.3.1
The
detailed survey report is attached in Appendix K.
7.3.2
The tentative ecology inspection and monitoring in the next
reporting period (January 2019) is scheduled on 15th January 2019.
8.1.1
The EIA has recommended EM&A for landscape and visual
resources to be undertaken during the design, construction and operational
stages of the project. The design, implementation and maintenance of landscape
mitigation measures is a key aspect of this and should be checked to ensure
that they are fully realized and that potential conflicts between the proposed
landscape measures and any other project works let its are resolved at the
earliest possible date and without compromise to the intention of the
mitigation measures. In addition, implementation of the mitigation measures
recommended by the EIA will be monitored through the site audit programme.
8.1.2
A number of mitigation measures to ameliorate the landscape and
visual impacts of the Project implementation is summarized in the EMIS of Appendix
13.1 of the EIA Report.
8.1.3
The landscape and visual
mitigation measures proposed should be incorporated in the landscape and
engineering design. Mitigation
measures to be implemented during construction should be adopted from the start
of construction and be in place throughout the entire construction period. Mitigation measures to be implemented
during operation should be integrated into the detailed design and built as
part of the construction works so that they are in place on commissioning of
the Project. Tree transplantation
and compensatory planting should be carried out as early as possible in the
Project with transplantation carried
out prior to construction starting in any particular area.
8.1.4
During
construction phase, Landscape & Visual Monitoring of the contractor¡¦s operations should be conducted monthly and
reported by ET, and countersigned by IEC.
8.2.1
In the Reporting Period, landscape & Visual inspection was
carried out by the Registered Landscape Architect (RLA) for works area of Contract 1 and
Contract 2 on 28th December 2018. The findings / reminders recorded
during the inspection are presented in Tables 8-1 and 8-2.
Table 8-1 Landscape
& Visual Inspection Finding for Contract 1
Date |
Findings and Reminder |
28th
December 2018 |
The Contractor was reminded to
prevent the construction material pile within Tree Protection Zone (TPZ) and
ensure no works is allowed with the TPZ. |
Table 8-2 Landscape
& Visual Inspection Finding for Contract 2
Date |
Findings and Reminder |
28th
December 2018 |
No adverse observation. |
8.2.2
Inspection checklist of Landscape & Visual signed by RLA is attached in Appendix L.
9.1.1
Waste management was carried out by an on-site Environmental
Officer or an Environmental Supervisor from time to time in accordance with the
Waste Management Plan (WMP).
9.2.1
All
types of waste arising from the construction work are classified into the
following:
l Construction & Demolition (C&D)
Material;
l Chemical Waste;
l General Refuse; and
l Excavated Soil.
9.2.2
The
quantities of waste for disposal in this Reporting Period are summarized in Table 9-1 and 9-2 and
the Monthly Summary Waste Flow Table is shown in
Appendix M. Whenever possible, materials were reused
on-site as far as practicable.
Table
9-1 Summary of Quantities of Inert C&D
Materials
Type of Waste |
Contract 1 |
Contract 2 |
||
Quantity |
Disposal Location |
Quantity |
Disposal Location |
|
C&D
Materials (Inert) (m3) |
0 |
-- |
0 |
-- |
Reused
in this Contract (Inert) (m3) |
3.528 |
Within Contract area |
0 |
-- |
Reused
in other Projects (Inert) (m3) |
0 |
-- |
0 |
-- |
Disposal
as Public Fill (Inert) (m3) |
35.793 |
Tuen Mun Area 38 |
0 |
-- |
Table 9-2 Summary
of Quantities of C&D Wastes
Type of Waste |
Contract 1 |
Contract 2 |
||
Quantity |
Disposal Location |
Quantity |
Disposal Location |
|
Recycled
Metal (kg) |
0 |
-- |
0 |
-- |
Recycled Paper / Cardboard Packing (kg) |
0 |
-- |
0 |
-- |
Recycled Plastic (kg) |
0 |
-- |
0 |
-- |
Chemical Wastes (kg) |
0 |
-- |
0 |
-- |
General Refuses (m3) |
0.077 |
NENT Landfill |
0 |
-- |
9.2.3
Since
canteen and/or kitchen are not allowed setting on the Project site,
no domestic wastewater was
generated from the Project.
10.1.1
According
to the approved Environmental Monitoring and Audit Manual, environmental site
inspection should be led by RE and attended by the Contractor and ET at
least once per week. Regular environmental site inspections shall
be carried out to assess the environmental performance.
Contract 1
In the Reporting Period, joint site inspections for Contract 1 to evaluate the site environmental performance carried out by the
RE, ET and the Contractor was on 6th, 13th, 20th
and 27th December 2018. Moreover, IEC attended a joint
site inspection on 13th
December 2018. No non-compliance was noted.
10.2.1
The findings / deficiencies that observed during the weekly site
inspection are listed in Table 10-1.
Table 10-1 Site Observations
for the Works of Contract-1
Date |
Findings / Deficiencies |
Follow-Up Status |
6th December 2018 |
Generator without drip tray was observed. The Contractor should place
generator inside drip tray to avoid any chemical leakage on ground. |
The generator was removed from site. |
The Contractor was reminded to dispose empty cement bags regularly. |
Not required for reminder. |
|
The Contractor was reminded to spray water regularly on exposed work
area regularly. |
Not required for reminder. |
|
The Contractor was reminded to provide mitigation measure to avoid
accumulation of sludge at U-channel next to site entrance. |
Not required for reminder. |
|
13th December 2018 |
Stagnant water was observed at drip tray under generator.
The Contractor should remove the stagnant water to prevent mosquito breeding. |
The stagnant water at drip tray under generator was
removed. |
The
Contractor should repair the broken part of the earth bund to direct any
surface run-off for treatment prior discharge. |
The earth bund has been repaired. |
|
The Contractor was reminded to improve the housekeeping of the
construction site. |
Not required for reminder. |
|
20th December 2018 |
The Contractor was reminded to provide water spraying at site area
regularly. |
Not required for reminder. |
The Contractor was reminded to ensure all the wastewater generated are
properly treated prior discharge. |
Not required for reminder. |
|
27th December 2018 |
Chemical containers without drip tray was observed. The Contractor
should place the containers into drip tray to avoid leakage on ground. |
To be followed. |
The Contractor was reminded to provide proper shelter for grout mixer during
the mixing process at CS11. |
Not required for reminder. |
Contract 2
10.2.2
In view of the major construction activities of Contract 2 have not yet commenced
in early December 2018, the 1st site inspection was arranged on 10 December
2018 which attended by CEDD, RE, IEC, Contractor and ET. In the
Reporting Period, joint site inspections for Contract 2 to evaluate the site environmental performance carried out by the
RE, ET and the Contractor was on 10th, 20th and 27th
December 2018. Moreover, IEC attended a joint
site inspection on 10th
December 2018. No non-compliance was noted.
10.2.3
The findings / deficiencies that observed during the weekly site
inspection are listed in Table 10-2.
Table 10-2 Site
Observations for the Works of Contract-1
Date |
Findings / Deficiencies |
Follow-Up Status |
10th
December 2018 |
Stockpile of construction materials
without dust mitigation measures was observed. The Contractor should wet the exposed stockpile
and cover the stockpile with
impervious sheeting to
minimize dust impact. |
Stockpile of construction materials was covered with impervious sheet. |
Muddy trail was observed at site exit and there
was no proper wheel washing facilities provided. The
Contractor should provide wheel washing facility and ensure wheel washing was
performed for all vehicles before leaving the site. Moreover, the Contractor was reminded
to maintain the site exit cleanliness. |
Muddy trail at the public road was cleaned and hose for vehicle washing
were provided. |
|
Chemical container without chemical label
and drip tray were observed. The
Contractor should provide proper label for chemical container with drip tray
underneath to prevent land contamination. |
Chemical container was removed from site. |
|
A tree to be transplanted (T2769) at site
boundary without proper protection was observed and some wastes were stacked nearby.
The Contractor should maintain a tree protection zone to prevent the tree
damage from works. Moreover, site cleaning for C&D waste should be
performed regularly. |
A tree protected zone was maintain properly. |
|
The Contractor was reminded to display
the Environmental Permit at all vehicle site entrances/exits |
Not required for reminder. |
|
It was
reminded that dust mitigation measures shall be
implemented in accordance with EMIS stipulation to suppress construction dust
and reduce impact on surrounding environment. |
Not required for reminder. |
|
20th
December 2018 |
Muddy trial was observed at site entrance
of TTA1 and TTA2. The Contractor should ensure all the vehicles are properly
washed before leaving the site. |
Muddy trail at the public road was
cleaned and hose for vehicle washing were provided at site entrance of TTA1
and TTA2. |
C&D waste was removed near the tree
to be transplanted (T2769). However, the Contractor should maintain a tree
protection zone to prevent the tree damage from works. |
Tree protection was provided for the tree
to be transplanted (T2769) at TTA2. |
|
27th
December 2018 |
NRMM label was not observed for the
excavator at TTA2. The Contractor should display the NRMM label in accordance
to the NRMM regulation. |
NRMM label was not required for the
excavator at TTA2 after checked |
The Contractor should check whether NRMM
label is required for the generator at CS22 and display the NRMM label if
necessary. |
NRMM label was not required for the
generator as CS22 after checked |
11.1.1
In
the Reporting Month,
no
environmental complaint was
received for the Project. No summons and prosecution
was lodged for the Contract.
The
statistical summary table of the environmental complaint, summons and
prosecution are presented in Tables 11-1, 11-2 and 11-3.
Table
11-1 Statistical
Summary of Environmental Complaints
Reporting Period |
Environmental Complaint Statistics |
|||
Frequency |
Cumulative |
Complaint Nature |
||
1 ¡V 31 Dec 2018 |
Contract 1 |
0 |
0 |
NA |
1 ¡V 31 Dec 2018 |
Contract 2 |
0 |
0 |
NA |
Table 11-2 Statistical
Summary of Environmental Summons
Reporting Period |
Environmental Summons Statistics |
|||
Frequency |
Cumulative |
Complaint Nature |
||
1 ¡V 31 Dec 2018 |
Contract 1 |
0 |
0 |
NA |
1 ¡V 31 Dec 2018 |
Contract 2 |
0 |
0 |
NA |
Table 11-3 Statistical
Summary of Environmental Prosecution
Reporting Period |
Environmental Prosecution
Statistics |
|||
Frequency |
Cumulative |
Complaint Nature |
||
1 ¡V 31 Dec 2018 |
Contract 1 |
0 |
0 |
NA |
1 ¡V 31 Dec 2018 |
Contract 2 |
0 |
0 |
NA |
11.1.2
In addition, no complaints received and emergency events
relating to violation of environmental legislation for illegal dumping and landfilling
were received.
12.1.1
The environmental mitigation measures that recommended in the Implementation
Schedule for Environmental Mitigation Measures (ISEMM) in the approved EM&A
Manual covered the issues of dust, noise, water and waste and they are
summarized presented in Appendix N.
12.1.2
The Works of Contract 1
and Contract 2 under the Project shall be
implementing the required environmental mitigation measures according to the
approved EM&A Manual subject to the site condition. Environmental mitigation measures implemented
in this Reporting Month is summarized in Table 12-1.
Table 12-1 Environmental
Mitigation Measures
Issues |
Environmental Mitigation Measures |
Water
Quality |
¡P
Provided efficient silt removal facilities to reduce SS level before effluent
discharge. ¡P
Provided ditches, earth bunds or sand bag
barriers to minimize polluted runoff. ¡P
Temporary drainage was provided
to prevent runoff going through site
surface and minimize polluted runoff. ¡P
Provided perimeter cut-off drains at site
boundaries to intercept storm runoff from crossing the site. ¡P
Exposed slopes surface were compacted and covered with tarpaulin or similar means ¡P
Provided portable chemical toilets on site. |
Air
Quality |
¡P
Maintain damp /
wet surface on access road. ¡P
Maintain low vehicular speed within the works areas. ¡P
Provided vehicle wheel washing facilities at each
construction site exit; ¡P
Provided water spraying for all active works area. ¡P
Stockpiles
of dusty material were covered
with impervious sheeting. ¡P
Provided workers to clear dusty materials at the vehicle
entrance or exit regularly. ¡P
Stockpile more
than 20 bags of cement or dry pulverized fuel ash (PFA) has been covered entirely by impervious sheeting or placed in
an area sheltered on the top and the 3 sides. |
Noise |
¡P
Restricted operation time of plants from 07:00 to 19:00 on any
working day except for Public Holiday and Sunday. ¡P
Keep good
maintenance of plants ¡P
Placed noisy plants away from residence and school ¡P
Provided noise barriers or hoarding to enclose the noisy
plants or works ¡P
Shut down the
plants when not in used. |
Waste
and Chemical Management |
¡P
Provided on-site sorting prior to disposal ¡P
Followed requirements and procedures of the ¡§Trip-ticket
System¡¨ ¡P
Predicted required quantity of concrete accurately ¡P
Collected the unused fresh concrete at designated
locations in the sites for subsequent disposal |
General |
¡P
The site was
generally kept tidy and clean. |
12.2.1 According to the information provided by HCTYJV, the
forthcoming construction activities for Contract 1
are listed below:
(i)
General
Site Clearance
(ii)
Bulk
Excavation
(iii)
Construction
of Cut Slope, installation of soil nailing and construction of surface channel.
(iv)
Construction
of retaining wall
(v)
Construction
of fill
slope
12.2.2 According to the information provided by Sang
Hing, the forthcoming construction activities for Contract 2
are listed below:
Tree Survey at Part C1, C2, A1 and A3
Site Patrol and daily cleaning within the
site boundary including the anti-mosquito measures.
Site preparation of PM¡¦s Office
Utilities Detection and trial pit
excavation along Lin Ma Hang Road and Man Kam To Road.
Liaison with Contract 1 Contractor
regarding the access road
Construction of Manhole, gullies, drainage
pipe at Lin Ma Hang Road between CH240-280 & CH1015-1075 Southbound.
Construction of Temporary haul road at Part
A1
Construction of soil nail at slope CS22
(Part A1)
12.3.1
Key
issues to be considered in the coming month for the works of Contract 1 include:
Implementation of control measures for
rainstorm;
Regular clearance of stagnant water during
wet season;
Implementation of dust suppression measures
at all times;
Potential wastewater quality impact due to
surface runoff;
Potential fugitive dust quality impact due
from the dry/loose/exposure soil surface/dusty material;
Ensure dust suppression measures are
implemented properly;
Sediment catch-pits and silt removal
facilities should be regularly maintained;
Discharge of site effluent to the nearby
wetland is prohibited;
Nearby wetland prohibited stockpiling
and/or disposal of materials;
Follow-up of improvement on general waste
management issues; and
Implementation of construction noise
preventative control measures.
13.1.1
This
is the 5th monthly
Environmental Monitoring and Audit Report presenting the monitoring results and
inspection findings for the period of 1 to 31 December 2018.
13.1.2
No
24-hour or 1-hour TSP monitoring result that triggered the Action or Limit
Levels was
recorded. No NOEs or the associated corrective action was
therefore required.
13.1.3
No
noise complaint (which is an Action Level exceedance) was received and no
construction noise measurement result that exceeded the Limit Level was recorded in this Reporting Month. No NOEs or the associated corrective actions were therefore issued.
13.1.4
For water quality monitoring, no exceedance was triggered in the Reporting
Month.
13.1.5
Monthly ecological
monitoring for
sensitive habitat for area of Contract 1 and Contract 2 were undertaken on 13th
December 2018. Moreover, Landscape and visual inspection at both Contracts were undertaken by the RLA on 22nd
December 2018.
13.1.6
In the Reporting Period, no environmental complaint, summons and prosecution was received. In addition, no complaints received and emergency events relating to
violation of environmental legislation for illegal dumping and landfilling
were received.
13.1.7
In the Reporting Period, joint site inspections for Contract 1 to evaluate the site environmental performance were carried out by the RE, ET and the Contractor on 6th, 13th, 20th and 27th
December 2018 and IEC attended joint site inspection on 13th
December 2018. No non-compliance
was noted.
13.1.8
Joint site inspections for Contract 2 to evaluate the site environmental performance carried out by the
RE, ET and the Contractor was on 10th, 20th and 27th
December 2018 and
IEC attended joint site inspection on 10th December 2018. No
non-compliance was noted.
13.2.1
The Contractors should pay special
attention on water quality mitigation measures and fully implement according
to the ISEMM of the EM&A Manual, in particular to prevent surface
runoff with high SS content and other pollutants from flowing to local steam
and Conservation Area (CA).
13.2.2
Construction
noise would be a key environmental issue during construction phase of the Project. Noise mitigation measures such as using
quiet plants and mobile noise barriers should be implemented in accordance with
the EM&A requirement.
13.2.3
Since
construction site under the Works of Contract 1 of the Project is located near villages, HCTYJV should
fully implement air quality mitigation measures to reduce construction dust
emission.
13.2.4
Furthermore,
daily cleaning and weekly tidiness shall be properly performed and maintained.
In addition, mosquito control should be
performed to prevent mosquito breeding on site.