Job No.: TCS00881/18

 

 

 

 

 

 

 

 

 

CEDD Contract CV/2016/10

Site Formation and Associated Infrastructural Works for Development of Columbarium at Sandy Ridge Cemetery

 

 

 

 

 

 

 

 

 

Monthly Environmental Monitoring and Audit Report (No.1) ¡V August 2018

 

 

 

 

 

 

 

 

Prepared For

 

 

 

 

Hsin Chong Tsun Yip Joint Venture

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

18 September 2018

TCS00881/18/600/R0114v3

Nicola Hon

(Environmental Consultant)

Tam Tak Wing

(Environmental Team Leader)

 

Version

Date

Remarks

1

10 September 2018

First Submission

2

14 September 2018

Amended according to the IEC¡¦s comment on 13 September 2018

3

18 September 2018

Amended according to the IEC¡¦s comment on 15 September 2018

 

 

 

 

 

 


 

Verification for EMA Rpt Aug 2018_v4 (3)

 

 

executive summary

ES.01.        Civil Engineering and Development Department (hereafter referred as ¡§CEDD¡¨) is the Project Proponent for the Project ¡§Site Formation and Associated Infrastructural Works for Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge Cemetery¡¨ (hereafter referred as ¡§the Project¡¨).  The Project is a Designated Project to be implemented under Environmental Permit No. EP-534/2017.  To facilitate the Project management, the Project works were separated into three different Contracts and they are listed below.

Ÿ   CEDD Contract No. CV/2016/10 - Site Formation and Associated Infrastructural Works for Development of Columbarium at Sandy Ridge Cemetery (hereafter referred as ¡§Contract 1¡¨)

Ÿ   CEDD Contract No. CV/2017/02 - Infrastructural Works at Man Kam To Road and Lin Ma Hang Road for Development of Columbarium at Sandy Ridge Cemetery (hereafter referred as ¡§Contract 2¡¨)

Ÿ   Other CEDD¡¦s Contract as related Development of Columbarium at Sandy Ridge Cemetery (hereafter referred as ¡§Contract 3¡¨)

 

ES.02.        Hsin Chong Tsun Yip Joint Venture (hereafter referred as ¡§HCTYJV¡¨) has been awarded the CEDD Contract No. CV/2016/10 ¡§Site Formation and Associated Infrastructural Works for Development of Columbarium at Sandy Ridge Cemetery¡¨ on 5 December 2017.  According to the Contract requirement, HCTYJV shall take over the responsibility for part of the Environmental Permit No. EP-534/2017 for ease of management, therefore application for Further Environmental Permit was submitted by HCTYJV to EPD on 26 January 2018 and Further Environmental Permit No. FEP-01/534/2017 was granted to HCTYJV by EPD on 23 February 2018.    

 

ES.03.        Action-United Environmental Services & Consulting (hereinafter referred as ¡§AUES¡¨) has been commissioned by HCTYJV as an Environmental Team (hereinafter referred as ¡§the ET¡¨) to implement the Environmental Monitoring & Audit (EM&A) programme in accordance with the approved EM&A Manual as well as the associated duties.

 

ES.04.        According to the Further Environmental Permit (FEP-01/534/2017) and Environmental Permit (EP-534/2017) Condition 3.3, Baseline Monitoring Report shall be deposited to EPD at least one month before commencement of the construction of the Project.  The coverage of baseline monitoring includes the whole site boundary of EP-534/2017.  Baseline monitoring for air quality was conducted from 25 April 2018 to 9 May 2018 and baseline noise monitoring was conducted from 25 April 2018 to 8 May 2018.  Due to accessibility to the monitoring point, baseline water quality monitoring was conducted from 27 April 2018 to 23 May 2018 for Locations M1, M3 and M4.  Baseline Monitoring Report (ver.1) which verified by Independent Environmental Checker (IEC) was submitted to Environmental Protection Department (EPD) on 30 May 2018.  Upon receipt comment from EPD, baseline water quality monitoring at M2 was carried out from 12 July 2018 to 6 August 2018 upon the access was available.  Baseline Monitoring Report (ver.2) was submitted to EPD on 8 August 2018 before commencement of construction activities of the Contract. Further comment was issued by EPD on 15 August 2018 and the Baseline Monitoring Report (Version 3) was submitted to EPD on 13 September 2018 for endorsement.

 

ES.05.        The Baseline Monitoring Report (air, noise and water) has summarized the key findings and the rationale behind determining a set of Action and Limit Levels (A/L Levels) from the baseline data.  As notified by HCTYJV, construction works of the Contract 1 was commenced on 16 August 2018 and therefore construction phase impact monitoring was started on 16 August 2018.

 

ES.06.        The baseline monitoring results form the basis for determining the environmental acceptance criteria for the impact monitoring. The air quality, construction noise and water quality criteria, namely Action and Limit levels were established according to Approved EM&A Manual and they are given in Tables ES-1, ES-2 and ES-3 below.

 

Table ES-1      Action and Limit Levels of Air Quality Monitoring

Monitoring Stations

Action Level (mg/m3)

Limit Level (mg/m3)

1-hour

24-hour

1-hour

24-hour

ASR-1

331

181

500

260

ASR-2

316

165

500

260

ASR-3

307

160

500

260

 

Table ES-2      Action and Limit Levels of Construction Noise Monitoring

Monitoring Location

Action Level

Limit Level

Time Period: 0700-1900 hours on normal weekdays

CN-1,CN-2, CN-3, CN-4

When one or more documented complaints are received

75 dB(A)

Note 1:  If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the NCA have to be followed.

 

Table ES-3        Action and Limit Levels of Water Quality Monitoring

Parameter

Performance criteria

Monitoring Location

M1

M2

M3

M4

DO (mg/L)

Action Level

3.03

4.99

4.58

3.62

Limit Level

2.97

4.90

4.49

3.52

Turbidity (NTU)

Action Level

7.1

39.7

5.6

5.4

Limit Level

7.6

42.2

5.9

5.9

SS (mg/L)

Action Level

8.5

29.0

9.3

4.8

Limit Level

10.1

31.0

9.5

5.0

 

ES.07.        In case where exceedance of these environmental criteria occurs, actions should be carried out in accordance with the ¡§Event Action Plan¡¨ in the Approved EM&A Manual.

 

ES.08.        This is the 1st monthly Environmental Monitoring and Audit Report presenting the monitoring results and inspection findings for the period of 16th to 31st August 2018 (the Reporting Month).

 

Environmental Monitoring and Audit Activities

ES.09.        Environmental monitoring activities under the EM&A program in this Reporting Month is summarized in the following table.

Table ES-4        Environmental monitoring activities in the Reporting Period

Issues

Environmental Monitoring Parameters / Inspection

Monitoring Location under CV/2016/10

Occasions

Air Quality

1-hour TSP

ASR-1

3

24-hour TSP

ASR-1

3

Construction Noise

Leq (30min) Daytime

CN-1

3

Water Quality

In-situ measurement and Water sampling

M3

7

Ecology

Monthly Monitoring

Transect within site area of CV/2016/10

1*

Landscape & Visual

Monthly Site Inspection

Site area of CV/2016/10

1

Inspection / Audit

ET Regular Environmental Site Inspection

Site area of CV/2016/10

3

IEC Monthly Environmental Site Audit

Site area of CV/2016/10

1

* Pre-survey was undertaken on 7th August 2018

 

Breach of Action and Limit (A/L) Levels

ES.010.    No exceedance of air quality and construction noise monitoring was recorded in this Reporting Month.  However, for water quality monitoring, a total of twelve (12) Limit Level exceedances were recorded.  Notification of Exceedance (NOE) of water quality was therefore issued.  The statistics of environmental exceedance, NOE issued and investigation of exceedance are summarized in the following table.

Table ES-5        Breach of Action and Limit (A/L) Levels in the Reporting Period

Environmental Issues

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation findings

Corrective Actions

Air Quality

1-hour TSP

0

0

0

-

-

24-hour TSP

0

0

0

-

-

Construction Noise

Leq30min Daytime

0

0

0

-

-

Water Quality

DO

0

0

0

-

-

Turbidity

7

7

7

Not related to the Contract Works

NA

SS

0

5

5

Not related to the Contract Works

NA

Note:      NOE ¡V Notification of Exceedance

 

ES.011.    Investigation for the cause of water quality exceedances have been undertaken by ET.  Investigation results revealed that the construction activities undertaken by Contract 1 were limited since contract works commencement on 16 August 2018.  As water quality mitigation measures, wastewater treatment facilities have been implemented and exposed surface have been covered by cement motar as far as practicable to minimize generation of muddy runoff during rain.  In addition, construction of temporary drainage system was on-going.  Nevertheless, except for 24th and 25th August 2018, there were continuous heavy rainstorms since the contract commencement.  It is considered that the exceedances were related to the rainstorm and unlikely caused by the works under the Contract 1.

 

Environmental Complaint

ES.012.    No environmental complaint was recorded or received in this Reporting Month.  The statistics of environmental complaint are summarized in the following table.

Table ES-6        Environmental Complaint Summaries in the Reporting Month

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

16 ¡V 31 August 2018

0

0

NA

 

ES.013.    In addition, no complaints received and emergency events relating to violation of environmental legislation for illegal dumping and landfilling were received. 

 

Notification of Summons and Successful Prosecutions

ES.014.    No environmental summons or successful prosecution was recorded in this Reporting Month.  The statistics of summons or successful prosecutions are summarized in the following tables.

Table ES-7        Environmental Summons Summaries in the Reporting Month

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Complaint Nature

16 ¡V 31 August 2018

0

0

NA

 

Table ES-8        Environmental Prosecution Summaries in the Reporting Month

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Complaint Nature

16 ¡V 31 August 2018

0

0

NA